12/3/2010
Reed Hollinshead
ITD Communication
208-334-8881
reed.hollinshead@itd.idaho.gov
Southwest Idaho highway construction report for Dec. 3-10
BOISE - The following
projects are part of the GARVEE Transportation Program in southwest Idaho,
which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to
expedite highway projects.
BOISE - Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and
widening east- and westbound I-84 between the Cole and Broadway interchanges in
Boise. When complete, the interstate will have four lanes in each direction.
Westbound
motorists bound for the Vista or Orchard interchanges will continue using the
temporary ramp lanes at the Broadway Interchange until late 2010. The speed limit is 45 mph on the temporary ramp lanes.
This $35.9
million project is expected to be complete in summer
2011.
MERIDIAN - Interstate 84, Ten
Mile Interchange construction
Work
continues on a project to construct a new interchange with on- and off-ramps at
Ten Mile Road.
Ten Mile Road is closed
to motorists, pedestrians and bicyclists between Franklin and Overland roads.
Construction vehicles
and heavy equipment are entering and exiting the project area from westbound
I-84 near the new bridge. The speed limit is 55 mph on I-84.
The $33.8 million project is
expected to be complete in summer
2011.
NAMPA
- Franklin to 11th interstate widening
Weather permitting, next week crews will
pave the median between the Union Pacific Railroad (UPRR) and Phyllis Canal
bridges on a project to widen Interstate 84 between the Franklin Boulevard and
Garrity Boulevard interchanges in Nampa.
This work was originally scheduled for
last weekend, but was delayed due to weather. It will require eastbound I-84 to
be reduced to one lane between Franklin and Garrity. The widening project
includes replacement of the bridges to accommodate the additional lanes on
I-84.
The newly paved median will eventually
carry traffic after the first of the year, following completion of bridge work.
Construction is expected to be complete
by early summer 2012.
Concrete Placing Company of Boise is the
contractor on this $22.2 million project.
Once these interstate improvements are
complete, I-84 between Franklin and Garrity will be widened to three lanes in
each direction, with an additional auxiliary lane for eastbound traffic. The
auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the
lane farthest right, and exit at Garrity - never having to merge with
interstate traffic.
NAMPA - Interstate 84, Garrity
Interchange Bridge reconstruction
Construction on the I-84 Garrity
Interchange improvement project continues. The project replaces two bridges on
I-84 at the Garrity Interchange with a single bridge to accommodate three lanes
in each direction on the interstate.
Overview
of Traffic Changes
- Garrity
Boulevard will be closed overnight Saturday and Sunday (Dec. 4 and 5) for
the removal of the eastbound bridge at the I-84 Garrity Interchange.
Traffic will not be able to pass underneath the bridge. However, the ramps
will still be open to access the interstate. Traffic north- and southbound
on Garrity will be detoured using Stamm Lane, Robinson Road and Franklin
Road between 10 p.m. and 5 a.m.
- I-84
eastbound will be closed overnight (10 p.m. to 5 a.m.) on Saturday (Dec.
4) between the Franklin and Garrity interchanges. Eastbound traffic will
exit I-84 at the Franklin Interchange and be detoured south on Franklin
Boulevard, Northeast on Garrity Boulevard, and re-enter I-84 at the
Garrity Interchange.
- I-84
eastbound traffic will be moved north into the median approximately
one-quarter mile east of the Garrity Interchange on Sunday morning (Dec.
5). Once motorists are past the Garrity Interchange, traffic switches back
to the south out of the median. This configuration is expected to last
several months while crews remove and replace the eastbound bridge at
Garrity.
- Garrity
Boulevard is reduced to one lane in each direction intermittently near the
Garrity Interchange while crews work under the bridge. The overnight (10
p.m. to 5 a.m.) lane restrictions will not take place on Friday or
Saturday nights. Two southbound and one northbound lane will be open by
the morning commute and during the day.
- I-84
is reduced to one lane in each direction most nights between 10 p.m. and 5
a.m., excluding weekends, between the 11th Avenue overpass and Robinson
Road overpass, while crews work along the shoulders. Both lanes will be
open by the morning commute and during the day. Lane reductions are not
expected to occur often on Friday or Saturday nights.
- Weather
permitting, ITD is flagging the I-84 on-ramps at Garrity following Idaho
Center events to move traffic through the construction area more
efficiently. Here are the two coming events for which ITD will provide
flagging:
- Dec. 3 - Dane Cook (Comedian)
- Jan. 27 - Jeff Dunham (Comedian)
Work also includes reconstructing the
interstate about a mile east of the interchange to tie into the widening of
I-84 between the Garrity and Meridian interchanges, and removing the bridge
piers in the roadway at Garrity Boulevard.
This project is part of ITD's plans to
improve I-84 between the Franklin and Garrity interchanges in Nampa.
The completed improvements will include
three lanes in each direction from the Franklin to Garrity interchanges, and
eventually four lanes in each direction from the Garrity to Meridian
interchanges.
The entire project is being constructed
in three stages:
Currently
Under Way
Step 1 - Build the median section of the
bridge between the existing bridges. Traffic will remain on existing bridges,
with two lanes open in each direction.
Step 2 - Remove the existing westbound
bridge and build a new westbound portion of bridge. Westbound traffic will be
moved onto the new median section. Two lanes will remain open in each
direction.
Tentatively starts Dec./Jan.
Step 3 - Remove the existing eastbound
bridge and build a new eastbound portion of bridge. Westbound traffic will be
shifted onto the new westbound portion of the bridge, and eastbound traffic
onto the median section.
Completion - By summer 2011, three
lanes will be open in each direction over the bridge, eventually connecting
with a fourth lane in each direction east of the interchange.
Concrete Placing Co. Inc., of Boise, is
the contractor on the $15 million project.
Following is an update on non-GARVEE
state highway construction projects in southwest Idaho.
ADA
COUNTY
MERIDIAN
- EAGLE ROAD AND ST LUKES ROAD IMPROVEMENT
Crews are going to try to work on Sunday
night (Dec. 5) to excavate the two remaining dry wells, weather permitting. There
will be a southbound right-hand lane closure from Autumn Way to Magic View
between 8 p.m. Sunday night and 5:30 a.m. Monday morning.
This is part of the earlier $1.35 million Eagle
Road resurfacing contract. Central Paving Co. Inc., of Boise, is the
contractor.
BOISE/VALLEY
COUNTY
BANKS
TO ROUND VALLEY ROCKFALL
A rockfall mitigation project to improve
safety along the highway is wrapping up on Idaho 55 from Banks to Round Valley.
Due to weather, rock scaling is done for
the winter. The contractor will do some final clean up and guardrail work, then
resume next spring (after March 1) for an estimated 10 more weeks.
ELMORE
COUNTY
MOUNTAIN
HOME Canyon Creek Bridge replacement
Replacement of the old, narrow Canyon
Creek Bridge is under way. The bridge is located near milepost 9 on Canyon
Creek Road, north of Mountain Home.
The road, which sees a fair amount of
hunting-related traffic each fall, will be completely closed through late
January.
The detour route will start at the
intersection of Canyon Creek Road and Frontage Road, and continue west past the
Sunset Highway on Old Oregon Trail Highway. The detour will cross I-84 to the
north at Ditto Creek road and continue along Martha Avenue to the east, back to
Canyon Creek.
The bridge replacement also involves minimal approach work to the connecting
roads to ensure that the bridge and road fit together seamlessly. The bridge
also will include guardrail (railing), which the old bridge lacks.
The old bridge has been removed and excavation
has started for the new structure.
The footings for the new bridge were placed
on Tuesday (Nov. 30).
The Mountain Home Highway District is the
local sponsor of the project.
McAlvain Contractors, of Boise, is the
contractor on this $493,000 project.
PAYETTE
COUNTY
PAYETTE U.S. 95, Payette River Bridge replacement
The project to improve the U.S. 95 bridge over
the Payette River south of Payette is now under way. It is expected to take about
two years to complete, finishing in fall 2012.
Crews will replace the existing northbound truss bridge (built in 1927) located
on U.S. 95 between Fruitland and Payette. The new bridge will be two feet
higher off the water. It will have no overhead bracing or struts as the current
one does and will be 84 feet in width, eliminating current safety concerns
regarding both width and height restrictions.
The new bridge will be constructed next
to, and will attach to, the existing southbound bridge. The project also
includes minor roadway realignment to tie into the new bridge location.
U.S. 95 is the main route connecting northern and southern Idaho. About 18,000
vehicles use this portion of the highway daily. By 2026, the volume is expected
to be more than 25,000.
Traffic will utilize the southbound bridge while the new bridge is constructed.
Traffic will then be switched to the new bridge while modifications to the
southbound bridge are made and it is connected to the new bridge.
Piers 1,2, and 3 have been completed. Abutment
1 is being formed and will be completed next week. Pile driving for Abutment 2
will be completed this week. The crane is being broken down and moved from the
North side to the South side to set girders. Setting the girders will follow
the cure time on the structures. Girder delivery is on hold, pending trucking
permits through Washington and Oregon because of winter conditions. Once the
girders are set, the cofferdam on the south side will be removed and moved to
the north side so construction can begin on piers 4 and 5.
JC Constructors Inc., of Meridian, is the
contractor for this $6.17 million project.
ITD and the Idaho State Police caution
motorists to slow down and pay attention when driving in work zones, where
increased speeding fines and other penalties apply. Motorists are encouraged to
plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state
highway or interstate system.