Southwest Idaho highway construction report for July 9-16
BOISE - The following projects are part of the GARVEE Transportation
Program in southwest Idaho, which uses funds from Grant Anticipation Revenue
Vehicle (GARVEE) bonds to expedite highway projects.
BOISE -
Interstate 84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild the Vista
Avenue Interchange to reduce congestion and accommodate future I-84 lanes. The
new SPUI signal was installed overnight Tuesday (July 6), but it wont be
operational immediately. It will take several weeks for crews to wire and test
the 125-foot, 13,000-lb. signal.
The speed limit on I-84 is 55 mph and
shoulders are restricted in the project area. The speed limit on Vista Avenue
is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction on the $17.8 million project
is expected to be complete in late
summer 2010.
* Design for the project was funded by
GARVEE, but project construction is funded through the federal stimulus
program, created to generate jobs and help boost Idaho's economy while
upgrading our foundation for future economic growth.
BOISE -
Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and
westbound I-84 between the Cole and Broadway interchanges in Boise. When
complete, the interstate will have four lanes in each direction.
Between
the Cole and Broadway interchanges, one east- and westbound lane will continue
to have intermittent lane closures overnight (10 p.m. to 5 a.m. on week nights,
and 10 p.m. to 7 a.m. on weekends) through July 31.
Crews will pour concrete in the median
during the closures.
This $35.9 million project is expected to
be complete in summer 2011.
MERIDIAN -
Interstate 84, Ten Mile Interchange construction
Work continues on a project to construct
a new interchange with on- and off-ramps at Ten Mile Road. The project includes
an extension of Tasa Road to connect with Overland Road. The new extension was
paved last week.
I-84 will be restricted on Monday and
Tuesday nights (July 12 and 13) while overhead signs are installed.
- One lane of westbound I-84 will be
closed from 10 p.m. Monday to 5 a.m. Tuesday between the Meridian Interchange
and Black Cat Road.
- One lane of eastbound I-84 will be
closed from 10 p.m. Tuesday to 5 a.m. Wednesday between Ten Mile Road and Black
Cat Road.
Ten Mile Road is closed between Franklin
and Overland roads during construction.
The $33.8 million project is expected to
be complete in summer 2011.
NAMPA - Franklin to 11th interstate
widening
The
final project in the widening of I-84 to three lanes from Nampa's Franklin Road
to Garrity Boulevard is now under way. Bridge projects at Garrity and at 11th
are already under way to accommodate the additional lanes.
The
project will improve I-84 between the Franklin and Garrity interchanges by
widening the interstate to three lanes in each direction and adding an
auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists
to enter I-84 at Franklin, remain in the lane furthest right, and exit at
Garrity - never having to merge with interstate traffic.
The
project includes also the replacement of the Union Pacific Railroad and Phyllis
Canal bridges.
Construction
is expected to be complete by late
spring or early summer 2012. The widening project is one of several
interstate improvement projects occurring in an 18-mile stretch of I-84, funded
by the GARVEE Transportation Program. The program uses proceeds from Grant
Anticipation Revenue Vehicle (GARVEE) bonds to accelerate highway improvements
throughout Idaho.
Concrete
Placing Company, of Boise, is the contractor on this $22.2 million project.
NAMPA 11th Avenue Bridge
Work is progressing on the 11th Avenue
bridge over I-84 in Nampa.
The
11th Avenue bridge closed in mid-May and will remain closed until late summer.
Reconstruction
of the bridge is required to accommodate future lanes on I-84.
Construction
on the widening is scheduled to be complete by early summer 2012.
McAlvain Civil Constructors the
contractor on the $4.1 million 11th Avenue Bridge project.
The
bridge reconstruction and I-84 widening projects are among several interstate
improvements occurring in an 18-mile stretch of I-84, funded by the GARVEE
Transportation Program. The program uses proceeds from Grant Anticipation
Revenue Vehicle bonds.
NAMPA - Interstate 84, Garrity
Interchange Bridge reconstruction
Construction
on the I-84 Garrity Interchange improvement project continues. The project will
replace two bridges on I-84 at the Garrity Interchange with a single bridge
that will accommodate three lanes in each direction on the interstate.
Work
also includes reconstructing the interstate about a mile east of the
interchange to tie into the widening of I-84 between the Garrity and Meridian
interchanges, and removing the bridge piers in the roadway at Garrity
Boulevard.
Motorists traveling westbound on I-84 should
expect a few changes at the Garrity Interchange starting Monday morning (July
12).
1. I-84 westbound
traffic will be shifted to the south onto the newly constructed median section
of the freeway between the Robinson Road Overpass and the Garrity Interchange.
The shift will occur overnight starting at 10 p.m. Sunday night, and be
completed by 5 a.m. Monday morning, prior to the morning commute.
After
motorists are past the Garrity construction area, they will shift back to the
north out of the middle.
2. Westbound motorists
wanting to exit at Garrity will need to stay to the right and enter the exit
lane near the Robinson Road Overpass. This is nearly a mile earlier than usual.
This
configuration on I-84 will last several months, allowing crews to remove and
replace the existing westbound bridge. Once a new westbound bridge is built,
westbound traffic will be moved back onto the new construction allowing the eastbound
bridge to be removed and replaced.
3. Garrity Boulevard
will be reduced to one lane in each direction under the Garrity Interchange
overnight (10 p.m. to 5 a.m.) each night from Monday night to Thursday night
(July 12-15) while crews prepare the bridge deck for removal. Two southbound
and one northbound lane will be open by the morning commute and during the day.
This
project is part of ITD's plans to improve I-84 between the Franklin and Garrity
interchanges in Nampa.
The
completed improvements will include three lanes in each direction from the
Franklin to Garrity interchanges, and eventually four lanes in each direction
from the Garrity to Meridian interchanges.
The
project is being constructed in three stages:
Currently Under Way
Stage
1 - Build the median section of the bridge between the existing bridges.
Traffic will remain on existing bridges, with two lanes open in each direction.
Tentatively starts December 2010
Stage
2 - Remove the existing westbound bridge and build a new westbound portion of
bridge. Westbound traffic will be moved onto the new median section. Two lanes
will remain open in each direction.
Tentatively starts Spring 2011
Stage
3 - Remove the existing eastbound bridge and build a new eastbound portion of
bridge. Westbound traffic will be shifted onto the new westbound portion of the
bridge, and eastbound traffic onto the median section.
Completion - By summer 2011, three
lanes will be open in each direction over the bridge, eventually connecting
with a fourth lane in each direction east of the interchange.
Concrete
Placing Co. Inc., of Boise, is the contractor on the $15 million project.
Following
is an update on non-GARVEE state highway construction projects in southwest
Idaho.
ADA COUNTY
MERIDIAN - Eagle Road resurfacing
The resurfacing project on heavily traveled Eagle Road (Idaho 55)
is nearing completion.
Both the north- and southbound lanes on
Eagle Road at the railroad crossing have been finished. Crews paved the
permanent tie-in to the railroad crossing in the northbound lanes Monday night
(July 5). The speed limit was raised from 35 mph limit during construction to
50 mph. Some occasional nighttime lane closures will be necessary in the coming
weeks for installation of some permanent pavement markings and signs. In
addition, some final work will be done closer to the freeway later in July.
Central
Paving Co. Inc., of Boise, is the contractor on the $1.35 million project.
ADAMS COUNTY
S. OF COUNCIL - Indian Valley Road
repaving
The
resurfacing of about three miles of Indian Valley Road, south of Council in
Adams County, is expected to be completed soon.
The
2.8-mile section from the end of pavement to the intersection with West Indian
Valley Road is being resurfaced to improve the driving surface and extend the
life of the road.
Crews finished
paving this week (July 5-9). The overall project is expected to be
substantially complete by today (Friday, July 9) with only minor clean-up items
remaining.
Adams
County is the local sponsor of the project.
The
project is located about 10 miles south of Council off of U.S. 95.
Knife
River Corp. Northwest, of Boise, is the contractor on the $349,000 project.
BOISE COUNTY
NORTH OF HORSESHOE BEND
HILL SUMMIT - spot repair
Repairs
to a slight depression on Idaho 55 on the north side of Horseshoe Bend Hill
continue.
Crews will shore up an area about 400 feet long near the Horseshoe
View Subdivision at milepost 60.4, which is about halfway down from the summit
on the Horseshoe Bend side of the hill. The work is expected
to be complete in August.
Crews returned
to work July 6 on this project, after the holiday, closing the left-hand
southbound lane to southbound traffic. In addition, both northbound lanes are
closed and northbound traffic has been shifted to the southbound left lane.
This
section of roadway has settled about 18 inches since it was paved in the early
1980s. Crews will grind the pavement off, add about 1,500 cubic yards of road
base to restore the road level, re-compact it and pave over the new surface.
The damaged area extends across both directions of travel.
The speed limit will be reduced to 45 mph through the work zone. The road will
be reduced to one lane in each direction. ITD will separate the work zone from
traffic with concrete guardrail.
This $22,000 project will be done by State of Idaho forces, with assistance
from Western Construction for the rotomilling and Idaho Sand & Gravel on
the paving. Knife River is contracted to supply the road base material for
compaction.
CANYON COUNTY
CALDWELL - Franklin and 21st
reconstruction
The reconstruction of the intersection of
Franklin and 21st in Caldwell continues.
Roadwork and lane striping is complete.
Crews finishing roadside sign installation (such as speed limit and stop signs)
this week. Next, crews will begin assembling the traffic signal at the Franklin
Road 21st Avenue intersection. The signal is expected to be operational
during the week of July 12. Once operational, traffic will be allowed onto 21st
Avenue, nearly two months ahead of schedule.
Commercial Way between Specht and
Franklin is closed to through traffic. Franklin is closed while the roadway is
reconstructed and realigned to match up with the new five-lane roadway
constructed last summer. Motorists are detoured to 21st and Chicago
streets. Businesses on Franklin
can be accessed via Chicago.
The Franklin-21st intersection is about
one-quarter mile west of the newly reconstructed Franklin Interchange (Exit
29). The project will improve sight distance and safety on 21st and includes
new asphalt pavement, curb and gutter, sidewalk and lighting.
The first phase of this project, about a
quarter-mile section of 21st, was rebuilt last summer. The three-lane roadway
was widened to five lanes.
Central Paving Co. of Boise is the
contractor on this $1.66 million project. Central Paving also was the
contractor on the first phase of the project last summer.
GEM COUNTY
EMMETT - Main Street resurfacing
Work
is under way on a project to resurface and improve a mile of Main Street in Emmett.
The project is expected to be
finished in early October.
This
project, from the intersection of Boise Avenue to the intersection of
Washington Street (Idaho 52), includes pavement rehabilitation to remove
excessive rutting and cracking, with pothole repair and slope work included for
proper drainage. Sidewalks also will be replaced, maintaining the current
11-foot width, along with curb and gutter work.
Lighting
and adjustments to the traffic signal at the intersection of Main and
Washington also will be included.
The project is
complete on the south side. The contractor is currently building subgrade on
the north side.
WF
Construction & Sales LLC, of Meridian, is the contractor on this $475,000
project.
The city of Emmett is the local sponsor for this project.
ELMORE COUNTY
SOUTHWEST OF MOUNTAIN HOME - Road to
C.J. Strike Reservoir paving
The
Dam Cutoff Road carrying recreational traffic to the C.J. Strike Reservoir area
in Elmore County is being paved in a project now under way.
Crews are now
paving. Guardrail installation and restriping is scheduled for later in July,
after which the road can be opened. The project is running ahead of
schedule.
The
road will be closed during construction.
This
route is one way to get to C.J. Strike, but possibly the least-common route.
However, the improvements will make it a more desirable route and will shorten
the trip from Mountain Home to the dam.
The
Strike Dam Cutoff Road currently is a two-lane unpaved rural route in rolling
terrain. The project begins at the junction of Idaho 67 and extends about
one-quarter mile north of the C.J. Strike Dam, from about milepost 100 to 107.
The
paving is designed to provide a safer route and save on annual maintenance
costs.
Western
Construction Inc. of Boise is the contractor on the $1.86 million project.
This
project is locally sponsored by the Mountain Home Highway District.
OWYHEE COUNTY
DUCK VALLEY State Line to Sheep Creek
Road resurfacing
A
pavement resurfacing project on approximately 20 miles of Idaho 51, from the
Nevada State Line to Sheep Creek Road in Owyhee County, has been delayed and is
now expected to start Monday (July 12). The project is expected to take until late August to complete.
The work is about 70 miles south of Mountain Home and travels through the Duck
Valley Indian Reservation.
On
this two-lane road, the first 11.4-mile stretch will receive a thin overlay of
asphalt (about 1.8 inches) and the entire 20-mile area will be seal coated. A
half-inch scrub coat, to mitigate cracking, also will be applied to the first
eight miles.
Traffic will be directed when necessary
by flaggers and pilot cars.
Valley Paving & Asphalt Co., of Cottonwood, is the contractor on this $1.92
million project.
PAYETTE COUNTY
WEST OF CALDWELL - I-84 resurfacing,
Black Canyon to Sand Hollow
The
pavement resurfacing and repair project on I-84 west of Caldwell continues. The
project, funded through stimulus savings, will treat the roadway surface
beginning west of the Black Canyon Interchange and extending for five miles, to
east of the Sand Hollow Interchange.
All
traffic within the project area has been traveling on the westbound side of the
interstate for several weeks. Crews continue replacing damaged concrete slabs,
grinding concrete and installing new guardrail end terminals on eastbound I-84. In late July, crews
should be finished with slab repair on the eastbound side and begin working in
the westbound lanes.
During
the majority of the work, only one interstate lane will be open in both
directions.
The
speed limit is 45 mph over the median crossovers, and 55 mph between them.
The
project is expected to be complete this
fall.
Several
badly damaged concrete slabs in that stretch will be removed and replaced.
Repairs also will include resealing pavement joints, repairing pavement cracks
and chips, grinding portions off of the existing pavement surface and
completing guardrail safety improvements. Work will start in the eastbound
lanes (through July), then turn around and come back westbound.
A
highly competitive construction environment led to significant savings on the
eight original projects funded by the federal stimulus program ARRA (American
Recovery and Reinvestment Act). This is one of nine smaller projects financed
through those initial bid savings.
Multiple
Concrete Enterprises, of Ogden, Utah, is the contractor on the $6.9 million
project.
FRUITLAND, PAYETTE - pavement
resurfacing
Work is under way on several pavement rehabilitation projects
encompassing about six miles of U.S. 95 from north Fruitland to north Payette
as well as about one-half mile of U.S. 30 between the Snake River and
Fruitland. In addition to resurfacing, pavement cracks also will be filled
throughout the project area.
Standard work hours will be 7 a.m. to dusk Monday through Thursday, and to noon
on Friday. No weekend work is expected. There may be some overnight (10 p.m. to
5 a.m.) work when the contractor is working on the signalized intersections at
U.S. 95 and U.S. 30 (Gayway Junction) and the U.S. 95/95 Spur intersection
south of Payette. The traffic signals at those intersections will be upgraded
to video detection-based operating systems.
Crews are continuing to pave and mill
U.S. 95 in Fruitland and into Payette. Milling through Payette will require one
lane closure (in the three-lane section). Two-way traffic will be allowed to
continue through the work zone. Paving in Payette is not expected to start
until next week (July 12-16).
Crews are halfway finished doing work at
Gayway Junction, and will finish the second half overnight Monday (July 12).
Work will progress to the intersection in south Payette overnight Tuesday.
Knife River, of Boise, is the contractor on this $2.1 million
project.
FRUITLAND - S. Pennsylvania Avenue
resurfacing
A
project to resurface South Pennsylvania Avenue in Fruitland is wrapping up.
The
project has entailed a mill and overlay (about two inches of the existing
surface will be removed, and replaced with two inches of new pavement) between
U.S. 95 and SW 4th Street.
Crews completed
milling and paving the week before the holiday. They installed signs and
pavement markings this week and will continue it next week (July 12-16), at
which time the project should be substantially complete.
South Pennsylvania Avenue is an integral part of the
transportation system for Fruitland. It is the only roadway access to the
Fruitland elementary and middle schools and also provides approach to the
Fruitland intermediate and high schools. The avenue also serves as a northbound
gateway into Fruitland.
The city of Fruitland is the local sponsor of this project, and also is
participating financially.
Irvco Asphalt & Gravel Inc., of Fruitland, is the contractor
on this $298,000 project.
PAYETTE U.S. 95, Payette River Bridge
replacement
The project to improve the U.S. 95 bridge over the Payette
River south of Payette has been pushed back and is now likely to start soon.
Once construction has started, it is expected to take about two years to complete.
Road resurfacing work near Payette, which is now under way
in a separate project, is finishing. This resurfacing work must be completed
before work on the Payette River Bridge can begin.
There are job
trailers on site, weekly meetings are being with the contractor, and crews are
awaiting the right river level to begin cofferdam placement.
ITD will replace the existing northbound truss bridge (built
in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will
be two feet higher off the water. It will have no overhead bracing or struts as
the current one does and will be 84 feet in width, eliminating current safety
concerns regarding both width and height restrictions.
The new bridge will be constructed next to, and will attach to,
the existing southbound bridge. The project includes also minor roadway
realignment to tie into the new bridge location.
U.S. 95 is the main route connecting northern and southern Idaho. About 18,000
vehicles use this portion of the highway daily. By 2026, the volume is expected
to be more than 25,000.
Traffic will utilize the southbound bridge while the new bridge is constructed.
Traffic will then be switched to the new bridge while modifications to the
southbound bridge are made and it is connected to the new bridge.
JC Constructors Inc., of Meridian, is the contractor for this $6.17
million project.
WASHINGTON COUNTY
WEISER - Snake River Bridge replacement
The
project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser
is nearing completion.
The roadway is
clear of all traffic-control drums. Last week there was no construction
activity, but next week (July 12-16), crews should begin final work on the
bridge and the fencing should be installed. Final clean-up items include seeding/planting (planting may
be in the spring), fencing, returning new mailboxes to their original locations,
and the replacement of a couple of signs.
The
original bridge was built in 1903, with an additional span added in 1911.
Traffic signals were added in 1949. The bridge was replaced in the 1950s - that
one is being replaced in this project. Once completed, the bridge will be 16
feet wider and able to carry greater traffic volumes. The highway on both sides
of the bridge also will be reconstructed.
Sletten Construction of Boise is the contractor on this $10 million project.
The project is expected to be completed by
mid-July.
ITD and the Idaho State Police caution
motorists to slow down and pay attention when driving in work zones, where
increased speeding fines and other penalties apply. Motorists are encouraged to
plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state
highway or interstate system.