11/6/2009
Reed Hollinshead
ITD Communication
208-334-8881
reed.hollinshead@itd.idaho.gov
Southwest Idaho highway construction report for Nov. 6-13
BOISE - The following projects are part
of the GARVEE Transportation Program in southwest Idaho, which uses funds from
Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.
BOISE - Interstate 84,
Orchard Street Interchange
Work continues on a project to reconstruct the Orchard Street Interchange
in Boise.
The speed
limit on I-84 is 55 mph and shoulders are restricted in the project area. The
speed limit on surrounding roadways (Orchard Street, Wright Street, Victory
Road) is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction
is expected to be complete in spring 2010.
BOISE - Interstate
84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild the Vista Avenue Interchange to
reduce congestion and accommodate future I-84 lanes.
Crews are preparing to switch traffic onto the new eastbound
off-ramp the week of Nov. 9 13. Eastbound I-84 will have one lane open from
10 p.m. to 5 a.m. while crews work overnight to stripe pavement and place
guardrail prior to the traffic switch.
The speed limit on I-84 is 55 mph. Watch for trucks entering
and exiting the construction zone.
Construction is expected to be complete in fall 2010.
* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading our foundation for future economic growth.
BOISE - Interstate
84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.
The speed limit is 55 mph in the project area on I-84.
This project is expected to be complete in summer 2011.
WEST TREASURE VALLEY - Interstate 84,
Garrity to Meridian widening
ITD has added a third east- and westbound lane to I-84
for the majority of the stretch between Nampa and Meridian.
The westbound shoulder will be closed until mid-November
while crews finish work in the median.
The I-84
speed limit is 55 mph during construction.
MERIDIAN - Interstate 84, Ten Mile
Interchange construction
Work continues on a project to replace the current Ten Mile
Overpass with an interchange with on- and off-ramps. This project includes
widening Ten Mile Road and constructing two undercrossings for local roads
north and south of I-84.
On Nov. 15, crews will resume driving steel piles into the
ground to support the interchange. Pile driving operations are noisy and are
only allowed between 7 a.m. to 9 p.m.
The speed limit has been reduced to 35 mph on Ten Mile Road
between Franklin and Overland roads. Motorists should watch for trucks
traveling in the area.
Construction is expected to be complete in summer 2011.
In
addition, this GARVEE project will begin this winter:
NAMPA - Interstate 84, Garrity
Bridge/11th Ave. to Garrity
ITD will replace two bridges in the Garrity Interchange with
a single, wider bridge to support additional lanes on the interstate. The
project will construct a third east- and westbound lane on I-84 through the
Garrity Interchange.
Est. Start: Dec. 2009
Est. Completion: Winter 2010
CANYON COUNTY
CALDWELL - Indian Creek Bridges replacement
Work
to improve the structural integrity of two bridges over Indian Creek in
Caldwell should be complete by late Nov./early Dec., weather permitting. The
projects to replace bridges at 21st and 11th Avenue started in June and are in
the final stages.
Motorists
can expect a minor traffic shift to the west on the 21st Avenue structure
beginning next Tuesday (Nov. 10). Removal of the existing bridge and
construction of the new concrete bridge has been completed in two phases.
During the first phase, the east portion of the bridge was removed and
reconstructed, and traffic was routed onto the existing bridge. During the
second phase, traffic has been shifted to the completed portion of the new
bridge while the other half is reconstructed.
When construction is complete the new bridge will have four lanes (two lanes in each direction) to better serve the well-traveled route between Interstate 84 and The College of Idaho. Two lanes of traffic are being maintained during construction and business access on 21st remains open. Temporary signs are in place to direct customers.
Abutments are in place at 11th Avenue and Arthur and crews are setting the steel girders. Vehicles continue to be detoured around the intersection but pedestrian access to local business remains open and signs are in place to direct customers.
Braun-Jensen of Payette is the contractor on this $2.3 million project. This is a Local Highway Technical Assistance Council project sponsored by the city of Caldwell.
WASHINGTON
COUNTY
A project to upgrade the rest area on U.S. 95 at Midvale Hill is nearing completion. The rest area is expected to be re-open by mid-November.
This project is rehabilitating the existing rest area - built in 1987 - and caretaker facilities, creating additional truck parking, and includes other repairs. The rest room building is being completely reconstructed.
Perimeter fencing, some electrical and mechanical system installation and some roofing remains to be finished. A security system also is being installed.
The rest area will be closed during this project, and signs will be posted in Cambridge and Weiser to announce the closure. No temporary facilities are planned during this work.
WF Construction & Sales LLC of Meridian is the contractor on this $1.4 million project.
WEISER - Snake River Bridge replacement
The Snake River Bridge on the U.S. 95 Spur in Weiser is being replaced with a wider structure. The bridge connects Annex, Ore., to Weiser.
The contractor is setting the rest of the girders, and will work on pouring intermediate diaphragms (to keep the girders in place/stabilize them), and work on decking the bridge in preparation for pouring it. The deck is expected to be poured next week (Nov. 9-13).
The right and left ramps on the Idaho side of the bridge are closed. Traffic must follow the detour to access Old Highway 70. In addition, any traffic 12 feet or wider and/or taller than 14 feet 2 inches will need to detour through Payette.
Both abutments on the Idaho side of the bridge have been finished.
The original bridge was built in 1903, with an additional span added in 1911. Traffic signals were added in 1949. The bridge was replaced in the 1950s - that's the one being replaced in this project. Once completed, the bridge will be 16 feet wider and able to carry greater traffic volumes. The highway on both sides of the bridge also will be reconstructed.
New curb, gutter and sidewalks are being reconstructed on the Idaho side of the bridge.
The speed limit is reduced to 25 mph on the Oregon side of the bridge.
Sletten Construction of Boise is the contractor on this $10 million project. The project is expected to be completed by mid-February.
ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.