Southwest Idaho highway construction report for Aug. 27-Sept. 3

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Vista Avenue Interchange Reconstruction*

ITD is finishing the last stage of reconstruction on the Vista interchange. The project will reduce congestion and accommodate more lanes on I-84. 

 

The speed limit on I-84 is 55 mph and shoulders are restricted in the project area. The speed limit on Vista Avenue is 25 mph. ITD advises motorists to be cautious of trucks and equipment.

 

Construction on the $17.8 million project is expected to be complete within a few weeks.

 

* Design for the project was funded by GARVEE, but project construction is funded through the federal stimulus program, created to generate jobs and help boost Idaho's economy while upgrading the states foundation for future economic growth.

 

BOISE - Interstate 84, Cole Road to Broadway Avenue widening

ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

Beginning at the Broadway Interchange, all westbound traffic will be shifted to the eastbound side of I-84 on Friday (Aug. 27).

 

Motorists bound for the Vista or Orchard interchanges will use a new temporary ramp lane at the Broadway Interchange.

 

Traffic will be in this configuration for the next six months. The speed limit on the temporary exit lane is 45 mph and for I-84 westbound through traffic it is 55 mph.

 

For more information on the traffic shiftn go to itd.idaho.gov/projects/d3 and click on I-84, Cole to Broadway Interchange Project.

 

This $35.9 million project is expected to be complete in summer 2011.

 

MERIDIAN - Interstate 84, Ten Mile Interchange construction

Work continues on a project to construct a new interchange with on- and off-ramps at Ten Mile Road. The project includes several improvements to Ten Mile Road.

 

Motorists can expect intermittent nighttime lane restrictions next week (Aug. 30-Sept. 3) during paving work at the interchange ramps. One lane will be closed overnight between 10 p.m. and 5 a.m. All lanes will be open during the day.

Ten Mile Road is closed between Franklin and Overland roads during construction.

The $33.8 million project is expected to be complete in summer 2011.

 

NAMPA - Franklin to 11th interstate widening

The Idaho Transportation Department will shift eastbound Interstate 84 traffic between Franklin Boulevard and the Garrity Boulevard Interchange in Nampa to newly constructed temporary lanes between 10 p.m. Sunday (Aug. 29) and 5 a.m. Monday (Aug. 30).
 
The traffic shift is planned during weekend nighttime hours, so that the new traffic configuration is in place by the morning commute.

This new traffic pattern will allow crews to begin construction work in the median area.

Motorists are advised to expect ongoing nighttime lane reductions on westbound I-84 between Franklin Boulevard and 11th Avenue between 10 p.m. and 5 a.m., Sunday evenings through Friday mornings. This allows crews to safely work along the shoulder, excavating, grading and performing pipe work.
 
The project includes also replacement of the Union Pacific Railroad (UPRR) and Phyllis Canal bridges. A portion of the UPRR Bridge is slated for demolition in early September, and a portion of the Phyllis Canal is slated for demolition in October, after the irrigation season is complete. Bridge projects at Garrity and 11th also are under way to accommodate the additional lanes on I-84.

Construction is expected to be complete by early summer 2012.

 

Concrete Placing Company of Boise is the contractor on this $22.2 million project.
 
Once these interstate improvements are complete, I-84 between the Franklin and Garrity interchanges will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the lane farthest right, and exit at Garrity without having to merge with interstate traffic.

 

NAMPA 11th Avenue Bridge

Work on the Interstate 84, 11th Avenue Bridge in Nampa is nearing completion.
 
Paving on 11th Avenue
On Thursday, crews paved 11th Avenue approaching the south side of the bridge. Paving on the north side is scheduled for today (Friday, Aug. 27).  
 
For all paving, expect delays when paving and roller equipment are in the area. Access to driveway or parking lot entryways will be restricted throughout the day.
 
Visitors to nearby businesses should plan to take alternate routes if possible, and be prepared for the delays.
 
On Monday (Aug. 30), crews will pave the bridge approaches. No traffic delays are expected. Crews will paint lane stripes next week, and the bridge is expected to be open to traffic before Labor Day weekend.
 
I-84 Overnight Lane Reductions
Early next week, crews will remove brackets and temporary structures used to support the bridge during the construction process. Overnight lane reductions on I-84 near the 11th Avenue Bridge will be necessary to allow crews to safely remove these materials:
 

- Monday night (Aug. 30) beginning at 10 p.m., lanes will be reduced for eastbound traffic. This work will be complete by 5 a.m. Tuesday morning (Aug. 31).

 

- On Tuesday night, also beginning at 10 p.m., lanes will be reduced for westbound traffic, and reopen by 5 a.m. Wednesday morning (Sept. 1).


Motorists are advised to use extra caution in the work zone.
 
On the bridge, the placement of sidewalk, curb and gutter, and installation of fence and light poles are complete. Some additional work, including minor clean-up and final construction activities, are anticipated to be complete by mid-September. Until then, minor traffic impacts may be expected.
 
McAlvain Civil Constructors is the contractor on the $4.1 million 11th Avenue Bridge project.
 
The 11th Avenue Bridge closed to all traffic in May. Reconstruction of the bridge was required to allow the addition of one lane in each direction on I-84 between Franklin Boulevard and Garrity Boulevard. That project is under way and is scheduled to be complete by early summer 2012.
 
 
NAMPA - Interstate 84, Garrity Interchange Bridge reconstruction

Construction on the I-84 Garrity Interchange improvement project continues. The project will replace two bridges on I-84 at the Garrity Interchange with a single bridge that will accommodate three lanes in each direction on the interstate.

 

Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.

 

Upcoming traffic changes include:
- Placing bridge girders on the westbound side is scheduled for Sunday night, (Sept. 12). This work will need an overnight (10 p.m. Sunday to 5 a.m. Monday) closure of Garrity Boulevard between the ramps (under the bridge only). The ramps will remain open.

- Reducing the westbound shoulder to 5 ft. from Robinson Road Overpass to Garrity Interchange. This should be in this configuration for a few weeks while crews place concrete. Emergency stopping through this area will be hazardous to motorists.

 

This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa.

 

The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and eventually four lanes in each direction from the Garrity to Meridian interchanges.

 

The project is being constructed in three stages:

 

Currently Under Way

Step 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Step 2 - Remove the existing westbound bridge and build a new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

Tentatively starts Dec./Jan.

Step 3 - Remove the existing eastbound bridge and build a new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.

 

Concrete Placing Co. Inc., of Boise, is the contractor on the $15 million project.

 

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

 

BOISE COUNTY

Seal coat from Overhead Message Board to Horseshoe Bend

Seal coating is under way on Idaho 55 from the overhead message sign just north of the Shadow Valley Golf Course to Horseshoe Bend's south city limits, a distance of about 13 miles. Work is expected to finish by early September.

 

Traffic will be controlled by a pilot car. Motorists can expect delays of up to 20 minutes.

 

Crews will work a 9 a.m. to 4 p.m. weekday schedule on both projects.
 

Speed limits will be reduced to 35 mph. Traffic will be controlled by lane closures, lane restrictions or pilot cars. No work is allowed from 6 a.m. on Friday morning through 7 a.m. on Monday morning.  

Seal coating begins by applying a layer of asphalt, then a cover coat of gravel on the roadway surface. The highway is rolled and traffic allowed on to the roadway to help pack the surface before "brooming" or sweeping to remove excess gravel. A properly applied seal coat can add several years of service to a heavily traveled roadway by sealing the surface and adding roughness for winter traction.


The work is done during the day to allow extreme heat to help asphalt and rock bond more quickly to the roadway surface, providing a higher-quality finished product.

 

Kloepfer Inc., of Paul, is the contractor on the $1.9 million projects.

 

CANYON COUNTY

MIDDLETON- road improvement projects

Crews are working on two road improvement projects in Middleton: Widening a .3-mile section of North Middleton Road from Idaho 44 to Mill Slough (north of Main Street) and realigning a .15-mile section of Cemetery Road, from Idaho 44 to 3rd Street.

 

Most work will be performed during the weekdays, though crews may work on Saturdays as needed. Work hours are limited to 8 a.m. 7 p.m.

 

During construction the contractor will establish detours around the project areas, using local roads. Work is planned to be complete in late December.

 

North Middleton Road

North Middleton Road is closed to through traffic and open to local residents only. Non-resident motorists driving around road closure signs may be ticketed.

 

Idaho Power crews will start relocating power poles beginning Monday (Aug. 30). Also, Intermountain Gas crews are scheduled to lower gas main lines beginning Sept. 2, and will likely continue after Labor Day. No service interruptions are anticipated with this utility work.

 

The Middleton Road widening will include one lane in each direction, a center turn lane, sidewalks, curb and gutter.

 

Cemetery Road

A .15-mile section Cemetery Road will be realigned, extending from Idaho 44 to 3rd Street.

 

This will result in a section of Cemetery Road becoming a residential cul-de-sac off of Idaho 44; the cul-de-sac will be renamed North Highland Court. Crews are currently working on storm drains and manholes.

 

To accommodate the growing demand on this section of roadway, crews will widen the road in that area to include wider roadways, center turn lanes, curb, gutter and sidewalk.

 

Traffic on this stretch of road is projected to grow from nearly 3,900 vehicles per day in the most recent count (Oct. 2006) to 11,200 per day by 2035.

 

Mill Creek Elementary School is on Middleton Road within the construction area, so the project also will promote pedestrian and student safety with improved sidewalks and crosswalks.

 

Work is planned to be complete in late December.

 

Nampa Paving & Asphalt Co. is the contractor on this $884,000 combined project.

 

GEM COUNTY

EMMETT - Main Street resurfacing

Work is finishing on a project to resurface and improve a mile of Main Street in Emmett.

 

This project, from the intersection of Boise Avenue to the intersection of Washington Street (Idaho 52), includes pavement rehabilitation to remove excessive rutting and cracking, with pothole repair and slope work included for proper drainage. Sidewalks also will be replaced, maintaining the current 11-foot width, along with curb and gutter work.

 

Lighting and adjustments to the traffic signal at the intersection of Main and Washington also are included.

 

A ribbon-cutting ceremony is planned for next Friday (Aug. 27).

 

WF Construction & Sales LLC, of Meridian, is the contractor on this $475,000 project.


The city of Emmett is the local sponsor for this project.

 

OWYHEE COUNTY

HOMEDALE U.S. 95 paving from Idaho 55 to South City Limits

A 7.3-mile pavement rehabilitation project on U.S. 95 from the junction with Idaho 55 to the South City Limits of Homedale is under way.

 

It is expected to be completed in late September.

 

The project will use the CRABS (Cement Recycled Asphalt Base Stabilization) method of pavement rehabilitation. In addition, existing guardrail will be upgraded, shoulder rumble strips installed for the length of the project and an additional width (up to two feet) added to each side of the roadway

 

A project by State maintenance forces this spring added to the gravel shoulders in that area in preparation for this project.

 

This project also will be coupled with a thin-lift overlay resurfacing (1.8 inches of new pavement) from the Marsing Port of Entry to the junction with Idaho 55, about an 8.5-mile stretch.

 

Next week (Aug. 23-27), crews will continue pavement pulverization and start the CRABS process. Paving may begin early next week.The width is restricted to 10 feet and will the speed limit will be lowered to 35 mph. Flaggers and a pilot car will be used throughout the project.

 

PAYETTE COUNTY
WEST OF CALDWELL - I-84 resurfacing, Black Canyon to Sand Hollow
The pavement resurfacing and repair project on I-84 west of Caldwell continues. The project, funded through stimulus savings, begins west of the Black Canyon Interchange and extends for five miles, to east of the Sand Hollow Interchange.
 

Crews finished the concrete slab replacement this week. The dowel bar retrofit - a method of reinforcing cracks in highway pavement by inserting steel dowel bars in slots cut across the cracks - is still ongoing, as is pavement grinding. Next week (Aug. 23-27) crews will repave the asphalt on the interstate right at the approaches to the concrete section.

 

During the majority of the work, only one interstate lane will be open in both directions.  
 
The speed limit is 45 mph over the median crossovers, and 55 mph between them.
 
The project is expected to be complete in September. It is about a month ahead of schedule.
 
Several badly damaged concrete slabs in that stretch will be removed and replaced. Repairs also will include resealing pavement joints, repairing pavement cracks and chips, grinding portions off of the existing pavement surface and completing guardrail safety improvements.
 
A highly competitive construction environment led to significant savings on the eight original projects funded by the federal stimulus program ARRA (American Recovery and Reinvestment Act). This is one of nine smaller projects financed through those initial bid savings.
 
Multiple Concrete Enterprises, of Ogden, Utah, is the contractor on the $6.9 million project.

 

PAYETTE U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is now under way. It is expected to take about two years to complete, finishing in fall 2012.

Crews will replace the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Traffic will utilize the southbound bridge while the new bridge is constructed. Traffic will then be switched to the new bridge while modifications to the southbound bridge are made and it is connected to the new bridge.

 

Crews continue to set up the cofferdam, and the dewatering operation is in progress and should be complete by the last week of August. Removal of the bridge deck from the truss bridge continues, and as soon as the cofferdams are prepared, removal of the old truss bridge will commence.

 

Removal of the bridge deck from the truss bridge is in progress. The next step is the removal of the steel truss sections of the bridge.   

JC Constructors Inc. of Meridian is the contractor for this $6.17 million project.

 

VALLEY COUNTY

Idaho 55, Donnelly North City Limits to Deinhard Lane in McCall
An 11-mile pavement preservation/resurfacing project between Donnelly's north city limit and Deinhard Lane on the southern end of McCall is now under way, using the Cement Recycled Asphalt Base Stabilization (CRABS) resurfacing method. The existing surface will be removed, crushed and mixed with cement, then reapplied to the highway as a base for the new surface.
 
The project is expected to take about two months to complete. During construction, one lane will be closed in the project area, with flaggers directing traffic.
 
The work from milepost 132 to 143 also involves some drainage improvements.

 

Crews are working a 7:00 a.m. to 6:00 p.m. schedule, with no weekend work and crews must be done and off the roadway by noon on Fridays to accommodate weekend recreational traffic.

The replacement of deteriorated culvert that crosses Idaho 55 continued this week. Temporary patching of completed culvert crossings will continue on Fridays.

Assembly of the asphalt plant for the production and crushing operations of rocks also was completed this week.

Milling operations - grinding off the top layer of pavement surface also began this week, starting at Donnellys north city limits and proceeding north. Both directions of Idaho 55 will be milled, one direction in the morning, the other in the afternoon. Motorcycles should use extra caution in milled areas.

Edge-drain installation, between mileposts 135 and 136, may begin this week. Milepost 135.3 is the end of the Lake Fork Bridge and Smilie Lane. Kimble Lane and Fairbrothers Lane are also in that stretch. Edge drains are parallel to the road, just off the edge. These are buried drains that collect ground and surface water that filters down to them and take that away. The intent is to direct water away from the roadway foundation so that it cant contributes to winter frost heaves.

 

Paving on the project is not expected until after Labor Day.


Culvert replacement will require traffic-control measures (such as a speed limit reduction to 45 mph, flaggers and pilot cars if needed) while crews trench across the highway.

 

Idaho 55, Gold Dust Road Turn Bay, south of Cascade
Work began Monday (Aug. 16) to construct a left-turn bay on Idaho 55 for Gold Dust Road, about 1.5 miles south of Cascade. The roadway will be widened in that location (milepost 112) to accommodate the turning lane.
 
The project is expected to take about a month. During construction, one lane will be closed in the project area, with flaggers directing traffic.
 
Knife River Corp., of Boise, is the contractor for both Valley County projects. The Gold Dust Road Turn Bay is a $177,000 project, and the Donnelly to Deinhard contract is $3.6 million.

 

WASHINGTON COUNTY

WEISER - Snake River Bridge replacement

The project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser 

is nearly finished. Top soil work and seeding remain.

 

The original bridge was built in 1903, with an additional span added in 1911. Traffic signals were added in 1949. The bridge was replaced in the 1950s - that one is being replaced in this project. Once completed, the bridge will be 16 feet wider and able to carry greater traffic volumes. The highway on both sides of the bridge also will be reconstructed.

 

This past week (Aug. 9-13), fencing was installed as was permanent signage. No construction is planned for next week.


Sletten Construction, of Boise, is the contractor on this $10 million project.


ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.

  

 
+