Idaho 78 resurfacing from Murphy south to begin Sept. 2

BOISE - A resurfacing project on rural Idaho 78, from Murphy south for about eight miles, is expected to begin Sept. 2, the Idaho Transportation Department advises. The project is expected to finish by late September.

Crews plan to begin paving Sept. 2, then resume Sept. 7 after the Labor Day weekend holiday. The surface of the two-lane road will receive a 1.8-inch thin-lift overlay, to extend the life of the roadway and provide a smoother ride for motorists.  
 
During the overlay, traffic will be restricted to one lane. Flaggers will guide traffic. The speed limit will be reduced to 45 mph.
 
This stretch of roadway was last improved with a CRABS (Cement Recycled Asphalt Base Stabilization) resurfacing project in 1997.
 
Central Paving Co., of Boise, is the contractor on this $958,000 project.

 
+