3/9/2010
Emmett's Main Street to be resurfaced in project beginning this spring/summer
EMMETT - The Idaho Transportation advises motorists that a project to resurface and improve a mile of Main Street in Emmett is expected
to get under way this spring or early summer.
This
project, from the intersection of Boise Avenue to the intersection of
Washington Street (Idaho 52), includes pavement rehabilitation to remove
excessive rutting and cracking, with pothole repair and slope work included for
proper drainage. Sidewalks also will be replaced, maintaining the current
11-foot width, along with curb and gutter work.
Lighting and adjustments to the traffic signal at the intersection of Main and Washington also will be included.
WF Construction & Sales LLC of Meridian is the contractor on this $475,000 project.
The city of Emmett is the local sponsor for this project.