Southwest Idaho highway construction report for July 30-Aug. 6
BOISE - The following projects are part of the GARVEE Transportation
Program in southwest Idaho, which uses funds from Grant Anticipation Revenue
Vehicle (GARVEE) bonds to expedite highway projects.
BOISE -
Interstate 84, Vista Avenue Interchange Reconstruction*
The new Single Point Urban Interchange
traffic light was activated at the Vista Interchange last week. ITD is
finishing the last stage of reconstruction on the interchange. The project will
reduce congestion and accommodate more lanes on I-84.
Airport Way will be reduced to one lane
in both directions until early August.
The new left-turn lanes on Vista Avenue
will remain closed while ITD finishes paving and constructing center islands.
All lanes are expected to be open in late August.
The speed limit
on I-84 is 55 mph and shoulders are restricted in the project area. The speed
limit on Vista Avenue is 25 mph. ITD advises motorists to be cautious of trucks
and equipment.
Construction on the $17.8 million project
is expected to be complete in late
summer or early fall 2010.
* Design for the project was funded by
GARVEE, but project construction is funded through the federal stimulus
program, created to generate jobs and help boost Idaho's economy while
upgrading our foundation for future economic growth.
BOISE -
Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and
westbound I-84 between the Cole and Broadway interchanges in Boise. When
complete, the interstate will have four lanes in each direction.
ITD
will open a fourth lane on westbound I-84 just west of the Orchard Interchange
on Wednesday morning (Aug. 4) at 5 a.m.
Between
the Cole and Broadway interchanges, one east- and westbound lane will continue
to have intermittent lane closures overnight (10 p.m. to 5 a.m. on week nights,
and 10 p.m. to 7 a.m. on weekends) Aug. 2 to Aug. 17.
Crews will pave new lanes in the median
during the closures.
This $35.9 million project is expected to
be complete in summer 2011.
MERIDIAN -
Interstate 84, Ten Mile Interchange construction
Work
continues on a project to construct a new interchange with on- and off-ramps at
Ten Mile Road. The project includes several improvements to Ten Mile Road.
Ten Mile Road is closed between Franklin
and Overland roads during construction.
The $33.8 million project is expected to
be complete in summer 2011.
NAMPA - Franklin to 11th interstate
widening
Work is under
way to widen Interstate 84 to three lanes from Nampa's Franklin Boulevard to
Garrity Boulevard.
Nighttime lane closures are expected through August.
The project also includes replacement of the Union Pacific Railroad and Phyllis
Canal bridges. Bridge projects at Garrity and 11th are already under way to
accommodate the additional lanes on I-84.
When these improvements are complete, I-84 between the Franklin and Garrity
interchanges will be widened to three lanes in each direction, with an
additional auxiliary lane for eastbound traffic. The auxiliary lane will allow
motorists to enter I-84 at Franklin, remain in the lane furthest right, and
exit at Garrity - never having to merge with interstate traffic.
Construction is expected to be complete by early summer 2012.
Concrete
Placing Company, of Boise is the contractor on this $22.2 million project.
NAMPA - 11th Avenue Bridge
Work is progressing on the 11th Avenue
bridge over I-84 in Nampa.
The
bridge deck pours are now complete.
The 11th Avenue
Bridge closed to all traffic in May and will remain closed until late summer.
Reconstruction of the bridge is required to allow the addition of one lane in
each direction on I-84 between Franklin Boulevard and Garrity Boulevard. That
project began this week and is scheduled to be complete by early summer 2012.
The bridge reconstruction and I-84 widening projects are
among several interstate improvements occurring in an 18-mile stretch of I-84,
funded by the GARVEE Transportation Program. The program uses proceeds from
Grant Anticipation Revenue Vehicle bonds.
McAlvain
Civil Constructors the contractor on the $4.1 million 11th Avenue Bridge
project.
NAMPA - Interstate 84, Garrity
Interchange Bridge reconstruction
Construction
on the I-84 Garrity Interchange improvement project continues. The project will
replace two bridges on I-84 at the Garrity Interchange with a single bridge
that will accommodate three lanes in each direction on the interstate.
Work
also includes reconstructing the interstate about a mile east of the
interchange to tie into the widening of I-84 between the Garrity and Meridian
interchanges, and removing the bridge piers in the roadway at Garrity
Boulevard.
I-84
westbound traffic will shift to the south and be reduced to two lanes between
the Robinson Road Overpass and the Garrity Interchange starting Saturday night
(July 31). The ramp relocation will begin at 10 p.m., and be completed by 5
a.m. Sunday morning (Aug. 1). Motorists wanting to exit at Garrity will enter a
newly constructed temporary off-ramp three-quarters of a mile closer to the
interchange than the current exit ramp.
This
project is part of ITD's plans to improve I-84 between the Franklin and Garrity
interchanges in Nampa.
The
completed improvements will include three lanes in each direction from the
Franklin to Garrity interchanges, and eventually four lanes in each direction
from the Garrity to Meridian interchanges.
The
project is being constructed in three stages:
Currently Under Way
Step
1 - Build the median section of the bridge between the existing bridges.
Traffic will remain on existing bridges, with two lanes open in each direction.
Step
2 - Remove the existing westbound bridge and build a new westbound portion of
bridge. Westbound traffic will be moved onto the new median section. Two lanes
will remain open in each direction.
Tentatively starts Dec./Jan.
Step
3 - Remove the existing eastbound bridge and build a new eastbound portion of
bridge. Westbound traffic will be shifted onto the new westbound portion of the
bridge, and eastbound traffic onto the median section.
Completion - By summer 2011, three lanes
will be open in each direction over the bridge, eventually connecting with a
fourth lane in each direction east of the interchange.
Concrete
Placing Co. Inc., of Boise, is the contractor on the $15 million project.
Following
is an update on non-GARVEE state highway construction projects in southwest
Idaho.
ADA COUNTY
MERIDIAN - Eagle Road resurfacing
The
resurfacing project on heavily traveled Eagle Road (Idaho 55) is nearing
completion.
Crews have
completed permanent pavement markings.
Some occasional nighttime lane closures will be necessary in the coming weeks
for installation of some permanent pavement markings and signs. In addition,
some final work will be done closer to the freeway later in July/August.
Central
Paving Co. Inc., of Boise, is the contractor on the $1.35 million project.
BOISE - Broadway Avenue resurfacing
A resurfacing project on Broadway Avenue
(U.S. 20) from the Ridenbaugh Canal to the south side of the I-84 junction is
under way The project is expected to finish in late August.
Work
has begun and the contractor has milled
the roadway surface (ground off the top layer) on Broadway Avenue from the New York
Canal to Federal Way (including the Federal Way ramps).
They are now in
the process of paving this same area.
The contractor
is going to reconstruct the approaches to the I-84 bridge and intersections of
the I-84 ramps starting on Aug. 6 at 10 p.m. and will work through the weekend
until Monday at 5 a.m. Work in this area will require that Broadway be closed
to one lane in each direction and one of the I-84 ramps to be closed at a time
while work is done in the intersections.
Ramp traffic
will be detoured to Gowen and Vista interchanges during the closures.
Work on the
approaches and intersections will take place over three consecutive weekends,
with Broadway and the ramps completely open during weekday daytime hours. The
ramps will only be closed on weekends.
During this project, the top three inches
of pavement will be milled off the surface and replaced. Sections of the
roadway are deteriorated, cracked and rutted. The project will extend the life
of the roadway and result in a smoother ride.
Work will then proceed to the interchange bridge, tentatively starting in late
July and progressing for three consecutive weekends. This work will follow a 9
p.m. Friday to 5 a.m. Monday weekend schedule. Only one ramp at a time will be
closed during this stage of the project, but ramp closures will last for the
duration of each weekend during this construction phase.
All efforts will be made to maintain cross street and business access; however,
temporary closures can be expected as the paving process moves through the
project. The Federal Way ramps will not be closed during the day, but
intermittent closures of the Federal Way ramps will be in place on select
evenings. Detours will be established and advanced warning given prior to the
intermittent closures.
Crews also will be updating the traffic signals at the Federal Way and I-84
ramps to include a video-detection system.
Broadway was resurfaced from Rossi Street to the Ridenbaugh Canal in fall 2008,
including pedestrian ramp reconstruction. Broadway was resurfaced from the
Boise River Bridge to Rossi Street in summer 2003.
Central Paving Co., of Boise, is the contractor on this $556,000 project.
BOISE COUNTY
NORTH OF HORSESHOE BEND HILL SUMMIT -
spot repair
Repairs
to a slight depression on Idaho 55 on the north side of Horseshoe Bend Hill
continue.
Crews
will shore up an area about 400 feet long near the Horseshoe View Subdivision
at milepost 60.4, which is about halfway down from the summit on the Horseshoe
Bend side of the hill. The work is expected to be complete in August.
The northbound
lanes have been paved, and crews are improving the shoulders and installing
temporary lines. Starting next week (Aug. 2-6), crews will prepare to start
work on the next section just north, at milepost 60.6.
This
section of roadway has settled about 18 inches since it was paved in the early
1980s. Crews will grind the pavement off, add about 1,500 cubic yards of road
base to restore the road level, re-compact it and pave over the new surface.
The damaged area extends across both directions of travel.
The speed limit will be reduced to 45 mph through the work zone. The road will
be reduced to one lane in each direction. ITD will separate the work zone from
traffic with concrete guardrail.
This $22,000 project will be done by State of Idaho forces, with assistance
from Western Construction for the rotomilling and Idaho Sand & Gravel on
the paving. Knife River is contracted to supply the road base material for
compaction.
Lowman to Banner Creek Summit seal coat
now under way
A seal coat covering
nearly 30 miles of Idaho 21 began July 27 from Lowman to Banner Creek Summit.
This is a two-step seal coat from milepost 70.7 to 91.6 and from 97.5 to 105.5.
A future project will address the segment between the two.
No work will be
performed on Friday, Saturday and Sunday. The project is expected to be
complete by the end of next week (Aug. 2-6).
During
construction, motorists can expect slight delays as crews spray liquid asphalt
on the highway and spread a layer of crushed rock over it.
Kloepfer Construction Inc., of Paul, is the contractor on this $1.36 million
project.
GEM COUNTY
EMMETT - Main Street resurfacing
Work
is under way on a project to resurface and improve a mile of Main Street in
Emmett. The project is expected to
be finished in early October.
This
project, from the intersection of Boise Avenue to the intersection of
Washington Street (Idaho 52), includes pavement rehabilitation to remove
excessive rutting and cracking, with pothole repair and slope work included for
proper drainage. Sidewalks also will be replaced, maintaining the current
11-foot width, along with curb and gutter work.
Lighting
and adjustments to the traffic signal at the intersection of Main and
Washington also will be included.
Work continues
on the north side of Main Street. Curb and gutter have been installed. Work
resumes on the patterned sidewalk and illumination planters.
WF
Construction & Sales LLC, of Meridian, is the contractor on this $475,000
project.
The city of Emmett is the local sponsor for this project.
A pair of pavement-preservation projects
near Emmett are expected to begin soon:
Ola Highway, Kirkpatrick Road North
Extending into mid-August, crews will be working on a 3.7-mile pavement
preservation of Ola Highway, a two-lane rural roadway that runs north and south
starting at Kirkpatrick Road and proceeding north. This is a stimulus-funded
overlay.
Paving could begin as soon as Tuesday
(Aug. 3)
Gem County is the local sponsor of the Local Highway Technical Assistance
Council project.
C&A Paving Company, of Boise, is the contractor on this $385,000
project.
Idaho
52, Emmett to Sweet-Ola Highway sealcoat
A 13-mile stretch of Idaho 52 from Emmett to the junction with the Sweet-Ola
Highway will be seal coated starting Aug. 2. The project is expected to last six
days.
The seal coat will work from east to west.
The seal coat, from milepost 31.8 to milepost 45, will protect the existing
roadway against water damage, add traction to
the surface and prolong the highways life.
During construction, motorists can expect slight delays as crews spray liquid
asphalt on the highway and spread a layer of crushed rock over it.
Travel will be reduced to one lane in each direction, with flaggers directing
traffic through the work zones. The speed limit in work areas will be reduced
to 35 mph.
Kloepfer Inc., of Paul, is the contractor on this $994,000 project.
ELMORE COUNTY
SOUTHWEST OF MOUNTAIN HOME - Road to
C.J. Strike Reservoir paving
The
Dam Cutoff Road carrying recreational traffic to the C.J. Strike Reservoir area
in Elmore County is being paved in a project now under way.
Paving,
striping and guardrail for the new road are complete. The road is slated to
re-open by Aug. 1. Delineation and signing still remain. The project is
running ahead of schedule.
The
road will be closed during construction.
This
route is one way to get to C.J. Strike, but possibly the least-common route.
However, the improvements will make it a more desirable route and will shorten
the trip from Mountain Home to the dam.
The
Strike Dam Cutoff Road currently is a two-lane unpaved rural route in rolling
terrain. The project begins at the junction of Idaho 67 and extends about
one-quarter mile north of the C.J. Strike Dam, from about milepost 100 to 107.
The
paving is designed to provide a safer route and save on annual maintenance costs.
Western
Construction Inc. of Boise is the contractor on the $1.86 million project.
This
project is locally sponsored by the Mountain Home Highway District.
OWYHEE COUNTY
DUCK VALLEY State Line to Sheep Creek
Road resurfacing
A
pavement resurfacing project on approximately 20 miles of Idaho 51, from the
Nevada State Line to Sheep Creek Road in Owyhee County, is now under way. The
project is expected to take until late
August to complete.
Mainline and approach paving
have been completed. There will be a week-long curing period prior to the seal
coat application. The seal coat is expected to start the week of Aug. 9. This
operation should only take one week.
The
work is about 70 miles south of Mountain Home and travels through the Duck
Valley Indian Reservation.
On
this two-lane road, the first 11.4-mile stretch will receive a thin overlay of
asphalt (about 1.8 inches) and the entire 20-mile area will be seal coated.
A
half-inch scrub coat, to mitigate cracking, was applied to the first eight miles. Crews are
waiting for the scrub coat to cure, and will resume paving operations on
Monday. All lanes are open to traffic, but the speed limit is still
reduced to 45 mph.
Traffic will be directed when necessary
by flaggers and pilot cars.
Valley Paving & Asphalt Co., of Cottonwood, is the contractor on this $1.92
million project.
PAYETTE
COUNTY
WEST OF CALDWELL - I-84 resurfacing, Black Canyon to Sand Hollow
The pavement resurfacing
and repair project on I-84 west of Caldwell continues. The project, funded
through stimulus savings, begins west of the Black Canyon Interchange and
extends for five miles, to east of the Sand Hollow Interchange.
Traffic
has been switched over to the eastbound side and will remain there until mid-
to late September. The contractor is working on the westbound side now. All
work, with the exception of approach work to the concrete and some ramp
approach work, is done on the eastbound side.
Crews continue replacing damaged concrete slabs, grinding concrete and installing
new guardrail end terminals on eastbound I-84. By the end of this month, crews
should complete slab repair on the eastbound side and begin working in the
westbound lanes.
During the majority of the work, only one interstate lane will be open in both
directions.
The speed limit is 45 mph over the median crossovers, and 55 mph between them.
The project is expected to be complete
this fall.
Several badly damaged concrete slabs in that stretch will be removed and
replaced. Repairs also will include resealing pavement joints, repairing
pavement cracks and chips, grinding portions off of the existing pavement
surface and completing guardrail safety improvements.
A highly competitive construction environment led to significant savings on the
eight original projects funded by the federal stimulus program ARRA (American
Recovery and Reinvestment Act). This is one of nine smaller projects financed
through those initial bid savings.
Multiple Concrete Enterprises, of Ogden, Utah, is the contractor on the $6.9
million project.
FRUITLAND, PAYETTE - pavement
resurfacing
Work
is under way on several pavement rehabilitation projects encompassing about six
miles of U.S. 95 from north Fruitland to north Payette as well as about
one-half mile of U.S. 30 between the Snake River and Fruitland. In addition to
resurfacing, pavement cracks also will be filled throughout the project area.
Standard work hours will be 7 a.m. to dusk Monday through Thursday, and to noon
on Friday. No weekend work is expected. There may be some overnight (10 p.m. to
5 a.m.) work when the contractor is working on the signalized intersections at
U.S. 95 and U.S. 30 (Gayway Junction) and the U.S. 95/95 Spur intersection
south of Payette. The traffic signals at those intersections will be upgraded
to video detection-based operating systems.
Crews completed paving through Payette
this week (July 19-23). Approach paving (public and private) has been completed
to the 7th Avenue North intersection in Payette. The remaining approaches will
be paved next week (July 26-30). Speed limit reductions will remain in place
until all work is completed.
The contractor is expecting to have
approximately five to six days of bump grinding, followed by restriping.
Knife
River, of Boise, is the contractor on this $2.1 million project.
Idaho 52, Idaho 72 Resurfacing
A
resurfacing project is expected to begin in late July on about 14 miles of
rural highway on Idaho 52, from Payette's east city limits to its junction with
Idaho 72, and on Idaho 72, from the junction with U.S. 30 to the junction with
Idaho 52. The project is expected to take about two months to complete,
finishing in late September.
In addition to the thin overlay to be applied to the roadway surface, the
project also includes guardrail upgrades.
Traffic control is expected to consist of a pilot car and
flaggers when needed.
Crews
continue paving. Idaho 52 should be resurfaced by the end of next week (Aug.
2-6).
Western
Construction of Boise is the contractor on this nearly $2 million project.
FRUITLAND - S. Pennsylvania Avenue
resurfacing
A
project to resurface South Pennsylvania Avenue in Fruitland is nearing
completion.
The
project has entailed a mill and overlay (about two inches of the existing
surface will be removed, and replaced with two inches of new pavement) between
U.S. 95 and SW 4th Street.
Crews have been
working on minor items such as repairing sod, adjusting and cleaning manholes
and water valves, installing signs, and general clean-up this week (July
12-16). The project is anticipated to be finished this week with the exception
of installing school crossing signs and school zone signs.
South
Pennsylvania Avenue is an integral part of the transportation system for
Fruitland. It is the only roadway access to the Fruitland elementary and middle
schools and also provides approach to the Fruitland intermediate and high
schools. The avenue also serves as a northbound gateway into Fruitland.
The city of Fruitland is the local sponsor of this project, and also is participating
financially.
Irvco
Asphalt & Gravel Inc., of Fruitland, is the contractor on this $298,000
project.
PAYETTE U.S. 95, Payette River Bridge
replacement
The project to
improve the U.S. 95 bridge over the Payette River south of Payette is now under
way. It is expected to take about two years to complete, finishing in fall
2012.
Crews will replace the existing northbound truss bridge (built in 1927) located
on U.S. 95 between Fruitland and Payette. The new bridge will be two feet
higher off the water. It will have no overhead bracing or struts as the current
one does and will be 84 feet in width, eliminating current safety concerns
regarding both width and height restrictions.
The new bridge will be constructed next to, and will attach
to, the existing southbound bridge. The project also includes minor roadway
realignment to tie into the new bridge location.
U.S. 95 is the main route connecting northern and southern Idaho. About 18,000
vehicles use this portion of the highway daily. By 2026, the volume is expected
to be more than 25,000.
Traffic will utilize the southbound bridge while the new bridge is constructed.
Traffic will then be switched to the new bridge while modifications to the
southbound bridge are made and it is connected to the new bridge.
Two-way traffic
has been switched onto the southbound bridge and all traffic control is in
place for the project from Fruitland to Payette. Crews are making preparations,
including the demolition of minor existing structures. Setup of the cofferdam
a temporary steel structure allowing water to be pumped out and replaced by
air, creating a dry work environment - is scheduled to begin in early August,
along with removal of the bridge deck from the truss bridge.
JC Constructors Inc. of Meridian is the contractor for this $6.17 million
project.
VALLEY
COUNTY
Idaho
55, Donnelly North City Limits to Deinhard Lane in McCall
An 11-mile pavement preservation/resurfacing project between Donnelly's north
city limit and Deinhard Lane on the southern end of McCall is expected to begin
Aug. 2, using the Cement Recycled Asphalt Base Stabilization (CRABS)
resurfacing method. The existing surface will be removed, crushed and mixed
with cement, then reapplied to the highway as a base for the new surface.
The project is expected to take about two months. During construction, one lane
will be closed in the project area, with flaggers directing traffic.
The work from milepost 132 to 143 also involves some drainage work.
Idaho 55, Gold Dust Road Turn Bay, south of Cascade
Work is expected to begin Aug. 9 to construct a left-turn bay on Idaho 55 for Gold
Dust Road, about 1.5 miles south of Cascade. The roadway will be widened in
that location (milepost 112) to accommodate the turning lane.
The project is expected to take about a month. During construction, one lane
will be closed in the project area, with flaggers directing traffic.
Knife River Corp., of Boise, is the contractor for both projects. The Gold Dust
Road Turn Bay is a $177,000 project, and the Donnelly to Deinhard contract is
$3.6 million.
WASHINGTON COUNTY
WEISER - Snake River Bridge replacement
The
project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser
is
nearly finished.
The
original bridge was built in 1903, with an additional span added in 1911.
Traffic signals were added in 1949. The bridge was replaced in the 1950s - that
one is being replaced in this project. Once completed, the bridge will be 16
feet wider and able to carry greater traffic volumes. The highway on both sides
of the bridge also will be reconstructed.
Sletten Construction, of Boise, is the contractor on this $10 million project.
The project is expected to be completed by
the end of the month. Final clean-up items continue until then.
ITD and the Idaho State Police caution
motorists to slow down and pay attention when driving in work zones, where
increased speeding fines and other penalties apply. Motorists are encouraged to
plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state
highway or interstate system.