10/22/2010

Reed Hollinshead
ITD Communication
208-334-8881
reed.hollinshead@itd.idaho.gov

Southwest Idaho highway construction report for Oct. 22-29

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Cole Road to Broadway Avenue widening

ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

Motorists will use new westbound ramps at the Vista and Orchard interchanges next week. Crews will switch traffic to the new ramps on Sunday and Monday nights (Oct. 24 and 25).

 

Westbound motorists bound for the Vista or Orchard interchanges will continue using the temporary ramp lanes at the Broadway Interchange until early 2011. The speed limit is 45 mph on the temporary ramp lanes.

 

This $35.9 million project is expected to be complete in summer 2011.

 

MERIDIAN - Interstate 84, Ten Mile Interchange construction

Work continues on a project to construct a new interchange with on- and off-ramps at Ten Mile Road.

 

All lanes on I-84 will be closed overnight between the Garrity and Meridian interchanges on Friday and Saturday (Oct. 22 and 23) from 10 p.m. to 7 a.m. each night.

 

The closures will allow the Ten Mile Interchange contractor to continue disassembling the 200-foot wood-and-steel structure that supported the new bridge during initial construction.

 

Starting Sunday (Oct. 24), I-84 will be reduced to one lane in both directions at night for the next few weeks. The restrictions will affect a three-mile stretch between the Meridian Road Interchange and Black Cat Road overpass.

 

Restrictions and closures will occur between 10 p.m. and 5 a.m. on weeknights, and between 10 p.m. and 7 a.m. on the weekend.

 

The $33.8 million project is expected to be complete in summer 2011.

 

The landscapers are mobilizing onsite starting in early November. The initial work this fall will be the placement of irrigation and sprinkler pipe. Locations of pipe placement will be in the median on Ten Mile Road, in the drainage ponds around the interchange, and potentially any slopes that are finished and are out of the contractors way.

 

NAMPA - Franklin to 11th interstate widening

Work is progressing on a project to widen Interstate 84 between the Franklin Boulevard and Garrity Boulevard interchanges in Nampa.  
 
Expect ongoing nighttime lane reductions between Franklin and Garrity from 10 p.m. to 5 a.m., Sunday evenings through Saturday mornings. This allows crews to safely work along the shoulder while excavating, grading and performing pipe work in the median.
 
Crews are in the early stages of paving sections of the median; this involves finishing pipe work and preparing the road bed. Paving is scheduled during overnight hours (10 p.m. - 5 a.m.) and will continue into November. These newly paved sections will eventually carry traffic, though that may be months from now, after bridge work is complete.
 
The widening project includes replacement of the Union Pacific Railroad (UPRR) and Phyllis Canal bridges to accommodate the additional lanes on I-84. The UPRR Bridge has been partially dismantled to prepare for reconstruction in the median between eastbound and westbound lanes. A portion of the Phyllis Canal is slated for demolition in early November, after the irrigation season is complete.
 
Construction is expected to be complete by early summer 2012.

 

Concrete Placing Company, of Boise, is the contractor on this $22.2 million project.
 
Once these interstate improvements are complete, I-84 between Franklin and Garrity will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the lane furthest right, and exit at Garrity - never having to merge with interstate traffic.

 

NAMPA - Interstate 84, Garrity Interchange Bridge reconstruction

Construction on the I-84 Garrity Interchange improvement project continues. The project will replace two bridges on I-84 at the Garrity Interchange with a single bridge that will accommodate three lanes in each direction on the interstate.

 

Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.

 

This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa.

 

The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and eventually four lanes in each direction from the Garrity to Meridian interchanges.

 

I-84 will be closed in both directions from Meridian to Garrity overnight (10 p.m. 7 a.m.) Friday and Saturday nights (Oct. 22 and Oct. 23). Traffic will be detoured down Franklin Road and will enter or exit I-84 at the Meridian and Garrity interchanges.

 

The entire project is being constructed in three stages:

 

Currently Under Way

Step 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Step 2 - Remove the existing westbound bridge and build a new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

Tentatively starts Dec./Jan.

Step 3 - Remove the existing eastbound bridge and build a new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.

 

Concrete Placing Co. Inc., of Boise, is the contractor on the $15 million project.

 

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

 

ADA & VALLEY COUNTY

Idaho 55 bridge deck repairs

Three bridge decks spanning Idaho 55 in Ada and Valley counties will have surface cracks repaired. The project is expected only to last several weeks.

 

The work will extend the life of the bridges. The cracks vary in size, and are caused by general wear-and-tear and the aging concrete. The project will fill the cracks and then seal the repaired surface.  A full-width concrete waterproofing also will be added

 

The bridges are at Lake Fork near milepost 135, Boulder Creek near milepost 131 and Dry Creek near milepost 48. Dry Creek Bridge is about 28-and-a-half miles north of the U.S. 20/26 junction. Boulder Creek is on the south side of Donnelly, at the city limits. The Lake Fork structure is three miles south of the town of Lake Fork.

 

Restruction Corp., of West Valley City, Utah, is the contractor on this $90,000 project.

 

BOISE/VALLEY COUNTY

BANKS TO ROUND VALLEY ROCKFALL

A rockfall mitigation project to improve safety along the highway is under way on Idaho 55 from Banks to Round Valley.

 

Loose rock will be removed from the rockfall zone and crews will add netting to prevent falling rocks from entering the roadway. Work must be completed by mid-November.

 

Lane closures and traffic delays will occur during the removal of the rocks on the slopes and the cleanup required on the road. Delays could last for more than 15 minutes because of the unpredictability of the size and amount of rock that could come down at any one time. The operations will concentrate on one area at a time, but there will be two locations of traffic control because guardrail at the north end of the project is being removed to be used during rock-removal operations.


Crews will work on the side of the roads in several locations along this 26-mile stretch of highway (milepost 76 to 102). Crews are working a weekdays-only schedule, and must be off the road by noon on Fridays.

 

Western Construction, of Boise, is the contractor on this $971,000 project.

 

BOISE COUNTY

IDAHO 21 - Repair of 10 bridges

Ten bridge decks along Idaho 21 are being repaired and preserved in a unique highway contract.

 

The bridges include the Boise River Bridge at Diversion Dam and one at Chapman Creek. The rest are along Mores Creek. Under this "Fixed Price/Best Value" contracting method, construction is likely to finish before winter arrives - just in time for the traveling public to benefit from the new riding surface on the usually snowy Idaho 21 route.

In contrast to the department's typical method of selecting the lowest qualified bidder for each project, contractors were asked on this project to bid the maximum amount of bridge deck rehabilitation they could accomplish within a fixed budget. The contract was then awarded to the lowest responsible bidder, defined as the bidder providing the lowest price per square yard of deck rehab. Each bidder also was asked to tell ITD how long it would take to do the work.
  
Truesdell Corp. of Tempe, Arizona, was awarded the contract, based on the ability to do all 10 bridges - 10,435.5 square yards of bridge decks - for the $700,000 price tag.

 

IDAHO 21 - Warm Spring Creek bridge guardrail

Guardrail replacement on the Warm Spring Creek Bridge on Idaho 21 is under way. Work is expected to continue through late October or early November.

The bridge is located at milepost 91, about 19 miles east of Lowman, near the Bonneville Campground and one-half mile from the South Fork Payette River Bridge.

Flaggers and the occasional use of a temporary traffic signal will be required for traffic control. The speed limit will be reduced to 35 mph through the work zone.

MarCon Inc., of Meridian, is the contractor on this $177,000 project.

 

CANYON COUNTY

MIDDLETON- road improvement projects

Crews are working on two road improvement projects in Middleton: Widening a third-of-a-mile section of North Middleton Road, from Idaho 44 to Mill Slough (north of Main Street), and realigning a short segment of Cemetery Road, from Idaho 44 to 3rd Street.

Most work will be performed during the weekdays, though crews may work on Saturdays as needed. Work hours are limited to 8 a.m.7 p.m.

 

During construction the contractor will establish detours around the project areas, using local roads. Work is planned to be complete in late December.

 

Nampa Paving & Asphalt Co. is the contractor on this $884,000 combined project.

 

North Middleton Road

North Middleton Road between Idaho 44 and Main Street is closed to through traffic and open to local residents only. Non-resident motorists driving around road closure signs may be ticketed.

 

Crews are paving North Middleton Road this week between Idaho 44 and Main Street. Lanes will be marked with temporary tabs before crews paint permanent lane stripes. Permanent markings for crosswalks and stop lines at intersections will also be installed.

Curb, gutter and sidewalk work is complete in this area. Before project completion, crews will return to repair sections of roadway and adjacent landscaping that were disturbed during previous water line work.

 

During the week of Oct. 25, work will shift north, to the section of North Middleton Road between Main Street and the south side of the canal bridge, just south of Mill Creek School. The widening will include one lane in each direction, a center turn lane, sidewalks, curb and gutter. Work on this section is anticipated to be complete in December. This section of road will be closed during construction. Traffic will be detoured by way of Triumph Drive and Dewey Avenue to access Idaho 44.

 

Cemetery Road

A 0.15-mile section of Cemetery Road is being realigned, extending from Idaho 44 to 3rd Street.

 

The new alignment is in place and traffic has been shifted to the new alignment so that crews can work on the section of Cemetery Road that will become a residential cul-de-sac off of Idaho 44 (to be called North Highland Court). The Cemetery Road section is open to one lane of traffic in each direction. Curb, gutter and sidewalk are also complete along this section.

 

Crews will be working on curb, gutter and sidewalk on North Highland Court and anticipate paving in the coming week to 10 days.

 

To address pedestrian safety across Idaho 44 and along the new Cemetery Road/Idaho 44 intersection, crews have implemented a pedestrian detour route to safely navigate the project area. Additional signage has been added to direct pedestrian traffic, and the 25 mph zone is extended 300 feet west of the construction area.

 

A temporary crosswalk has been added at 3rd Street to keep pedestrians away from the work zone. In addition, cones were added along Idaho 44 to create a safe corridor for pedestrians who are passing near the construction area.

 

ELMORE COUNTY

MOUNTAIN HOME Canyon Creek Bridge replacement

Replacement of the old, narrow Canyon Creek Bridge is expected to begin Monday (Oct. 25). The bridge is located near milepost 9 on Canyon Creek Road, north of Mountain Home.

 

The road, which sees a fair amount of hunting-related traffic each fall, will be completely closed from Oct. 29 to late January.   

 

The detour route will start at the intersection of Canyon Creek Road and Frontage Road, and continue west past the Sunset Highway on Old Oregon Trail Highway. The detour will cross I-84 to the north at Ditto Creek road and continue along Martha Avenue to the east, back to Canyon Creek.

The bridge replacement also involves minimal approach work to the connecting roads to ensure that the bridge and road fit together seamlessly. The bridge also will include guardrail (railing), which the old bridge lacks.

The Mountain Home Highway District is the local sponsor of the project.

 

McAlvain Contractors, of Boise, is the contractor on this $493,000 project.

 

PAYETTE COUNTY
WEST OF CALDWELL - I-84 resurfacing, Black Canyon to Sand Hollow
The pavement resurfacing and repair project on I-84 west of Caldwell, from the Black Canyon Interchange to east of the Sand Hollow Interchange, is substantially complete.
 

Crews will continue final project clean-up and some minor items.


PAYETTE U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is now under way. It is expected to take about two years to complete, finishing in fall 2012.

Crews will replace the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Traffic will utilize the southbound bridge while the new bridge is constructed. Traffic will then be switched to the new bridge while modifications to the southbound bridge are made and it is connected to the new bridge.

 

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.

 

VALLEY COUNTY

Idaho 55, Donnelly North City Limits to Deinhard Lane in McCall
An 11-mile pavement preservation/resurfacing project between Donnelly's north city limit and Deinhard Lane on the southern end of McCall is starting to wrap up.

 

Crews will complete pavement markings this weekend if weather allows. Normally crews have to be off the roadway during the weekend, but that requirement is waived in the case of roadway striping due to the added safety benefits of finishing the striping early, and a minimal disruption to traffic.
 
Next weeks activities include finishing striping if necessary, re-installing snow poles, and finishing some culvert work.

 

Knife River Corp., of Boise, is the contractor for this $3.6 million project.

 

WASHINGTON COUNTY

WEISER - Snake River Bridge replacement

The project to replace the Snake River Bridge on the U.S. 95 Spur in Weiser 

is nearly finished.

 

Applying topsoil and seeding the area still remain to be done.

 

The original bridge was built in 1903, with an additional span added in 1911. Traffic signals were added in 1949. The bridge was replaced in the 1950s - that one is being replaced in this project. Once completed, the bridge will be 16 feet wider and able to carry greater traffic volumes. The highway on both sides of the bridge also will be reconstructed.

 

Sletten Construction, of Boise, is the contractor on this $10 million project.


ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.

 
+