BOISE -
The following projects are part of the GARVEE Transportation Program in
southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle
(GARVEE) bonds to expedite highway projects.
BOISE - Interstate 84, Orchard Street Interchange
Work continues on a project
to reconstruct the Orchard Street Interchange in Boise.
Orchard
Street north of I-84 is reduced to one lane in each direction with a center
turn lane. The lane restrictions begin at Malad Street and end just before the
westbound off-ramp. The restrictions are in place continuously until the end of
September, when two lanes will open in each direction.
On Friday
(Sept. 25) and Saturday (Sept. 26) the outside westbound lane on Interstate 84
will be closed from 10 p.m. to 5 a.m.
The speed
limit on I-84 is 55 mph and shoulders are restricted in the project area. The
speed limit on surrounding roadways (Orchard Street, Wright Street, Victory
Road) is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction
is expected to be complete in spring 2010.
BOISE - Interstate
84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild the interchange to reduce
congestion and accommodate future I-84 lanes.
Work on the new bridge deck will continue until Sunday
(Sept. 27). All lanes will be open on I-84 during the day, and at least one
lane will be open in both directions at night (10 p.m. to 5 a.m.).
Construction is expected to be complete in fall 2010.
* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading our foundation for future economic growth.
BOISE - Interstate
84, Cole Road to Broadway Avenue widening
ITD will rebuild and widen east- and westbound I-84 between
the Cole and Broadway interchanges in Boise. When complete, the interstate will
have four lanes in each direction.
This project began Sept. 21.
The speed limit is now 55 mph in the project area on I-84.
This project is expected to be complete in summer 2011.
ITD is adding a third east- and westbound lane to I-84
between Nampa and Meridian. The first 2.5 miles of the third lane opened near
the Meridian Interchange in August 2009. The remainder is expected to open in
November 2009.
The I-84
speed limit is 55 mph during construction.
Work began in late July to replace the current Ten Mile
Overpass with an interchange with on- and off-ramps. This project includes
widening Ten Mile Road and constructing two undercrossings for local roads
north and south of I-84.
Crews are driving steel piles into the ground to support the
interchange and two undercrossings. Pile driving operations are noisy and are
only allowed between 7 a.m. to 9 p.m.
During the week
of Monday (Sept. 28), the pile driving operation will be located at the future
undercrossing on Ten Mile Road, north of I-84.
The speed limit has been reduced to 35 mph on Ten Mile Road
between Franklin and Overland roads. Motorists should watch for trucks
traveling in the area.
Construction is expected to be complete in summer 2011.
In
addition, this GARVEE project will begin in the fall:
Replace two bridges in the Garrity Interchange with a
single, wider bridge to support additional lanes on the interstate. The project
will construct a third east- and westbound lane on I-84 through the Garrity
Interchange.
Est. Start: Fall 2009
Est. Completion: Winter 2010
Working hours are primarily 7 p.m. to 6 a.m. Sunday through Thursday to minimize interference with traffic.
Paving resumed Wednesday (Sept. 23) evening. The speed limit has been raised from 35 mph to 45 mph.
The pavement in this stretch is rough and rutted. The resurfacing process will
extend the life of the roadway and create a smoother ride for motorists.
About an inch and a half of the existing pavement is being milled off the
surface, then replaced with new material in an overlay.
The 5.5-mile corridor shifts from as few as two lanes to as many as six. At
least one lane in each direction will be maintained throughout the project. The
traffic pattern for the corridor will change several times throughout the life
of the project, which is expected to be completed in early to mid-October.
Knife River of Boise is the contractor for this $1.4 million project.
CANYON COUNTY
CALDWELL - Indian Creek Bridges replacement
Crews
continue to work extended hours at 11th Avenue and Arthur as they
drive piles as part of the effort to build a new bridge over Indian Creek.
The old structure has been removed, exposing Indian Creek. As a result, vehicles are being detoured around the intersection but pedestrian access to local business remains open and signs are in place to direct customers.
Traffic
at the 21st Avenue bridge over Indian Creek has been shifted to the
new half of the structure while crews work to finish the deck on the second
half of the bridge.
Removal
of the existing 21st Avenue bridge and construction of the new concrete bridge
is being completed in two phases. During the first phase, the east portion of the
bridge was removed and reconstructed, and traffic was routed onto the existing
bridge. During the second phase, traffic has been shifted to the completed
portion of the new bridge while the other half is reconstructed.
When construction is complete the new bridge will have four lanes (two lanes in each direction) to better serve the well-traveled route between Interstate 84 and The College of Idaho. Two lanes of traffic are being maintained during construction and business access on 21st remains open. Temporary signs are in place to direct customers.
These
projects will improve the structural integrity of both bridges and extend the
life of the roadway. Construction is expected to be
complete in November 2009.
Braun-Jensen of Payette is the contractor on this $2.3 million project. This is a Local Highway Technical Assistance Council project sponsored by the city of Caldwell.
Motorists can expect lane closures during the day. One lane will
remain open through the project with flaggers and pilot cars used to guide
traffic through the work zone.
The top layer of pavement in the two-mile section will be milled off. The CRABS
(Cement Recycled Asphalt Base Stabilization) method of resurfacing will then place a new layer of pavement on
the surface. Guardrail also will be upgraded during the project.
Nampa Paving & Asphalt Co. is the contractor on this $716,000 project.
The old bridge was removed Aug. 5 and work has begun on
the new bridge.
The roadway ballast section is constructed, and concrete work
(sidewalk, drop inlets, curbs) should be completed. Work on the bridge back
wall and sidewalk is expected to be completed in three weeks. After that,
paving will take place.
Exterior work is complete on the restroom building, volunteer enclosure and storage building, with roofing still to come. Electrical and mechanical system installation is 75 percent complete in the restroom and storage buildings. Striping of the main parking areas has been completed.
Concrete flatwork, sidewalk, and curb and gutter is complete. Paving of the road and parking areas also is under way.