Construction set to begin Sunday (Jan. 10) at I-84 Garrity Interchange in Nampa

BOISE - Construction on the I-84 Garrity Interchange improvement project in Nampa is anticipated to begin Sunday, (Jan. 10).

           

Crews will begin placing traffic barrels for the Idaho Transportation Department project and installing advanced warning signs on Sunday night. Trucks and heavy equipment will begin working in the area on Monday (Jan. 11).

 

Later this month, lane restrictions are anticipated to begin on Garrity Boulevard. At least one lane in each direction will be open on Garrity during daytime hours. Drivers can expect two lanes open in one direction and one lane open in the opposite direction during some of the construction. Many times, two lanes will be open in each direction. The speed limit will be lowered to 35 mph on Garrity and 55 mph on I-84 through the construction zones.

 

The project will remove two bridges on I-84 at the Garrity Interchange and replace them with a single bridge that will accommodate three lanes in each direction on the interstate. Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.


This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa. The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and four lanes in each direction from the Garrity to Meridian interchanges.


The project will be constructed in three stages:

 

Stage 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Stage 2 - Remove existing westbound bridge and build new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

Stage 3 - Remove existing eastbound bridge and build new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.


Concrete Placing Co. Inc. of Boise is the contractor of the $15 million project.

 

This work is funded through the GARVEE Transportation Program, which uses Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite interstate improvements.

 

ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.

 
+