New Plymouth alert: Resurfacing on U.S. 30 from west end of town to junction of Idaho 72 to begin Sept. 14
NEW
PLYMOUTH - Resurfacing through New
Plymouth will begin Sept. 14 on the portion of U.S. 30 from the west end of town to the
junction with Idaho 72. The Idaho Transportation Department anticipated work to
be complete by mid-October.
Motorists can expect lane closures during the day. One lane will
remain open through the project with flaggers and pilot cars used to guide
traffic through the work zone.
The top layer of pavement in the two-mile section will be milled off. The CRABS
(Cement Recycled Asphalt Base Stabilization) method of resurfacing will then place a new layer of pavement on
the surface. Guardrail also will be upgraded during the project.
Nampa Paving & Asphalt Co. is the contractor on this $716,000 project.