Southwest Idaho highway construction report for July 16-23
BOISE - The following projects are part of the GARVEE Transportation
Program in southwest Idaho, which uses funds from Grant Anticipation Revenue
Vehicle (GARVEE) bonds to expedite highway projects.
BOISE
- Interstate 84, Vista Avenue Interchange Reconstruction*
Work is under way to rebuild
the Vista Avenue Interchange to reduce congestion and accommodate future I-84
lanes.
Vista Avenue at the bridge will be reduced to one lane in each direction overnight tonight (Friday, July 16). Flaggers will direct traffic from 10 p.m. Friday to 5 a.m. Saturday while crews re-wire the signal at the Vista Avenue/Airport Way/ Wright Street intersection.
One lane will be closed in both directions on Vista Ave. at 10 p.m. Thursday (July 22). All lanes across the bridge will be closed from 11:30 p.m. Thursday to 5:30 a.m. Friday. Flaggers will direct traffic at the on- and off-ramps while crews activate the new traffic signal at the center of the interchange.
The speed limit on I-84 is 55
mph and shoulders are restricted in the project area. The speed limit on Vista
Avenue is 25 mph. ITD advises motorists to be cautious of trucks and equipment.
Construction on the $17.8
million project is expected to be complete in late
summer 2010.
* Design for the project was
funded by GARVEE, but project construction is funded through the federal
stimulus program, created to generate jobs and help boost Idaho's economy while
upgrading our foundation for future economic growth.
BOISE
- Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and
widening east- and westbound I-84 between the Cole and Broadway interchanges in
Boise. When complete, the interstate will have four lanes in each direction.
Between the Cole and Broadway interchanges, one east- and
westbound lane will continue to have intermittent lane closures overnight (10
p.m. to 5 a.m. on week nights, and 10 p.m. to 7 a.m. on weekends) through July
31.
Crews will pour concrete in
the median during the closures.
This $35.9 million project is
expected to be complete in summer
2011.
MERIDIAN
- Interstate 84, Ten Mile Interchange construction
Work
continues on a project to construct a new interchange with on- and off-ramps at
Ten Mile Road. The project includes an extension of Tasa Road to connect with
Overland Road.
Ten Mile Road is closed
between Franklin and Overland roads during construction.
The $33.8 million project is
expected to be complete in summer
2011.
NAMPA - Franklin to 11th interstate
widening
Work has begun
on widening Interstate 84 to three lanes from Nampa's Franklin Boulevard to
Garrity Boulevard.
Beginning Sunday night (July 18), traffic on I-84 will be reduced to one lane
in each direction between the Franklin Interchange and 11th Avenue from 10 p.m.
until 5 a.m. The lane reduction will continue through Friday (July 23) and will
allow crews to clear the median, perform pipe work and prepare for widening
activities.
The project also includes replacement of the Union Pacific Railroad and Phyllis
Canal bridges. Bridge projects at Garrity and 11th are already under way to
accommodate the additional lanes on I-84.
When these improvements are complete, I-84 between the Franklin and Garrity
interchanges will be widened to three lanes in each direction, with an
additional auxiliary lane for eastbound traffic. The auxiliary lane will allow
motorists to enter I-84 at Franklin, remain in the lane furthest right, and
exit at Garrity - never having to merge with interstate traffic.
Construction is expected to be complete by early summer 2012.
Concrete
Placing Co. Inc., of Boise is the contractor on this $22.2 million project.
NAMPA - 11th Avenue Bridge
Work is progressing on the 11th Avenue
bridge over I-84 in Nampa.
Crews poured the first section of
concrete deck early today (Friday, July 16) for the new bridge. The early
morning work was needed to allow the concrete to harden while temperatures were
cool.
A second deck pour is scheduled for
early Monday morning (July 19). That pour, for the center portion of the bridge
deck, will start at 5 a.m. and will not impact traffic.
The 11th Avenue
Bridge closed to all traffic in May and will remain closed until late summer.
Reconstruction of the bridge is required to allow the addition of one lane in
each direction on I-84 between Franklin Boulevard and Garrity Boulevard. That
project began this week and is scheduled to be complete by early summer 2012.
The
bridge reconstruction and I-84 widening projects are among several interstate
improvements occurring in an 18-mile stretch of I-84, funded by the GARVEE
Transportation Program. The program uses proceeds from Grant Anticipation
Revenue Vehicle bonds.
McAlvain Civil Constructors the
contractor on the $4.1 million 11th Avenue Bridge project.
NAMPA - Interstate 84, Garrity
Interchange Bridge reconstruction
Construction
on the I-84 Garrity Interchange improvement project continues. The project will
replace two bridges on I-84 at the Garrity Interchange with a single bridge
that will accommodate three lanes in each direction on the interstate.
Work
also includes reconstructing the interstate about a mile east of the
interchange to tie into the widening of I-84 between the Garrity and Meridian
interchanges, and removing the bridge piers in the roadway at Garrity
Boulevard.
This
project is part of ITD's plans to improve I-84 between the Franklin and Garrity
interchanges in Nampa.
Heres
the weekly update on construction and traffic at the I-84 Garrity Interchange.
The main changes and configurations for traffic include:
- Garrity Boulevard will be closed overnight (10
p.m. to 5 a.m.) Friday and Saturday for the removal of the westbound bridge at
the I-84 Garrity Interchange.
Next Week, July 20 24, Snake River Stampede
(Rodeo)
- Flagging every night session of the event, but
not the Saturday matinee session. Traffic is expected to grow from about 7,000
vehicles per day to 8,500 vehicles per day as the event culminates.
The
completed improvements will include three lanes in each direction from the
Franklin to Garrity interchanges, and eventually four lanes in each direction
from the Garrity to Meridian interchanges.
The
project is being constructed in three stages:
Currently Under Way
Step
1 - Build the median section of the bridge between the existing bridges.
Traffic will remain on existing bridges, with two lanes open in each direction.
July 2010
Step
2 - Remove the existing westbound bridge and build a new westbound portion of
bridge. Westbound traffic will be moved onto the new median section. Two lanes
will remain open in each direction.
Tentatively starts Dec./Jan.
Step
3 - Remove the existing eastbound bridge and build a new eastbound portion of
bridge. Westbound traffic will be shifted onto the new westbound portion of the
bridge, and eastbound traffic onto the median section.
Completion - By summer 2011, three
lanes will be open in each direction over the bridge, eventually connecting
with a fourth lane in each direction east of the interchange.
Concrete
Placing Co. Inc., of Boise, is the contractor on the $15 million project.
Following
is an update on non-GARVEE state highway construction projects in southwest
Idaho.
ADA COUNTY
MERIDIAN - Eagle Road resurfacing
The resurfacing project on heavily traveled Eagle Road (Idaho 55)
is nearing completion.
Crews have
completed permanent pavement markings.
Some occasional nighttime lane closures will be necessary in the coming weeks
for installation of some permanent pavement markings and signs. In addition,
some final work will be done closer to the freeway later in July.
Central
Paving Co. Inc., of Boise, is the contractor on the $1.35 million project.
ADAMS COUNTY
S. OF COUNCIL - Indian Valley Road
repaving
The
resurfacing of about three miles of Indian Valley Road, south of Council in
Adams County, is now substantially complete.
The
2.8-mile section from the end of pavement to the intersection with West Indian
Valley Road was resurfaced to improve the driving surface and extend the life
of the road.
Adams
County is the local sponsor of the project.
The
project is located about 10 miles south of Council off of U.S. 95.
Knife
River Corp. Northwest, of Boise, is the contractor on the $349,000 project.
BOISE COUNTY
NORTH OF HORSESHOE BEND
HILL SUMMIT - spot repair
Repairs
to a slight depression on Idaho 55 on the north side of Horseshoe Bend Hill
continue.
Crews will shore up an area about 400 feet long near the Horseshoe
View Subdivision at milepost 60.4, which is about halfway down from the summit
on the Horseshoe Bend side of the hill. The work is expected
to be complete in August.
Crews have
milled and removed the old asphalt, and completed deep base repair on both ends
of the project. Next week (July 19-23), crews will prepare the road base for
asphalt, with paving scheduled to begin the following week.
This
section of roadway has settled about 18 inches since it was paved in the early
1980s. Crews will grind the pavement off, add about 1,500 cubic yards of road
base to restore the road level, re-compact it and pave over the new surface.
The damaged area extends across both directions of travel.
The speed limit will be reduced to 45 mph through the work zone. The road will
be reduced to one lane in each direction. ITD will separate the work zone from
traffic with concrete guardrail.
This $22,000 project will be done by State of Idaho forces, with assistance
from Western Construction for the rotomilling and Idaho Sand & Gravel on
the paving. Knife River is contracted to supply the road base material for
compaction.
CANYON COUNTY
CALDWELL - Franklin and 21st
reconstruction
The reconstruction of the intersection of
Franklin and 21st in Caldwell is nearing completion.
Crews are installing the poles for the
traffic signal at the Franklin Road/21st Avenue intersection. Once wiring work
is complete, the signal is expected to be operational late next week (July
19-23) and traffic will be allowed onto 21st Avenue, nearly two months ahead of
schedule.
Commercial Way between Specht and
Franklin is closed to through traffic. Franklin is closed while the roadway is
reconstructed and realigned to match up with the new five-lane roadway
constructed last summer. Motorists are detoured to 21st and Chicago
streets. Businesses on Franklin
can be accessed via Chicago.
The Franklin-21st intersection is about
one-quarter mile west of the newly reconstructed Franklin Interchange (Exit
29). The project will improve sight distance and safety on 21st and includes
new asphalt pavement, curb and gutter, sidewalk and lighting.
The first phase of this project, about a
quarter-mile section of 21st, was rebuilt last summer. The three-lane roadway
was widened to five lanes.
Central Paving Co. of Boise is the
contractor on this $1.66 million project. Central Paving also was the
contractor on the first phase of the project last summer.
GEM COUNTY
EMMETT - Main Street resurfacing
Work
is under way on a project to resurface and improve a mile of Main Street in Emmett.
The project is expected to be
finished in early October.
This
project, from the intersection of Boise Avenue to the intersection of
Washington Street (Idaho 52), includes pavement rehabilitation to remove
excessive rutting and cracking, with pothole repair and slope work included for
proper drainage. Sidewalks also will be replaced, maintaining the current
11-foot width, along with curb and gutter work.
Lighting
and adjustments to the traffic signal at the intersection of Main and
Washington also will be included.
The project is
complete on the south side. The contractor is currently building subgrade on
the north side.
WF
Construction & Sales LLC, of Meridian, is the contractor on this $475,000
project.
The city of Emmett is the local sponsor for this project.
ELMORE COUNTY
SOUTHWEST OF MOUNTAIN HOME - Road to
C.J. Strike Reservoir paving
The
Dam Cutoff Road carrying recreational traffic to the C.J. Strike Reservoir area
in Elmore County is being paved in a project now under way.
Crews are now
paving. Guardrail installation and restriping is scheduled for later in July,
after which the road can be opened. The project is running ahead of
schedule.
The
road will be closed during construction.
This
route is one way to get to C.J. Strike, but possibly the least-common route.
However, the improvements will make it a more desirable route and will shorten
the trip from Mountain Home to the dam.
The
Strike Dam Cutoff Road currently is a two-lane unpaved rural route in rolling
terrain. The project begins at the junction of Idaho 67 and extends about
one-quarter mile north of the C.J. Strike Dam, from about milepost 100 to 107.
The
paving is designed to provide a safer route and save on annual maintenance
costs.
Western
Construction Inc. of Boise is the contractor on the $1.86 million project.
This
project is locally sponsored by the Mountain Home Highway District.
OWYHEE COUNTY
DUCK VALLEY State Line to Sheep Creek
Road resurfacing
A
pavement resurfacing project on approximately 20 miles of Idaho 51, from the
Nevada State Line to Sheep Creek Road in Owyhee County, is now under way. The
project is expected to take until late
August to complete.
The work is about 70 miles south of Mountain Home and travels through the Duck
Valley Indian Reservation.
On
this two-lane road, the first 11.4-mile stretch will receive a thin overlay of
asphalt (about 1.8 inches) and the entire 20-mile area will be seal coated.
A
half-inch scrub coat, to mitigate cracking, also was applied to the first eight
miles this week
(July 12-16). Paving is expected to begin on Monday (July 19).
Traffic will be directed when necessary
by flaggers and pilot cars.
Valley Paving & Asphalt Co., of Cottonwood, is the contractor on this $1.92
million project.
PAYETTE COUNTY
WEST OF CALDWELL - I-84 resurfacing,
Black Canyon to Sand Hollow
The
pavement resurfacing and repair project on I-84 west of Caldwell continues. The
project, funded through stimulus savings, begins west of the Black Canyon
Interchange and extends for five miles, to east of the Sand Hollow Interchange.
As
it was last week, all traffic within the project area has been traveling on the
westbound side of the interstate for several weeks. Crews continue replacing
damaged concrete slabs, grinding concrete and installing new guardrail end
terminals on eastbound I-84. In late July, crews should complete slab repair on
the eastbound side and begin working in the westbound lanes.
During
the majority of the work, only one interstate lane will be open in both
directions.
The
speed limit is 45 mph over the median crossovers, and 55 mph between them.
The
project is expected to be complete this
fall.
Several
badly damaged concrete slabs in that stretch will be removed and replaced.
Repairs also will include resealing pavement joints, repairing pavement cracks
and chips, grinding portions off of the existing pavement surface and
completing guardrail safety improvements. Work will start in the eastbound
lanes (through July), then turn around and come back westbound.
A
highly competitive construction environment led to significant savings on the
eight original projects funded by the federal stimulus program ARRA (American
Recovery and Reinvestment Act). This is one of nine smaller projects financed
through those initial bid savings.
Multiple
Concrete Enterprises, of Ogden, Utah, is the contractor on the $6.9 million
project.
FRUITLAND, PAYETTE - pavement
resurfacing
Work is under way on several pavement rehabilitation projects
encompassing about six miles of U.S. 95 from north Fruitland to north Payette
as well as about one-half mile of U.S. 30 between the Snake River and
Fruitland. In addition to resurfacing, pavement cracks also will be filled
throughout the project area.
Standard work hours will be 7 a.m. to dusk Monday through Thursday, and to noon
on Friday. No weekend work is expected. There may be some overnight (10 p.m. to
5 a.m.) work when the contractor is working on the signalized intersections at
U.S. 95 and U.S. 30 (Gayway Junction) and the U.S. 95/95 Spur intersection
south of Payette. The traffic signals at those intersections will be upgraded
to video detection-based operating systems.
Crews are continuing to pave and mill
U.S. 95 in Fruitland and into Payette. Milling through Payette will require one
lane closure (in the three-lane section). Two-way traffic will be allowed to
continue through the work zone. Paving in Payette is not expected to start
until next week (July 12-16).
Crews are halfway finished doing work at
Gayway Junction, and will finish the second half overnight Monday (July 12).
Work will progress to the intersection in south Payette overnight Tuesday.
Knife River, of Boise, is the contractor on this $2.1 million
project.
Idaho 52, Idaho 72 Resurfacing
A resurfacing project is expected to
begin in late July on about 14 miles of rural highway on Idaho 52, from
Payette's east city limits to its junction with Idaho 72, and on Idaho 72, from
the junction with U.S. 30 to the junction with Idaho 52. The project is
expected to take about two months to complete, finishing in late September.
In addition to the thin overlay which will be applied to the roadway surface,
the project also includes guardrail upgrades.
Traffic
control is expected to consist of a pilot car and flaggers when needed.
Western Construction of Boise is the
contractor on this nearly $2 million project.
FRUITLAND - S. Pennsylvania Avenue
resurfacing
A
project to resurface South Pennsylvania Avenue in Fruitland is nearing completion.
The
project has entailed a mill and overlay (about two inches of the existing
surface will be removed, and replaced with two inches of new pavement) between
U.S. 95 and SW 4th Street.
Crews have been
working on minor items such as repairing sod, adjusting and cleaning manholes
and water valves, installing signs, and general clean-up this week (July
12-16). The project is anticipated to be finished this week with the exception
of installing school crossing signs and school zone signs.
South Pennsylvania Avenue is an integral part of the
transportation system for Fruitland. It is the only roadway access to the
Fruitland elementary and middle schools and also provides approach to the
Fruitland intermediate and high schools. The avenue also serves as a northbound
gateway into Fruitland.
The city of Fruitland is the local sponsor of this project, and also is
participating financially.
Irvco Asphalt & Gravel Inc., of Fruitland, is the contractor
on this $298,000 project.
PAYETTE U.S. 95, Payette River Bridge
replacement
The
project to improve the U.S. 95 bridge over the Payette River south of Payette is
expected to begin Monday (July 19). Once construction has started, it is
expected to take 20 months to complete, finishing in spring 2012.
Crews
will replace the existing northbound truss bridge (built in 1927) located on
U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher
off the water. It will have no overhead bracing or struts as the current one
does and will be 84 feet in width, eliminating current safety concerns
regarding both width and height restrictions.
The new
bridge will be constructed next to, and will attach to, the existing southbound
bridge. The project also includes minor roadway realignment to tie into the new
bridge location.
U.S. 95 is the main route connecting northern and southern Idaho. About 18,000
vehicles use this portion of the highway daily. By 2026, the volume is expected
to be more than 25,000.
Traffic will utilize the southbound bridge while the new bridge is constructed.
Traffic will then be switched to the new bridge while modifications to the
southbound bridge are made and it is connected to the new bridge.
JC Constructors Inc. of Meridian is the contractor for this $6.17 million
project.
WASHINGTON COUNTY
WEISER - Snake River Bridge replacement
The
project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser
is
wrapping up.
The
original bridge was built in 1903, with an additional span added in 1911.
Traffic signals were added in 1949. The bridge was replaced in the 1950s - that
one is being replaced in this project. Once completed, the bridge will be 16
feet wider and able to carry greater traffic volumes. The highway on both sides
of the bridge also will be reconstructed.
Sletten Construction of Boise is the contractor on this $10 million project.
The project is expected to be completed by
the end of the month.
ITD and the Idaho State Police caution
motorists to slow down and pay attention when driving in work zones, where
increased speeding fines and other penalties apply. Motorists are encouraged to
plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state
highway or interstate system.