Southwest Idaho highway construction report for Nov. 13-20

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Orchard Street Interchange
Work continues on a project to reconstruct the Orchard Street Interchange in Boise.


A westbound lane on I-84 will be closed between 10 p.m. and 5 a.m. Wednesday through Friday (Nov. 18-20) while crews work each night:

 

- Guardrail will be removed Wednesday (Nov. 18)

- Traffic will switch to the new westbound off-ramp on Thursday (Nov. 19)

 

Westbound I-84 will be closed from 10 p.m. Friday to 5 a.m. Saturday to set girders for the new bridge. Motorists will be diverted to the off- and on-ramps during this closure. Flaggers will direct motorists.

 

The speed limit on I-84 is 55 mph and shoulders are restricted in the project area. The speed limit on surrounding roadways (Orchard Street, Wright Street, Victory Road) is 25 mph. ITD advises motorists to be cautious of trucks and equipment.

 

Construction is expected to be complete in spring 2010.

 

BOISE - Interstate 84, Vista Avenue Interchange Reconstruction*

Work is under way to rebuild the Vista Avenue Interchange to reduce congestion and accommodate future I-84 lanes.

 

Traffic will switch to the new Vista Avenue bridge later this month. In early December, the old bridge will be demolished.

 

The speed limit on I-84 is 55 mph. Watch for trucks entering and exiting the construction zone.

 

Construction is expected to be complete in fall 2010.

 

* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading our foundation for future economic growth.

 

BOISE -  Interstate 84, Cole Road to Broadway Avenue widening

ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

Crews will place guardrail on Monday and Tuesday (Nov. 16 and 17) on I-84 between the Orchard and Vista interchanges. An eastbound lane will be closed on Monday night, and a westbound lane will be closed on Tuesday night. Both closures are from 10 p.m. and 5 a.m.

 

The speed limit is 55 mph in the project area on I-84.

 

This project is expected to be complete in summer 2011.

 

WEST TREASURE VALLEY - Interstate 84, Garrity to Meridian widening

ITD has added a third east- and westbound lane to I-84 between Nampa and Meridian.

 

Between Black Cat and Ten Mile roads, the third lane will remain closed until spring 2010 during work on the Ten Mile Interchange.

 

The westbound shoulder will be closed until mid-November while crews finish work in the median.

 

The I-84 speed limit is 55 mph during construction.

 

MERIDIAN -  Interstate 84, Ten Mile Interchange construction

Work continues on a project to replace the current Ten Mile Overpass with an interchange with on- and off-ramps. This project includes widening Ten Mile Road and constructing two undercrossings for local roads north and south of I-84.

 

On Monday (Nov. 16), crews will resume driving steel piles into the ground to support the interchange. Work will be done at the site of the future Ten Mile Interchange. It is the final location for pile driving.

 

Crews will do tests on Monday and Wednesday (Nov. 16 and 18) between 7 a.m. to 9 p.m. Daily pile driving will resume later in the week.

 

The Ten Mile Overpass will be demolished in mid-December. During the demolition, I-84 will be closed between the Meridian and Garrity interchanges, and a detour route will be posted to guide motorists through the area.

 

The speed limit has been reduced to 35 mph on Ten Mile Road between Franklin and Overland roads. Motorists should watch for trucks traveling in the area.

 

Construction is expected to be complete in summer 2011.

 

NAMPA - Interstate 84, Garrity Bridge/11th Ave. to Garrity

ITD will replace two bridges in the Garrity Interchange with a single, wider bridge to support additional lanes on the interstate. The project will construct a third east- and westbound lane on I-84 through the Garrity Interchange.
Est. Start: Late Fall 2009

Est. Completion: Winter 2010

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.


CANYON COUNTY
CALDWELL - Indian Creek Bridges replacement

Crews will finish paving and striping the new structure at 21st Avenue by Monday (Nov. 16). Work to improve the structural integrity of bridges over Indian Creek at 21st and 11th Avenue and Arthur is in the final stages and should be complete by late Nov./early Dec., weather permitting.

 

Removal of the existing bridge and construction of the new concrete bridge at 21st has been completed in two phases. During the first phase, the east portion of the bridge was removed and reconstructed, and traffic was routed onto the existing bridge. During the second phase, traffic has been shifted to the completed portion of the new bridge while the other half is reconstructed.

 

When construction is complete the new bridge will have four lanes (two lanes in each direction) to better serve the well-traveled route between Interstate 84 and The College of Idaho. Two lanes of traffic are being maintained during construction and business access on 21st remains open. Temporary signs are in place to direct customers.

 

All of the steel girders have been set for the new bridge at 11th Avenue and Arthur but vehicles continue to be detoured around the intersection. Pedestrian access to local business remains open and signs are in place to direct customers.

 

Braun-Jensen of Payette is the contractor on this $2.3 million project. This is a Local Highway Technical Assistance Council project sponsored by the city of Caldwell.

 

WASHINGTON COUNTY

MIDVALE HILL - rest area improvement project
A project to upgrade the rest area on U.S. 95 at Midvale Hill is nearing completion. The rest area is expected to be re-open by the end of November. Door locks and hardware issues have delayed the re-opening.

This project has rebuilt the existing rest area - built in 1987 - and caretaker facilities, created additional truck parking, and includes other repairs. The rest room building was completely reconstructed.

Perimeter fencing, some electrical and mechanical system installation and some roofing remains. A security system is being installed.


The rest area will be closed during this project, and signs are posted in Cambridge and Weiser announcing the closure. No temporary facilities are available.


WF Construction & Sales LLC of Meridian is the contractor on this $1.4 million project.

WEISER - Snake River Bridge replacement
The Snake River Bridge on the U.S. 95 Spur in Weiser is being replaced with a wider structure. The bridge connects Annex, Ore., to Weiser.


The contractor is working on a cold-weather concrete plan and setting the deck-finishing machine. The deck pour is expected this next week (Nov. 16-20).

 
The right and left ramps on the Idaho side of the bridge are closed. Traffic must follow the detour to access Old Highway 70. In addition, any traffic 12 feet or wider and/or taller than 14 feet 2 inches will need to detour through Payette.

Both abutments on the Idaho side
of the bridge have been finished.

The original bridge was built in 1903, with an additional span added in 1911. Traffic signals were added in 1949. The bridge was replaced in the 1950s - that's the one being replaced in this project. Once completed, the bridge will be 16 feet wider and able to carry greater traffic volumes. The highway on both sides of the bridge also will be reconstructed.

New curb, gutter and sidewalks are being reconstructed on the Idaho side of the bridge.

The speed limit is reduced to 25 mph on the Oregon side of the bridge.

Sletten Construction of Boise is the contractor on this $10 million project. The project is expected to be completed by mid-February 2010.

ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.

 
+