Our Mission. Your Mobility.





4/4/2008

Reed Hollinshead
ITD Communication
208-334-8881
reed.hollinshead@itd.idaho.gov

Traffic impacts begin Monday (April 7) on Idaho 45, Melba Road to Deer Flat Road south of Nampa
BOISE - A pavement rehabilitation project along eight miles of Idaho 45 south of Nampa, from Melba Road to Deer Flat Road, will begin Monday (April 7), the Idaho Transportation Department announced.

Traffic will be reduced to one lane through the construction zone and will be assisted by flaggers and a pilot car.

This project also will upgrade substandard bridge guardrail at the Mora Canal in the area.
 
The work is scheduled for completion in late May.


American Paving Co. of Meridian is the contractor on this $2.2 million project.

 
+