July 17, 2009
Contact:
Reed Hollinshead
Public Information Specialist
(208) 334-8881
June Sparks
Public Information Specialist
(208) 334-8003
FOR IMMEDIATE RELEASE
Asphalt removal for resurfacing project on Main Street in Donnelly to begin on Monday (July 20)
DONNELLY - Asphalt removal on an Idaho Transportation Department project to reconstruct Main Street in Donnelly is expected to begin Monday (July 20). Crews have been performing survey work thus far.
The contractor will remove asphalt starting at the north end of the project limits and proceeding into town on the southbound lane to the old flea market near the gas station. Crews will then turn around and perform the same work heading north.
At the same time, trenching is planned for pipe work and roadway drainage on the south end of town.
This
half-mile project consists of adding a left-turn bay onto Roseberry
Street (milepost 131) and a two-way left-turn (center turn) lane through
town, starting at Boulder Creek Bridge. The project also includes minor
sidewalk additions, drainage improvements and traffic-access control.
The
downtown section will be five lanes wide, and includes parking on each
side. In addition, there will be new curb and gutter on each side and a
new storm-drain system that includes underground pipe and ditches.
Crews
will work from 7 a.m. to 9 p.m. Monday through Thursday, and 7 a.m. to
noon on Fridays. No weekend work is expected. There are no length,
weight or width load restrictions on the project.
Flaggers will
be on hand throughout work hours to assist traffic and the public in
and out of businesses and residences in the project vicinity. The
contractor is required to maintain two-way traffic at night and on
weekends.
Valley Paving & Asphalt of Cottonwood, Idaho, is the contractor for this $975,000 project.
The project is expected to be completed by mid-September.
-30-