Chinden seal coat may cause significant delays Saturday

BOISE - The ongoing seal-coating project on Chinden Boulevard (U.S. 20/26) may result in significant delays for residents traveling east to the Western Idaho Fair Saturday, or traveling west to the Caldwell Night Rodeo in the evening. The seal coat will extend the life of the roadway and provide greater traction for motorists.

 

Delays of up to 20 minutes are expected as traffic volumes increase throughout the day. Pilot cars and flaggers will be used to guide traffic.

 

Crews will work on the section between Aviation Way and Middleton Road on the Caldwell end of the project Saturday morning at 8 a.m.. Work also will include the addition of turnbays at four intersections with Chinden at KCID Road, Northside Boulevard, Midland Boulevard and Can-Ada Road. All four locations have significant accident histories. The KCID/Chinden intersection is on the High Accident Location list for the Southwest Idaho region.

 

Crews are planning to then return to work on the section from Locust Grove east to Eagle Road on Sunday, finishing the entire 15-mile Chinden Boulevard work completely by Monday. This will allow them to start seal coating on Idaho 55 from the overhead message sign at Shadow Valley Golf Course to Horseshoe Bend's south city limits on Tuesday (Aug. 24). That project spans about 13 miles, and is expected to finish by early September.

 

Seal coating begins by applying a layer of asphalt, then a cover coat of gravel on the roadway surface. The highway is rolled and traffic allowed on to the roadway to help pack the surface before "brooming" or sweeping to remove excess gravel. A properly applied seal coat can add several years of service to a heavily traveled roadway by sealing the surface and adding roughness for winter traction.

The work is done during the day to allow extreme heat to help asphalt and rock bond more quickly to the roadway surface, providing a higher-quality finished product.

 

Kloepfer Inc., of Paul, is the contractor on the $1.9 million projects.

 
+