3/5/2010
Motorists advised to expect minor delays at U.S. 95, Lancaster Road intersection for utlity work Tuesday
COEUR D'ALENE - Motorists can expect minor delays as
Avista utility relocates a transmission line along U.S. 95 at the highway's intersection with Lancaster Road, on Tuesday (March 9), the Idaho Transportation Department
announced.
The transmission line is located north of Hayden on state right-of-way, which is part of the U.S. 95 Wyoming to Idaho 53 highway widening, known locally as "the Gap" project.
Avista will be pulling a transmission line across U.S. 95 on Tuesday from 9 a.m. to 11 a.m. at the intersection of U.S. 95 and Lancaster. Traffic on U.S. 95 will be stopped for 2-3 minute intervals, approximately three times. Traffic on Lancaster Road also will be affected.
The $6 million project will widen approximately two miles of U.S. 95 to four lanes.