BOISE - The following projects are part
of the GARVEE Transportation Program in southwest Idaho, which uses funds from
Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.
BOISE - Interstate 84,
Orchard Street Interchange
Work continues on a project to reconstruct the Orchard Street Interchange
in Boise.
Traffic
will switch to the new eastbound off-ramp when it opens Friday night (Oct. 30).
The speed
limit on I-84 is 55 mph and shoulders are restricted in the project area. The
speed limit on surrounding roadways (Orchard Street, Wright Street, Victory
Road) is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction
is expected to be complete in spring 2010.
BOISE - Interstate
84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild the Vista Avenue Interchange to
reduce congestion and accommodate future I-84 lanes.
The speed limit on I-84 is 55 mph. Watch for trucks entering
and exiting the construction zone.
Construction is expected to be complete in fall 2010.
* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading our foundation for future economic growth.
BOISE - Interstate
84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.
The speed limit is 55 mph in the project area on I-84.
This project is expected to be complete in summer 2011.
ITD is adding a third east- and westbound lane to I-84
between Nampa and Meridian. The first 2.5 miles of the third lane opened near
the Meridian Interchange in August 2009.
The westbound portion of the third lane opened the afternoon
of Friday, Oct. 30 as part of a dedication ceremony with Gov. C.L. "Butch"
Otter.
The eastbound portion will open by Sunday, Nov. 1 or Monday, Nov. 2.
One lane will be closed in both directions at night
throughout the weekend (Oct. 30-Nov. 1) as crews clear the work zone and
complete the project.
The I-84 speed
limit is 55 mph during construction.
Work continues to replace the current Ten Mile Overpass with
an interchange with on- and off-ramps. This project includes widening Ten Mile
Road and constructing two undercrossings for local roads north and south of
I-84.
Crews are driving steel piles into the ground to support the
interchange and two undercrossings. Pile driving operations are noisy and are
only allowed between 7 a.m. to 9 p.m.
The pile driving work will resume on Wednesday, Nov. 4 at
the future location of the Ten Mile Interchange near Ten Mile Road and I-84.
The speed limit has been reduced to 35 mph on Ten Mile Road
between Franklin and Overland roads. Motorists should watch for trucks
traveling in the area.
Construction is expected to be complete in summer 2011.
In
addition, this GARVEE project will begin in the fall:
ITD will replace two bridges in the Garrity Interchange with
a single, wider bridge to support additional lanes on the interstate. The
project will construct a third east- and westbound lane on I-84 through the
Garrity Interchange.
Est. Start: Late Fall 2009
Est. Completion: Winter 2010
Following is an update on
non-GARVEE state highway construction projects in southwest Idaho.
CANYON COUNTY
CALDWELL - Indian Creek Bridges replacement
Work to improve the structural integrity of two bridges over Indian Creek in Caldwell is in its final stages. The projects to replace bridges at 21st and 11th Avenue started in June and are scheduled for completion in November.
Abutments
are in place at 11th Avenue and Arthur and crews will begin setting the
steel girders this week.
Vehicles continue to be detoured around the intersection but pedestrian access to local business remains open and signs are in place to direct customers.
The bridge deck on the 21st Avenue structure was completed this week and in the next few days, concrete approaches will be in place. Traffic remains shifted to the new half of the structure while work to finish the deck on the second half of the bridge is completed.
Removal of the existing 21st Avenue bridge and construction of the new concrete bridge is being completed in two phases. During the first phase, the east portion of the bridge was removed and reconstructed, and traffic was routed onto the existing bridge. During the second phase, traffic has been shifted to the completed portion of the new bridge while the other half is reconstructed.
When construction is complete the new bridge will have four lanes (two lanes in each direction) to better serve the well-traveled route between Interstate 84 and The College of Idaho. Two lanes of traffic are being maintained during construction and business access on 21st remains open. Temporary signs are in place to direct customers.
Braun-Jensen of Payette is the contractor on this $2.3 million project. This is a Local Highway Technical Assistance Council project sponsored by the city of Caldwell.
WASHINGTON
COUNTY