New Plymouth alert: Resurfacing on U.S. 30 from west end of town to junction of Idaho 72 to begin Sept. 14

NEW PLYMOUTH - Resurfacing through New Plymouth will begin Sept. 14 on the portion of U.S. 30 from the west end of town to the junction with Idaho 72. The Idaho Transportation Department anticipated work to be complete by mid-October.

Motorists can expect lane closures during the day. One lane will remain open through the project with flaggers and pilot cars used to guide traffic through the work zone. 

The top layer of pavement in the two-mile section will be milled off. The CRABS (Cement Recycled Asphalt Base Stabilization) method
of resurfacing will then place a new layer of pavement on the surface. Guardrail also will be upgraded during the project.

Nampa Paving & Asphalt Co. is the contractor on this $716,000 project.





 








 
+