District 3 construction roundup
Southwest Idaho highway construction report for Aug. 7-13

BOISE Following is the southwest Idaho highway construction report for Aug. 7-13:

ADAMS COUNTY

U.S. 95 New Meadows to Cattle Crossing

This project will rehabilitate deteriorated pavement on U.S. 95 from its junction with Idaho 55 in New Meadows north seven miles to Cattle Crossing. The speed limit is 35 mph in the work zone.

BOISE COUNTY

Idaho 55 Horseshoe Bend turn lane

This project widens Idaho 55 through Horseshoe Bend, adding a continuous left-turn lane. A seal coat will be applied through town and past the port of entry just north of Horseshoe Bend as the last work of the project. Idaho Sand and Gravel is the contractor for this $800,000 project that is expected to be complete in September.

Banks to Lowman Road rock stabilization

This week crews will finish removing and stabilizing rock on the slopes above the Banks to Lowman Road to improve safety for motorists. Guardrail installation and pavement repair also are being finished. Both highway and river traffic should expect delays of up to 15 minutes when rocks are being removed. Flaggers will assist both river and highway traffic. This $400,000 project is scheduled to be complete Thursday (Aug. 11).

CANYON COUNTY

Interstate 84, Karcher Interchange

A new interchange will be built to serve businesses, commuters and residents in the west side of Nampa and surrounding areas. The project includes a five-lane interchange overpass to connect a new section of Idaho 55 with Karcher Road going past its intersection with Caldwell Boulevard. Current work includes clearing the ground, tree removal, fence removal, demolition and installation of sediment control devices. Aside from increased truck traffic in the area, traffic impacts are minimal. The interchange is expected to be open for traffic by winter 2006-7. Central Paving Inc. of Boise is the contractor for this $30 million project.

ELMORE COUNTY

Idaho 51, milepost 85 to I-84B, Mountain Home

This project consists of repaving Idaho 51 near Mountain Home. Mainline paving is complete. Crews are working on approach paving, striping, shoulder grooming and final touch-up items. All lanes will remain open during commute hours, 6-9 a.m. and 4-7 p.m., Mondays through Fridays. Idaho Sand and Gravel is the contractor for this $1.6 million project that is expected to be complete this month.

PAYETTE COUNTY

Fruitland Pennsylvania Avenue improvements

Through traffic is detoured around Pennsylvania Avenue and SW 4th Street in Fruitland while bicycle and pedestrian facilities are added to the roads shoulders. Local traffic is permitted. The work will be completed this month.

VALLEY COUNTY

McCall East-West Loop

This new route through McCall will provide an alternative crossing of the North Fork of the Payette River for local traffic. The project is scheduled to be complete this fall.

WASHINGTON COUNTY

Cambridge, U.S. 95, Idaho 71 pavement rehabilitation

This project will rehabilitate pavement on U.S. 95 and Idaho 71 through Cambridge. Other work includes guardrail improvements, some curb and gutter work, minor drainage improvements, and minor work on the bridges over Pine Creek, Spring Creek, Rush Creek and the Weiser River. The project is expected to be complete this fall.
 
+