Southwest Idaho highway construction report for Jan. 4-11

BOISE - The following projects in southwest Idaho are now under way.

ADA COUNTY
BOISE - Idaho 16 Extension, Boise River Crossing plus Phyllis Canal Bridge replacement and South Segment

Work is under way on the extension of Idaho 16, which will be complete in late summer 2014.  

Crews will connect State Street (Idaho 44) to Chinden Boulevard, including a new 1726-foot bridge over the Boise River.  Idaho 16 is also being extended from U.S. 20/26 (at McDermott Road) to Joplin Road, where it ties in to the new Idaho 16 Boise River Bridge project.

For the next several weeks, new concrete girders for the bridge will be delivered to the job site. There are 11 spans between the abutments and piers on the new bridge. Each span requires 11 girders - a total of 121.

Each girder averages close to 155 feet in length.  No deliveries are allowed from 6 a.m.-8:30 a.m. and 4 p.m.-6:30 p.m., Monday through Friday. Law enforcement agencies in Ada and Canyon counties have been notified. 

Crews will also continue driving steel piling for the south abutment of the new 1,726-foot-long bridge.  They will continue forming and placing concrete for various pier footings, columns and pier caps.

The contractor has completed placement of the walls and three of four wing walls for the Phyllis Canal Bridge. They will continue forming and placing concrete for the wing walls and will be forming the beam seats for the pre-stressed voided slab girders for the bridge. Crews began girder delivery for the Phyllis Canal Bridge Wednesday (Jan. 3). There are no special delivery restrictions for the girders, because they are considerably smaller than those needed for the Boise River Bridge.

Concrete Placing Co. Inc., of Boise, is the contractor for both the first segment, which is the $19.4 million construction of the river crossing, as well as for the second segment, which includes the $10.8 million work to the south and a crossing of the Phyllis Canal Bridge.

ADA COUNTY
MERIDIAN - Eagle Road resurfacing and medians

Work is in winter shut-down mode on this project, which resurfaced Idaho 55 from Fairview Avenue in Meridian to State Street in Eagle, and installed raised medians from Franklin to Oakhampton Drive, one-half mile north of Chinden Boulevard. Crews began the work in early summer.

There will be limited construction activity during winter weather. ?Over the next few months, crews will:
- Finish placing sidewalks and landscaping at the Chinden and Eagle intersection
- Place a final coat of striping along the entire roadway from Franklin Road to Idaho 44
- Begin to place medians on Chinden Boulevard, east of Eagle Road
In late winter/early spring, ITD plans to place a signal at the intersection of Wainwright Street and Eagle Road.

Idaho Sand & Gravel Co., of Nampa, is the contractor on this $4.7 million project.

ADA COUNTY
State St./Linder Rd./Ballantyne Lane intersection work

The project will ultimately reconstruct the intersection of Idaho 44 and Linder, including the reconstruction and expansion of Idaho 44 between Linder and Ballantyne and the rebuilding of Linder in the vicinity of Idaho 44.

Crews will be installing conduit along the shoulder of Idaho 44.  Most work will be done with only a shoulder closure required, although an occasional lane closure may be needed.

No work took place this past week due to the holiday. To accommodate widening at the intersection, the free-running right turn from northbound Linder to Idaho 44 will be closed permanently on Friday (Jan. 4).

Central Paving, of Boise, is the contractor on this $9.23 million project.

ADA, BOISE COUNTY
Replacement of Dynamic Message Signs (DMS)

In this project, Dynamic Message signs are being replaced in several locations, primarily on Idaho 21. The work involves removing the existing message signs and controller cabinets and replacing them with upgraded signs and cabinets at their current locations.

The sign locations are on Idaho 21 at the junction to Warm Springs, Idaho City, Lowman, and Stanley. And on the Banks to Lowman Highway at Banks, and Idaho 55 near the Shadow Valley Golf Course.

The contractor has received the DMS signs and has erected them on Idaho 55 at Shadow Valley, at Banks on the Banks to Lowman Road, and on Idaho 21 at Warm Springs and Idaho City.

On Thursday and Friday, crews erected signs at Lowman and Stanley. A crew is following the installation crew, pulling wire and making connections.

All signs will be turned on for a trial period Jan. 14-28. The trial period will include various messages of a non-critical nature.

Quality Electric Inc., of Boise, is the contractor on this $321,000 project. The work, which is not impacting traffic, is expected to finish by January 2013.

BOISE COUNTY
Idaho 21 resurfacing to Lowman

A resurfacing project covering 20.4 miles of Idaho 21 in Boise County is wrapping up for this construction season. The project has been suspended for the winter. Work will resume after June 15, as consistently hot temperatures are required for the remaining resurfacing.

The project runs from Mores Creek Summit to Clear Creek Bridge below Lowman, adding a Stress-Absorbing Fiberglass Layer with Emulsified Asphalt (SAFLEA) on two adjoining sections of Idaho 21 (milepost 52.3 to 60 and 60 to 72.7), conducting slope stabilization, and upgrading guardrail at existing locations.

A SAFLEA treatment is a seal coat with a coating of chopped glass fibers between the oil and gravel aggregates to enhance durability and reduce cracking.

Knife River Corp, of Boise, is the contractor on this $3.9 million project.

VALLEY COUNTY
CASCADE – Bridge Replacement

A replacement of the North Fork Payette River Bridge in downtown Cascade is now under way. The bridgework will extend into late fall 2013.

This summer also saw resurfacing of the roadway between the bridges in town. The contractor worked on installing two new inlets this week and a manhole to better control the roadway drainage. A manhole cover may need to be replaced in the spring, but right now there is too much snow on the ground to tell.

This project will replace the old, narrow, width-restricted bridge built in 1933 with one more than twice as wide. The existing bridge is 24 feet wide, and will be replaced with a 60-foot wide, 393-foot long, three-span bridge. The new bridge will have two 12-foot lanes, two 11-foot shoulders and a 14-foot median.

In addition, a paved extension will be built to the dirt shared-use path under the bridge on the north side of the river that provides access from both sides of the bridge to the new riverside park.

In the first stage, two-thirds of the new bridge will be built to the west of the existing structure. Traffic will be maintained on the existing bridge through this first stage of bridge work, and then will be routed to the new section of bridge for the remaining work as the old bridge is demolished. There will be traffic interruptions while the new roadway section leading to the new bridge is built.

The project was shut down for the holidays for the last few weeks. Crews have now returned and are working nn the bridge decking.

From Monday through Thursday, work that limits drivers to one lane in each direction is only allowed between 9 a.m. and 4 p.m. Two lanes will be maintained between noon Friday and noon Monday. A river safety and navigation plan will be in place for recreationists that use this section of the river.

Wadsworth Brothers Construction Co. Inc., of Draper, Utah, is the contractor on this $4.83 million project.

     