Weekly GARVEE southwest Idaho highway construction report for May 29-June 5
BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

BOISE - Interstate 84, Orchard Street Interchange
Motorists can continue to expect north- and southbound lanes on Orchard Street to be shifted slightly west. 
   
Shifting traffic allows all five lanes to stay open during most of construction on the Orchard Interchange.

The speed limit on I-84 is 55 mph and shoulders are restricted in the project area. The speed limit on surrounding roadways (Orchard Street, Wright Street, Victory Road) is 25 mph.  ITD advises motorists to be cautious of trucks and equipment.

The project is expected to be complete in spring of 2010.

McAlvain Group of Companies, Inc. of Boise is the contractor for this $15.1 million project.

WEST TREASURE VALLEY - Interstate 84, Garrity to Meridian widening
Work continues on a project to widen I-84 to three lanes in both directions between the Garrity and Meridian interchanges.

Motorists are advised to use caution when heading westbound on I-84 near the Meridian Bridge.  Construction trucks will be merging with traffic in this area.

The project is expected to be complete in late 2009. The transportation department reminds motorists to use extra caution while traveling in the area.

The I-84 speed limit is 55 mph.


In addition, these GARVEE projects are upcoming this summer and fall:

MERIDIAN - Interstate 84, Ten Mile Interchange construction
Construct interchange to replace current overpass at location. Project also includes improvements to local roadways.
Est. Start:
Mid-July 2009
Est. Completion:
May 2011

BOISE - Interstate 84 Vista Avenue Interchange Reconstruction*

Rebuild Interchange to accommodate traffic and future I-84 lanes.
Est. Start:
Mid-July 2009
Est. Completion:
Sept. 2010
* Design for the project funded by GARVEE, butConstruction willbefunded by ARRA TIGER

BOISE - Interstate 84 Widening, Cole Road to Broadway Avenue interchange
Rebuild and widen freeway to add two new lanes, creating four in each direction.
Est. Start:
Sept. 2009
Est. Completion:
Dec. 2011

NAMPA - Interstate 84, Garrity Bridges replacement
This project will replace two bridges with a single, wider bridge to allow additional lanes on the interstate
Est. Start:
Nov. 2009
Est. Completion:
Late 2010

ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.
 
+