7/8/2010
I-90 repairs in the Coeur d'Alene and Post Falls area begin next week
COEUR D'ALENE - State work crews will be doing minor repair work at two locations along Interstate 90 beginning Tuesday (July 13). The Idaho Transportation Department adds that the work is being done as part of the department's ongoing maintenance of the state highway system.
Crews will be working on the I-90/Northwest
Boulevard overpass on Tuesday. They will be patching the roadway surface with an asphalt overlay. Work will then move to Spokane Street
under the interstate in Post Falls on Wednesday (July 14).
Work will begin each day at 9 a.m., after the
morning rush hour. Work is
expected to finish each day by about 2 p.m.
ITD and the Idaho State Police caution
motorists to slow down and pay attention when driving in work zones, where
increased speeding fines and other penalties apply. Motorists are encouraged to
plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state
highway or interstate system.