GARVEE bonds will be sold in late January to finance highway projects in eastern, southwestern Idaho
BOISE - Bonds to construct highway projects on U.S. 30 in eastern Idaho and rebuild interchanges in southwestern Idaho will be sold in late January, the Idaho Transportation Department announced.

The Idaho Housing and Finance Association will issue $176 million in GARVEE bonds later this month.

The bond was scheduled to be sold in November 2008, but postponed because of instability in the country's financial markets.

"Our financial advisors at the Idaho Housing and Finance Association tell us the bond market has stabilized," Idaho Transportation Department Director Pamela Lowe said. "The bonds will fund the construction of five projects this summer, preliminary work on two more, and create approximately 3,500 jobs."

The program uses Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway improvements. The Idaho Legislature previously authorized the transportation department to issue $597 million in bonds through a partnership with the Idaho Housing and Finance Association.

The following projects will be financed with the selling of the bonds:
    U.S. 30, Topaz Bridge, construction    
    U.S. 30, Portneuf crossings, construction
    U.S. 30, 12th St. to Crystal Springs, construction    
    I-84, Ten Mile Interchange, construction
    I-84, Franklin to Garrity Interchange, design and right-of-way
    I-84, Orchard Interchange, construction
    I-84, Vista Avenue Interchange, right-of way    

The transportation department is requesting an additional $125 million in bonding authority from the 2009 Idaho Legislature to fund the following projects:

    I-84, Cole to Broadway widening    
    I-84, Vista Ave. Interchange, construction
    I-84, Garrity Interchange, widening
    Idaho 16, U.S. 20/26 to Idaho 44, engineering

 
+