BOISE -
The following projects are part of the GARVEE Transportation Program in
southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle
(GARVEE) bonds to expedite highway projects.
BOISE - Interstate 84, Orchard Street Interchange
Work continues on a project
to reconstruct the Orchard Street Interchange in Boise.
Orchard
Street north of I-84 is reduced to one lane in each direction with a center
turn lane. The lane restrictions begin at Malad Street and end just before the
westbound off-ramp. The restrictions are in place continuously until late
September.
On Friday
(Sept. 18) from 9 to 11 p.m. Orchard Street will have one lane open in each
direction, with no center turn lane, while crews install a storm drain.
Flaggers will direct traffic during the work hours.
On Monday
(Sept. 21), motorists exiting eastbound I-84 will use a temporary off-ramp
starting at 10 p.m. and continuing until 5 a.m. Tuesday (Sept. 22). One lane
will be open on the temporary off-ramp.
The speed
limit on I-84 is 55 mph and shoulders are restricted in the project area. The
speed limit on surrounding roadways (Orchard Street, Wright Street, Victory
Road) is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction
is expected to be complete in spring 2010.
BOISE - Interstate
84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild the interchange to reduce
congestion and accommodate future I-84 lanes.
On Friday (Sept. 18), eastbound I-84 (under the Vista
Interchange) will be closed from 10 p.m. to 7 a.m. while crews set girders.
Motorists can exit and enter I-84 using the eastbound on- and off-ramps.
Westbound I-84 will be closed from 10 p.m. Saturday (Sept.
19) to 7 a.m. Sunday (Sept. 20) for the same work. Motorists can exit and enter
I-84 using the westbound on- and off-ramps. Flaggers will direct motorists
through the area.
Beginning Sunday (Sept. 20), I-84 will have one lane open in
each direction between the Broadway and Vista interchanges. These lane
restrictions will continue until the following Sunday (Sept. 27).
Flaggers will direct traffic through the intersection of Vista
Avenue and Airport Way/Wright Street from 10 p.m. Wednesday (Sept. 23) until
5:30 a.m. Thursday (Sept. 24). Crews will shut down and remove the old traffic
signal at this intersection and activate a new signal.
On Thursday (Sept. 24) at 10 p.m. the old signal will be
shut down and removed at the intersection of Vista Avenue and Elder Street/Sunrise
Rim. Flaggers will direct traffic at this intersection until 5:30 a.m. Friday
(Sept. 25) while crews activate the new signal.
Construction is expected to be complete in fall 2010.
* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading our foundation for future economic growth.
BOISE - Interstate
84, Cole Road to Broadway Avenue widening
ITD will rebuild and widen east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.
Crews will begin placing barrels and temporary guardrail on Monday (Sept. 21) near the Broadway Interchange. The speed limit will be 55 mph in the project area.
This project is expected to be complete in summer 2011.
ITD is adding a third east- and westbound lane to I-84
between Nampa and Meridian. The first 2.5 miles of the third lane opened near
the Meridian Interchange in August 2009. The remainder is expected to open in
November 2009.
The I-84
speed limit is 55 mph during construction.
Work began in late July to replace the current Ten Mile
Overpass with an interchange with on- and off-ramps. This project includes
widening Ten Mile Road and constructing two undercrossings for local roads
north and south of I-84.
Crews are driving steel piles into the ground to support the
interchange and two undercrossings. Pile driving operations are noisy and are
only allowed between 7 a.m. to 9 p.m. During the week of Monday, Sept. 21, the
pile driving operation will be located off Ten Mile Road, north of I-84.
Construction is expected to be complete in summer 2011.
In
addition, this GARVEE project will begin in the fall:
Replace two bridges in the Garrity Interchange with a
single, wider bridge to support additional lanes on the interstate. The project
will construct a third east- and westbound lane on I-84 through the Garrity
Interchange.
Est. Start: Fall 2009
Est. Completion: Winter 2010
A majority of the work will take place overnight from
7 p.m. to 6 a.m to minimize interference with traffic.
Milling (grinding was complete Tuesday (Sept. 15), and paving began Wednesday (Sept. 16). The speed limit has been raised from 35 mph to 45 mph.
The pavement in this stretch is rough and rutted. The resurfacing process will
extend the life of the roadway and create a smoother ride for motorists.
About an inch and a half of the existing pavement is being milled off the
surface, then replaced with new material in an overlay.
The 5.5-mile corridor shifts from as few as two lanes to as many as six. At
least one lane in each direction will be maintained throughout the project. The
traffic pattern for the corridor will change several times throughout the life
of the project, which is expected to be completed in early October.
Knife River of Boise is the contractor for this $1.4 million project.
CANYON COUNTY
CALDWELL - Indian Creek Bridges replacement
Crews are working extended hours, and pile driving is continuing.
Crews
have completed installation of the bridge deck for the first phase of the 21st
Avenue bridge over Indian Creek and shifted traffic to the new structure.
Removal
of the existing 21st Avenue bridge and construction of the new concrete bridge
is being completed in two phases. During the first phase, the east portion of
the bridge was removed and reconstructed, and traffic was routed onto the
existing bridge. During the second phase, traffic has been shifted to the
completed portion of the new bridge while the other half is reconstructed.
The bridge is being widened to four lanes (two lanes in each direction) to better serve the well-traveled route between Interstate 84 and The College of Idaho. Two lanes of traffic are being maintained during construction and business access on 21st remains open. Temporary signs are in place to direct customers.
These projects will
improve their structural integrity and extend the life of the roadway. Construction on both bridges is expected to be complete in
November 2009.
Braun-Jensen of Payette is the contractor on this $2.3 million project. This is
a Local Highway Technical Assistance Council project sponsored by the city of
Caldwell.
Motorists can expect lane closures during the day. One lane will
remain open through the project with flaggers and pilot cars used to guide
traffic through the work zone.
The top layer of pavement in the two-mile section will be milled off. The CRABS
(Cement Recycled Asphalt Base Stabilization) method of resurfacing will then place a new layer of pavement on
the surface. Guardrail also will be upgraded during the project.
Nampa Paving & Asphalt Co. is the contractor on this $716,000 project.
Re-striping has been completed and the detour removed. Caution is encouraged as some remaining items are being finished.
The old bridge was removed Aug. 5 and work has begun on
the new bridge.
The north portion is excavated, and bridge
stringers are scheduled for delivery and placement on Monday (Sept. 21). At this point, paving is still to
Exterior work is complete on the restroom building, volunteer enclosure and storage building, with roofing still to come. Electrical and mechanical system installation is 75 percent complete in the restroom and storage buildings. Striping of the main parking areas has been completed.
Concrete flatwork, sidewalk, and curb and gutter is complete. Paving of the road and parking areas also is under way.