BOISE - The following projects are part
of the GARVEE Transportation Program in southwest Idaho, which uses funds from
Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.
BOISE - Interstate 84,
Orchard Street Interchange
Work continues on a project to reconstruct the Orchard Street Interchange
in Boise.
The speed
limit on I-84 is 55 mph and shoulders are restricted in the project area. The
speed limit on surrounding roadways (Orchard Street, Wright Street, Victory
Road) is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction
is expected to be complete in spring 2010.
BOISE - Interstate
84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild the Vista Avenue Interchange to
reduce congestion and accommodate future I-84 lanes.
Crews are preparing to switch traffic onto the new eastbound
off-ramp the week of Nov. 9 13. Eastbound I-84 will have one lane open from
10 p.m. to 5 a.m. while crews work overnight to stripe pavement and place
guardrail prior to the traffic switch.
The speed limit on I-84 is 55 mph. Watch for trucks entering
and exiting the construction zone.
Construction is expected to be complete in fall 2010.
* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading our foundation for future economic growth.
BOISE - Interstate
84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.
The speed limit is 55 mph in the project area on I-84.
This project is expected to be complete in summer 2011.
ITD has added a third east- and westbound lane to I-84
for the majority of the stretch between Nampa and Meridian.
The westbound shoulder will be closed until mid-November
while crews finish work in the median.
The I-84
speed limit is 55 mph during construction.
Work continues on a project to replace the current Ten Mile
Overpass with an interchange with on- and off-ramps. This project includes
widening Ten Mile Road and constructing two undercrossings for local roads
north and south of I-84.
On Nov. 15, crews will resume driving steel piles into the
ground to support the interchange. Pile driving operations are noisy and are
only allowed between 7 a.m. to 9 p.m.
The speed limit has been reduced to 35 mph on Ten Mile Road
between Franklin and Overland roads. Motorists should watch for trucks
traveling in the area.
Construction is expected to be complete in summer 2011.
In
addition, this GARVEE project will begin this winter:
ITD will replace two bridges in the Garrity Interchange with
a single, wider bridge to support additional lanes on the interstate. The
project will construct a third east- and westbound lane on I-84 through the
Garrity Interchange.
Est. Start: Dec. 2009
Est. Completion: Winter 2010
CANYON COUNTY
CALDWELL - Indian Creek Bridges replacement
Work
to improve the structural integrity of two bridges over Indian Creek in
Caldwell should be complete by late Nov./early Dec., weather permitting. The
projects to replace bridges at 21st and 11th Avenue started in June and are in
the final stages.
Motorists
can expect a minor traffic shift to the west on the 21st Avenue structure
beginning next Tuesday (Nov. 10). Removal of the existing bridge and
construction of the new concrete bridge has been completed in two phases.
During the first phase, the east portion of the bridge was removed and
reconstructed, and traffic was routed onto the existing bridge. During the
second phase, traffic has been shifted to the completed portion of the new
bridge while the other half is reconstructed.
When construction is complete the new bridge will have four lanes (two lanes in each direction) to better serve the well-traveled route between Interstate 84 and The College of Idaho. Two lanes of traffic are being maintained during construction and business access on 21st remains open. Temporary signs are in place to direct customers.
Abutments are in place at 11th Avenue and Arthur and crews are setting the steel girders. Vehicles continue to be detoured around the intersection but pedestrian access to local business remains open and signs are in place to direct customers.
Braun-Jensen of Payette is the contractor on this $2.3 million project. This is a Local Highway Technical Assistance Council project sponsored by the city of Caldwell.
WASHINGTON
COUNTY