6/18/2010
Reed Hollinshead
ITD Communication
208-334-8881
reed.hollinshead@itd.idaho.gov
Southwest Idaho highway construction report for June 18-25
BOISE
- The following projects are part of the GARVEE Transportation Program in
southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle
(GARVEE) bonds to expedite highway projects.
BOISE
- Interstate 84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild
the Vista Avenue Interchange to reduce congestion and accommodate future I-84
lanes.
Vista
Avenue north of the bridge will be reduced to one lane Tuesday-Thursday (June
22-24) from 9:30 a.m. to 4 p.m. each day. Crews will be pouring concrete for
sidewalks and pedestrian ramps for the newly widened Vista Avenue.
Flaggers will direct motorists as traffic
is moved into a new configuration late next week from 10 p.m. to 5 a.m. All
traffic will be switched to the east side of the bridge while crews reconstruct
the west side. Vista Avenue traffic will remain this way for approximately two
weeks.
The speed limit on I-84 is 55
mph and shoulders are restricted in the project area. The speed limit on Vista
Avenue is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction on the $17.8
million project is expected to be complete in late summer 2010.
* Design for the project was
funded by GARVEE, but project construction is funded through the federal
stimulus program, created to generate jobs and help boost Idaho's economy while
upgrading our foundation for future economic growth.
BOISE - Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and
widening east- and westbound I-84 between the Cole and Broadway interchanges in
Boise. When complete, the interstate will have four lanes in each direction.
Between the Cole and Broadway
interchanges, one east- and westbound lane will continue to have intermittent
lane closures overnight (10 p.m. to 5 a.m. on week nights, and 10 p.m. to 7
a.m. on weekends) through June 30.
Crews will pour concrete in
the median during the closures.
This $35.9 million project is
expected to be complete in summer 2011.
MERIDIAN - Interstate 84, Ten Mile Interchange construction
Work continues on a project
to construct a new interchange with on- and off-ramps at Ten Mile Road. The
project will include widening I-84 between Black Cat and Ten Mile roads.
Ten Mile Road is closed
between Franklin and Overland roads during construction.
The $33.8 million project is
expected to be complete in summer 2011.
NAMPA - Interstate 84, Garrity
Interchange Bridge reconstruction
Construction
on the I-84 Garrity Interchange improvement project continues. The project will
replace two bridges on I-84 at the Garrity Interchange with a single bridge
that will accommodate three lanes in each direction on the interstate.
Work
also includes reconstructing the interstate about a mile east of the
interchange to tie into the widening of I-84 between the Garrity and Meridian
interchanges, and removing the bridge piers in the roadway at Garrity
Boulevard.
Two
lanes southbound and one lane northbound on Garrity under I-84 will be open by
the morning commute and be open during the day. Overnight restrictions are not
expected to occur on Friday or Saturday nights. Lane restrictions are expected
to continue for the next few weeks until the bridge work is completed.
ITD continues flagging around the intersection of the westbound
Garrity off-ramp and Garrity Boulevard. The flagging will take place from
approximately 9:30 a.m. to 4 p.m. Work will be intermittent and should be
completed in about two weeks.
Flaggers will direct traffic through the construction area. The
flagging is needed to allow crews to repair and modify the storm-water drainage
system.
This
project is part of ITD's plans to improve I-84 between the Franklin and Garrity
interchanges in Nampa.
The
completed improvements will include three lanes in each direction from the
Franklin to Garrity interchanges, and eventually four lanes in each direction
from the Garrity to Meridian interchanges.
The
project is being constructed in three stages:
Currently Under Way
Stage
1 - Build the median section of the bridge between the existing bridges.
Traffic will remain on existing bridges, with two lanes open in each direction.
Tentatively starts December 2010
Stage
2 - Remove the existing westbound bridge and build a new westbound portion of
bridge. Westbound traffic will be moved onto the new median section. Two lanes
will remain open in each direction.
Tentatively starts Spring 2011
Stage
3 - Remove the existing eastbound bridge and build a new eastbound portion of
bridge. Westbound traffic will be shifted onto the new westbound portion of the
bridge, and eastbound traffic onto the median section.
Completion - By summer 2011, three
lanes will be open in each direction over the bridge, eventually connecting
with a fourth lane in each direction east of the interchange.
Concrete
Placing Co. Inc. of Boise is the contractor on the $15 million project.
Following
is an update on non-GARVEE state highway construction projects in southwest
Idaho.
ADA COUNTY
MERIDIAN - Eagle Road resurfacing
The resurfacing project on heavily traveled Eagle Road (Idaho 55)
is nearing completion.
Boise
Valley Railroad is planning to replace the crossing south of Pine tonight
(Friday, June 18) and tomorrow (Saturday, June 19). Crews will repave the
approach to the crossing immediately after the crossing is replaced.
Crews
are working a Sunday-through-Thursday, 8 p.m to 6 a.m., overnight schedule to
minimize inconvenience for drivers. Two lanes each way, with turn bays, will be
maintained at all other times. The speed limit is reduced to 35 mph.
According to the Ada County Highway District (ACHD), the intersection of Eagle
and Fairview is the busiest intersection in Ada County and the state. Four
intersections on Eagle Road are in ACHD's top eight. This project encompasses
three of them. ITD statistics show that only the Flying Wye (134,500) is busier
than the 132,500 vehicles the Eagle Road Interchange sees every day.
ITD
initiated the Eagle Road Arterial Study in 2003. Local municipalities, ACHD,
the Community Action Partnership of Southwest Idaho, homeowners associations
and ValleyRide were all involved in the initial study. This project is largely
a result of those initial meetings.
Central
Paving Co. Inc. of Boise is the contractor on the $1.35 million project.
ADAMS COUNTY
S. OF COUNCIL - Indian Valley Road
repaving
About
three miles of Indian Valley Road, south of Council in Adams County, will be
resurfaced in a project which started Monday. The work was initially postponed
so that Cambridge Telephone could relocate telephone lines to avoid
interference with construction activities. The paving work may take several
months to complete.
The
2.8-mile section from the end of pavement to the intersection with West Indian
Valley Road will be resurfaced. Improvements include repairing areas of
distressed pavement, overlaying a portion of the roadway and applying a seal
coat on a portion of the roadway. This will improve the driving surface and
extend the life of the road.
Traffic is
reduced to one lane around work area.
Adams
County is the local sponsor of the project.
The
project is located about 10 miles south of Council off of U.S. 95.
Knife
River Corp. Northwest, of Boise, is the contractor on the $349,000 project.
BOISE COUNTY
NORTH OF HORSESHOE BEND
HILL SUMMIT - spot repair
Repairs
to a slight depression on Idaho 55 on the north side of Horseshoe Bend Hill continue.
The roadway base material has been repaired, and the roadway is being brought
back up to grade for paving, which is expected to begin Wednesday (June 23).
Crews will shore up an area about 400 feet long near the Horseshoe
View Subdivision at milepost 60.4, which is about halfway down from the summit
on the Horseshoe Bend side of the hill. The work is expected to be complete in
July.
This section of roadway has settled about 18 inches since it was paved in the
early 1980s. Crews will grind the pavement off, add about 1,500 cubic yards of
road base to restore the road level, re-compact it and pave over the new
surface.
The damaged area extends across both directions of travel.
The speed limit will be reduced to 45 mph through the work zone. The road will
be reduced to one lane in each direction. ITD will separate the work zone from
traffic with concrete guardrail.
This $22,000 project will be done by State forces, with assistance from Western
Construction for the rotomilling and Idaho Sand & Gravel on the paving.
Knife River is contracted to supply the road base material for compaction.
CANYON COUNTY
CALDWELL - Franklin and 21st
reconstruction
Motorists can expect lane restrictions on
Commercial Way tomorrow (Saturday, June 19) as crews begin paving. Flaggers
will direct motorists through the work zone.
Work will continue on Monday and Tuesday
(June 21 and 22), and will include Specht and 21st Avenues. Paving is
anticipated to be completed on Tuesday, weather permitting.
Commercial Way between Specht and
Franklin is closed to through traffic. Franklin is closed while the roadway is
reconstructed and realigned to match up with the new five-lane roadway
constructed last summer. Motorists are detoured to 21st and Chicago
streets. Businesses on Franklin
can be accessed via Chicago.
The Franklin/21st intersection is about
one-quarter mile west of the newly-reconstructed Franklin Interchange (Exit 29).
The project will improve sight distance and safety on 21st and includes new
asphalt pavement, curb and gutter, sidewalk and lighting.
The first phase of this project, about a
quarter-mile section of 21st, was rebuilt last summer. The three-lane roadway
was widened to five lanes.
Work on this phase is ahead of schedule
and should be complete in early July.
Central Paving Co. of Boise is the
contractor on this $1.66 million project. Central Paving also was the
contractor on the first phase of the project last summer.
GEM COUNTY
EMMETT - Main Street resurfacing
Work
is under way on a project to resurface and improve a mile of Main Street in
Emmett.
This
project, from the intersection of Boise Avenue to the intersection of
Washington Street (Idaho 52), includes pavement rehabilitation to remove
excessive rutting and cracking, with pothole repair and slope work included for
proper drainage. Sidewalks also will be replaced, maintaining the current
11-foot width, along with curb and gutter work.
Lighting
and adjustments to the traffic signal at the intersection of Main and
Washington also will be included.
Work
this week included installing pole foundations and grading for curb on the
south side of the road. Next week (June 14-18) curb, gutter and sidewalk work
is scheduled.
WF
Construction & Sales LLC of Meridian is the contractor on this $475,000
project.
The city of Emmett is the local sponsor for this project.
ELMORE COUNTY
SOUTHWEST OF MOUNTAIN HOME - Road to
C.J. Strike Reservoir paving
The
Dam Cutoff Road carrying recreational traffic to the C.J. Strike Reservoir area
in Elmore County is being paved in a project now under way.
Crews
have clearance for minor blasting and clearing. Paving is expected to begin in
July.
The
road will be closed during construction, which is expected to finish this fall.
This
route is one way to get to C.J. Strike, but possibly the least-common route. However,
the improvements will make it a more desirable route and will shorten the trip
from Mountain Home to the dam.
The
Strike Dam Cutoff Road currently is a two-lane unpaved rural route in rolling
terrain. The project begins at the junction of Idaho 67 and extends about
one-quarter mile north of the C.J. Strike Dam, from about milepost 100 to 107.
The
paving is designed to provide a safer route and save on annual maintenance
costs.
Western
Construction Inc. of Boise is the contractor on the $1.86 million project.
This
project is locally sponsored by the Mountain Home Highway District.
PAYETTE COUNTY
WEST OF CALDWELL - I-84 resurfacing,
Black Canyon to Sand Hollow
The
pavement resurfacing and repair project on I-84 west of Caldwell continues. The
project, funded through stimulus savings, will treat the roadway surface
beginning west of the Black Canyon Interchange and extending for five miles, to
east of the Sand Hollow Interchange.
All
traffic within the project area has been traveling on the westbound side of the
interstate for several weeks. Crews continue replacing
damaged concrete slabs on eastbound I-84. In late July, crews should be
finished with slab repair on the eastbound side and begin working in the
westbound lanes.
During
the majority of the work, only one interstate lane will be open in both
directions.
The
work currently under way to repair slab and upgrade guardrail will continue for
the next 2-3 weeks.
The
speed limit is 45 mph over the median crossovers, and 55 mph between them.
The
project is expected to be complete this
fall.
Several
badly damaged concrete slabs in that stretch will be removed and replaced.
Repairs also will include resealing pavement joints, repairing pavement cracks
and chips, grinding portions off of the existing pavement surface and
completing guardrail safety improvements. Work will start in the eastbound
lanes (through July), then turn around and come back westbound.
A
highly competitive construction environment led to significant savings on the
eight original projects funded by the federal stimulus program ARRA (American
Recovery and Reinvestment Act). This is one of nine smaller projects financed
through those initial bid savings.
Multiple
Concrete Enterprises of Ogden, Utah, is the contractor on the $6.9 million
project.
FRUITLAND, PAYETTE - pavement
resurfacing
Work began June 1 on several pavement rehabilitation projects
encompassing about six miles of U.S. 95 from north Fruitland to north Payette
as well as about one-half mile of U.S. 30 between the Snake River and
Fruitland. In addition to resurfacing, pavement cracks also will be filled
throughout the project area.
Standard work hours will be 7 a.m. to dusk Monday through Thursday, and to noon
on Friday. No weekend work is expected. There may be some overnight (10 p.m. to
5 a.m.) work when the contractor is working on the signalized intersections at
U.S. 95 and U.S. 30 (Gayway Junction) and the U.S. 95/95 Spur intersection
south of Payette. The traffic signals at those intersections will be upgraded
to video detection-based operating systems.
Knife River of Boise is the contractor on this $2.1 million project.
FRUITLAND - S. Pennsylvania
Avenue resurfacing
A
project to resurface South Pennsylvania Avenue in Fruitland is under way.
Construction is expected to last about two months.
The
project will include a mill and overlay (about two inches of the existing
surface will be removed, and replaced with two inches of new pavement) between
U.S. 95 and SW 4th Street.
The contractor
has been constructing curb, gutter and sidewalk along S. Penn Avenue. This work
is anticipated to continue through next Friday, June 25. Traffic delays are not
expected.
Milling and asphalt overlay work is expected to begin during the week of June
28. The public should expect traffic delays when this begins.
Improvements to the existing crosswalks and advanced signing will
be constructed to increase pedestrian safety. After this overlay, pavement
markings would be replaced and will improve vehicle circulation at the
elementary and middle schools.
South Pennsylvania Avenue is an integral part of the transportation system for
Fruitland. It is the only roadway access to the Fruitland elementary and middle
schools and also provides approach to the Fruitland intermediate and high
schools. The avenue also serves as a northbound gateway into Fruitland.
The city of Fruitland is the local sponsor of this project, and also is
participating financially.
Irvco Asphalt & Gravel Inc. of Fruitland is the contractor on
this $298,000 project.
WASHINGTON COUNTY
WEISER - Snake River Bridge replacement
The
project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser
is nearing completion.
Traffic control remains operational when needed. Flaggers will be
used, but the type and location of the work will dictate how many flaggers (if
any) are needed.
The
original bridge was built in 1903, with an additional span added in 1911.
Traffic signals were added in 1949. The bridge was replaced in the 1950s - that
one is being replaced in this project. Once completed, the bridge will be 16
feet wider and able to carry greater traffic volumes. The highway on both sides
of the bridge also will be reconstructed.
New curb, gutter and sidewalks are being reconstructed on the Idaho side of the
bridge.
The speed limit is reduced to 25 mph on the Oregon side of the bridge.
Sletten Construction of Boise is the contractor on this $10 million project.
The project is expected to be completed by
mid-July.
ITD and the Idaho State Police caution
motorists to slow down and pay attention when driving in work zones, where increased
speeding fines and other penalties apply. Motorists are encouraged to plan
ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state
highway or interstate system.