Five Year Fatality Rate per 100 Million Vehicle Miles
CY 2012 to 2016

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

1.28

Percent of Time Highways Clear of Snow/Ice During Winter Storms
2016/2017 Season

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

74%

Percent of Pavement in Good or Fair Condition
CY 2016

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

85%

Percent of Bridges in Good Condition
CY 2016

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

75%

Percent of Highway Project Designs Completed On or Ahead of Time
FFY 2018

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

99%

Final Construction Cost as a Percent of Contract Award
CY 2016

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

112.1%

Construction Cost at Award as a Percent of Budget
Federal Fiscal Year 2017

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

90.8%

Administration and Planning Expenditures ($000,000)
CY 2016

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

30.2

Days to Process Vehicle Titles
CYTD as of 11/30/17

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

4

DMV Transactions Processed on the Internet (in thousands)
CY 2016

/Apps/ScorecardDMZ/Images/gaugeBlack2.png

256.7