Southwest Idaho highway construction report for Oct. 8-15

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Cole Road to Broadway Avenue widening

ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

The westbound on-ramp at the Broadway Interchange will be closed for reconstruction Oct. 15-18. Motorists will be detoured to the Gowen Interchange from 8 p.m. Friday (Oct. 15) to 5 a.m. Monday (Oct. 18).

 

Westbound motorists bound for the Vista or Orchard interchanges will continue using the temporary ramp lanes at the Broadway Interchange until early 2011. The speed limit is 45 mph on the temporary ramp lanes.

 

The right-hand, westbound exit-only lane from Broadway to Orchard will be restricted to one lane for the next several weeks. Restrictions will occur between 10 p.m. and 5 a.m. on weeknights, and until 7 a.m. on weekends.

 

This $35.9 million project is expected to be complete in summer 2011.

 

MERIDIAN - Interstate 84, Ten Mile Interchange construction

Work continues on a project to construct a new interchange with on- and off-ramps at Ten Mile Road. The project includes several improvements to Ten Mile Road.

 

Only one lane will be open in both directions on I-84 Monday night between the Meridian Interchange and Black Cat Road while crews remove part of the falsework structure that supports the bridge during construction. Restrictions will begin at 10 p.m. Monday (Oct. 11) and end at 5 a.m. Tuesday (Oct. 12).

 

The $33.8 million project is expected to be complete in summer 2011.

 

NAMPA - Franklin to 11th interstate widening

Work is progressing on a project to widen Interstate 84 between the Franklin Boulevard and Garrity Boulevard interchanges in Nampa.  

I-84 motorists can expect ongoing nighttime lane reductions between Franklin and 11th Avenue from 10 p.m. to 5 a.m., Sunday evenings through Saturday mornings. This allows crews to safely work along the shoulder while excavating, grading and performing pipe work in the median.
 
Crews will soon begin the process of concrete paving in the median, once pipe work is complete and new roadbed is in place. Paving is scheduled overnight between 10 p.m. and 5 a.m.  
 
These newly paved sections will eventually carry traffic, though that may be months from now after bridge work is complete.
 
The widening project includes replacement of the Union Pacific Railroad (UPRR) and Phyllis Canal bridges to accommodate the additional lanes on I-84. The UPRR Bridge has been partially dismantled to prepare for reconstruction in the median between eastbound and westbound lanes. A portion of the Phyllis Canal is slated for demolition in early November, after the irrigation season is complete.

Construction is expected to be complete by early summer 2012.

 

Concrete Placing Company, of Boise, is the contractor on this $22.2 million project.
 
Once these interstate improvements are complete, I-84 between Franklin and Garrity will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the lane furthest right, and exit at Garrity - never having to merge with interstate traffic.

 
  
NAMPA - Interstate 84, Garrity Interchange Bridge reconstruction

Construction on the I-84 Garrity Interchange improvement project continues. The project will replace two bridges on I-84 at the Garrity Interchange with a single bridge that will accommodate three lanes in each direction on the interstate.

 

Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.

 

The westbound Garrity off-ramp will return to its original configuration in about two weeks.

 

This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa.

 

The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and eventually four lanes in each direction from the Garrity to Meridian interchanges.

 

The I-84 westbound off-ramp will be moved back to its original location closer to the Robinson Road overpass overnight Friday or Saturday depending on weather. The new ramp will allow traffic to use the far right lane on I-84 (slow lane) as a dedicated exit lane. This should reduce some of the congestion during the evening commute and for Idaho Center events.


The new dedicated right-turn lane on to the westbound on-ramp from Garrity Boulevard is open. Some work is still to be completed on or near the turn lane but it is open for traffic currently.

 

The project is being constructed in three stages:

 

Currently Under Way

Step 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Step 2 - Remove the existing westbound bridge and build a new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

Tentatively starts Dec./Jan.

Step 3 - Remove the existing eastbound bridge and build a new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.

 

Concrete Placing Co. Inc., of Boise, is the contractor on the $15 million project.

 

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

 

ADA & VALLEY COUNTY

Idaho 55 bridge deck repairs

Three bridge decks spanning Idaho 55 in Ada and Valley counties will have surface cracks repaired. The project is expected only to last several weeks.

 

The work will extend the life of the bridges. The cracks vary in size, and are caused by general wear-and-tear and the aging concrete. The project will fill the cracks and then seal the repaired surface.  A full-width concrete waterproofing also will be added

 

The bridges are at Lake Fork near milepost 135, Boulder Creek near milepost 131 and Dry Creek near milepost 48. Dry Creek Bridge is about 28-and-a-half miles north of the U.S. 20/26 junction. Boulder Creek is on the south side of Donnelly, at the city limits. The Lake Fork structure is three miles south of the town of Lake Fork.

 

Restruction Corp., of West Valley City, Utah, is the contractor on this $90,000 project.

 

BOISE/VALLEY COUNTY

BANKS TO ROUND VALLEY ROCKFALL

A rockfall mitigation project to improve safety along the highway is under way on Idaho 55 from Banks to Round Valley.

 

Loose rock will be removed from the rockfall zone and crews will add netting to prevent falling rocks from entering the roadway. Work must be completed by mid-November.

 

Lane closures and traffic delays will occur during the removal of the rocks on the slopes and the cleanup required on the road. Delays could last for more than 15 minutes because of the unpredictability of the size and amount of rock that could come down at any one time. The operations will concentrate on one area at a time, but there will be two locations of traffic control because guardrail at the north end of the project is being removed to be used during rock-removal operations.


Crews will work on the side of the roads in several locations along this 26-mile stretch of highway (milepost 76 to 102). Crews are working a weekdays-only schedule, and must be off the road by noon on Fridays.

 

The contractor completed setting the anchors for hanging the wire mesh in work area One (milepost 80.1) last week. They worked on hanging the wire mesh this week.

 
While the wire mesh is being installed, the contractor worked on scaling work area Two (milepost 80.3). Also, they worked on finishing the guardrail replacement between milepost 91.5 and 91.8.
 

Western Construction, of Boise, is the contractor on this $971,000 project.

 

BOISE COUNTY

IDAHO 21 - Warm Spring Creek bridge guardrail

Guardrail replacement on the Warm Spring Creek Bridge on Idaho 21 is under way. Work is expected to continue through late October or early November.

The bridge is located at milepost 91, about 19 miles east of Lowman, near the Bonneville Campground and one-half mile from the South Fork Payette River Bridge.

Flaggers and the occasional use of a temporary traffic signal will be required for traffic control. The speed limit will be reduced to 35 mph through the work zone.

MarCon Inc., of Meridian, is the contractor on this $177,000 project.

 

CANYON COUNTY

MIDDLETON- road improvement projects

Crews are working on two road improvement projects in Middleton: Widening a one-third-mile section of North Middleton Road from Idaho 44 to Mill Slough (north of Main Street) and realigning a short segment of Cemetery Road, from Idaho 44 to 3rd Street.


Most work will be performed during the weekdays, though crews may work on Saturdays as needed. Work hours are limited to 8 a.m.-7 p.m.


During construction the contractor will establish detours around the project areas, using local roads. Work is planned to be complete in late December.


Nampa Paving & Asphalt Co. is the contractor on this $884,000 combined project.

North Middleton Road
North Middleton Road is closed to through traffic and open to local residents only. Non-resident motorists driving around road closure signs may be ticketed.


By today (Friday, Oct. 8), crews will finish lowering water lines that run below N. Middleton Road between Harmon Way and Second Street to allow for paving. The project team would like to thank residents who may have experienced water service interruptions on Monday for their patience. At the completion of the project, crews will return to repair those sections of roadway and adjacent landscaping that were disturbed by the water line work.


Next week (the week of Oct. 11-15), crews will finish installing curb, gutter and driveway approaches. This work is weather dependent. Sidewalk installation on the east side of N. Middleton Road will begin as soon as curb and gutter work is complete.

The Middleton Road widening will include one lane in each direction, a center turn lane, sidewalks, curb and gutter.
 
Cemetery Road
A 0.15-mile section Cemetery Road is being realigned, extending from Idaho 44 to 3rd Street.


The new alignment is in place and traffic has been shifted to the new alignment so that crews can work on the section of Cemetery Road that will become a residential cul-de-sac off of Idaho 44 (to be called North Highland Court). The road is open to one lane of traffic in each direction.


To address pedestrian safety across Idaho 44 and along the new Cemetery Road/Idaho 44 intersection, crews have implemented a pedestrian detour route to safely navigate the project area. Additional signage has been added to direct pedestrian traffic. The Idaho Transportation Department also will temporarily extend the 25 mph zone 300 feet west of the project.


A temporary crosswalk has been added at 3rd Street to keep pedestrians away from the work zone. In addition, cones were added along Idaho 44 to create a safe corridor for pedestrians who are passing near the construction area.

 

OWYHEE COUNTY

HOMEDALE U.S. 95 paving from Idaho 55 to South City Limits

A 7.3-mile pavement rehabilitation project on U.S. 95 from the junction with Idaho 55 to the South City Limits of Homedale is nearly finished.

 

Crews are paving, striping and completing final clean-up items. The project is expected to finish in 2-3 weeks.

 

The project used the CRABS (Cement Recycled Asphalt Base Stabilization) method of pavement rehabilitation. In addition, existing guardrail was upgraded, shoulder rumble strips installed for the length of the project and an additional width (up to two feet) added to each side of the roadway

 

A project by State maintenance forces this spring added to the gravel shoulders in that area in preparation for this project.

 

This project also is coupled with a thin-lift overlay resurfacing (1.8 inches of new pavement) from the Marsing Port of Entry to the junction with Idaho 55, about an 8.5-mile stretch.

 

PAYETTE COUNTY
WEST OF CALDWELL - I-84 resurfacing, Black Canyon to Sand Hollow
The pavement resurfacing and repair project on I-84 west of Caldwell is nearing completion. The project, funded through stimulus savings, begins west of the Black Canyon Interchange and extends for five miles, to east of the Sand Hollow Interchange.
 

During the majority of the work, only one interstate lane will be open in both directions.  
 
The speed limit is 45 mph over the median crossovers, and 55 mph between them.

 

Traffic has been reduced to one lane while crews grind rumble strips. All major work should be done by the end of next week (Oct. 11-15).

 

Several badly damaged concrete slabs in the stretch will be removed and replaced. Repairs also will include resealing pavement joints, repairing pavement cracks and chips, grinding portions off of the existing pavement surface and completing guardrail safety improvements.
 
A highly competitive construction environment led to significant savings on the eight original projects funded by the federal stimulus program ARRA (American Recovery and Reinvestment Act). This is one of nine smaller projects financed through those initial bid savings.
 
Multiple Concrete Enterprises, of Ogden, Utah, is the contractor on the $6.9 million project.

 

PAYETTE U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is now under way. It is expected to take about two years to complete, finishing in fall 2012.

Crews will replace the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Traffic will utilize the southbound bridge while the new bridge is constructed. Traffic will then be switched to the new bridge while modifications to the southbound bridge are made and it is connected to the new bridge.

 

Crews are dismantling the existing bridge.

 

JC Constructors Inc. of Meridian is the contractor for this $6.17 million project.

 

VALLEY COUNTY

Idaho 55, Donnelly North City Limits to Deinhard Lane in McCall
An 11-mile pavement preservation/resurfacing project between Donnelly's north city limit and Deinhard Lane on the southern end of McCall is entering its final weeks, using the Cement Recycled Asphalt Base Stabilization (CRABS) resurfacing method. The existing surface will be removed, crushed and mixed with cement, then reapplied to the highway as a base for the new surface.
 
Crews were unable to work on Monday (Oct. 4) due to weather. On Tuesday crews added cement on a portion of the northbound lane but stopped when the asphalt hotplant broke down. Paving occurred at the end of the week.

 

The project is expected to take about two months to complete. During construction, one lane will be closed in the project area, with flaggers directing traffic.
 
The work also involves some drainage improvements.

 

Crews are working a 7 a.m. to 6 p.m. schedule, with no weekend work and crews must be done and off the roadway by noon on Fridays to accommodate weekend recreational traffic.

 

Knife River Corp., of Boise, is the contractor for the $3.6 million Donnelly to Deinhard project.

 

WASHINGTON COUNTY

WEISER - Snake River Bridge replacement

The project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser 

is nearly finished. Topsoil work and seeding remain.

 

The topsoil is in the process of being tested before being used.

 

The original bridge was built in 1903, with an additional span added in 1911. Traffic signals were added in 1949. The bridge was replaced in the 1950s - that one is being replaced in this project. Once completed, the bridge will be 16 feet wider and able to carry greater traffic volumes. The highway on both sides of the bridge also will be reconstructed.

 

Applying topsoil and seeding the area still remain to be done this fall.


Sletten Construction, of Boise, is the contractor on this $10 million project.


ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.

 
+