Southwest Idaho highway construction report for Jan. 14-21

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Cole Road to Broadway Avenue widening

ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

Westbound motorists bound for the Vista or Orchard interchanges will continue using temporary ramp lanes at the Broadway Interchange until late 2010. The speed limit is 45 mph on the temporary ramp lanes.

 

Concrete Placing Co., of Boise, is the contractor. This $35.9 million project is expected to be complete in summer 2011.

 

MERIDIAN - Interstate 84, Ten Mile Interchange construction

Work continues on a project to construct a new interchange with on- and off-ramps at Ten Mile Road.

 

Westbound I-84 will be reduced to one lane from 10 p.m. Sunday (Jan. 23) to 5 a.m. Monday (Jan. 24) while sign poles are installed on the interstate. Restrictions will continue at night the week of Jan. 23.

 

All lanes on Ten Mile Road are closed between Franklin and Overland roads. The Meridian Police and Ada County Sheriffs Department are enforcing the area. Violators will be ticketed for reckless driving.

 

The Ada County Highway District will begin to widen Ten Mile Road between the Ridenbaugh Canal and Overland Road in late January. Updates and traffic impacts from the ACHD project will be posted at www.achdidaho.org under Projects and Studies.  

 

The speed limit is 55 mph on I-84.

 

Idaho Sand & Gravel is the contractor on this $33.8 million project, which is expected to be complete in summer 2011.

 

The landscaping, under a separate $580,000 contract to Franz Witte Landscape Contracting, is set to begin this spring when the ground thaws.

 

NAMPA - Franklin to 11th interstate widening

As part of the project to widen Interstate 84 between the Franklin Boulevard and Garrity Boulevard interchanges in Nampa, crews have nearly completed construction of two new bridges over the Union Pacific Railroad (UPRR) and Phyllis Canal. However, any concrete work on the bridges is on hold due to the weather, as is concrete paving in the median.

 

A large section of I-84 in the project area was restriped last week.

 

Also, to improve visibility for motorists, yellow and white reflectors (similar to those used on the Cole to Broadway project) will be installed onto guardrails.

 

Replacement of the bridges will accommodate additional lanes on I-84.

 

Construction is expected to be complete by early summer 2012.

 

Concrete Placing Company of Boise is the contractor on this $22.2 million project.


 

Once these interstate improvements are complete, I-84 between Franklin and Garrity will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the lane farthest right, and exit at Garrity - never having to merge with interstate traffic. 

 

NAMPA - Interstate 84, Garrity Interchange Bridge reconstruction

Construction on the I-84 Garrity Interchange improvement project continues. The project replaces two bridges on I-84 at the Garrity Interchange with a single bridge to accommodate three lanes in each direction on the interstate.

 

Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.

 

Construction crews are not able to do a lot of the work while temperatures are below freezing at the interchange. In the meantime, ITD will continue performing maintenance work and minor repairs. Major construction activities should resume the week of Jan. 17. Also, as soon as weather permits, crews will refresh the paint striping on Garrity Boulevard under the bridge. Once the weather warms up, pile driving will begin on the eastbound bridge.

 

This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa.

 

The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and eventually four lanes in each direction from the Garrity to Meridian interchanges.

 

The entire project is being constructed in three stages:

 

COMPLETED

Step 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Step 2 - Remove the existing westbound bridge and build a new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

CURRENTLY UNDER WAY

Step 3 - Remove the existing eastbound bridge and build a new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.

 

Concrete Placing Co. Inc., of Boise, is the contractor on the $15 million project.

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

 

ADA COUNTY

BOISE - Floating Feather Road/Idaho 16 intersection turnbay project

A project to add a turnbay to the intersection of Floating Feather Road to serve north- and southbound traffic is expected to begin soon. Traffic control will be set Wednesday (Jan. 19) and the project is expected to begin Jan. 24.

The bridge must be completed by March 15, in time for the irrigation season. The roadwork will finish by May 1.

A 10-foot irrigation structure (concrete box culvert) exists within the project's limits and will be extended on both sides of Idaho 16 to allow for the lane addition. The project also involves some road widening.

During the project, traffic will use one lane in each direction, just as it is now. The speed limit will be reduced to 45 mph.

Deer Flat Sand & Gravel Inc., of Nampa, is the contractor on this $266,000 project.

BOISE COUNTY

East of Boise - Mores Creek Bridge upgrade

A project to update the Mores Creek Bridge (commonly known as the High Bridge) on Idaho 21 east of Boise is under way.

 

During this work, the bridge deck and joints will be rehabilitated and the bridge parapet and railing replaced. Work on the foundation during the low-water winter period will include a retaining wall, rock anchoring, slope armoring, and seismic retrofit.  Portions of the structural steel will be painted along with other repairs on the structure.  

 

During the nine-month project, traffic across the bridge will be controlled by signals at either end, with only one direction allowed to pass through at a time. Under normal conditions, the delays are expected to be 15 to 45 minutes in length. In addition, a nine-foot width restriction will be in effect.

 

RSCI, of Meridian, is the contractor on the $2.8 million project.

 

CANYON COUNTY

NAMPA City traffic signal synchronization

A project began on Jan. 3 to link traffic signals to create a more efficient traffic flow in and around downtown Nampa.

 

This six-month project will allow traffic signals to be synchronized through fiber optics and will add pedestrian signals with countdown indicators at intersections. The signal improvements will mean people who drive the posted speed through the area should have fewer stops for red lights.

 

The work will be done primarily on 2nd and 3rd Street South and on 12th and 16th Avenue South. Signals on 7th Street South also will be included, as will the signal at 1st Street South and 11th Avenue South.

 

The contractor has drilled and installed conduit down 16th Avenue from 7th Street to 2nd Street, and has started the same work down 7th Street from 11th Avenue to 12th Avenue.  

There will be intermittent lane closures on 16th Avenue and 12th Avenue (Idaho 45) during non-peak hours for equipment storage and utility exploration.

 

Construction crews will try to limit closures to sidewalks and parking stalls in the work areas. The contract does allow for lane closures if necessary, but only between the hours of 8:30 a.m. and 4 p.m.

 

Quality Electric Inc., of Boise, is the construction contractor on this $1.01 million project. The city of Nampa paid for the design on this project and will pay a portion of the construction contract cost. No ITD funds are being expended on this off-system project. The funding breakdown is almost 93 percent Federal Aid and just over 7 percent Local funding. ITD is involved as a steward of the federal aid monies.

 

NAMPA - Robinson Road Overpass safety railing

The Robinson Road bridge railing is now in place and lane closures are scheduled for Wednesday and Thursday nights (10 p.m. to 5 a.m.) to anchor the bolts and grout the plates. The rail, a rigid metal mesh, extends across both sides of the structure on top of the concrete parapet.

The work is being done at the request of the city of Nampa.
 
The entire project is expected to last about two weeks. One lane of traffic will be maintained across the overpass, with occasional nighttime I-84 lane and shoulder closures (10 p.m. to 5 a.m. on weekdays and 10 p.m. to 7 a.m. on weekends).
  

Randell Concrete Inc., of Boise, is the contractor on this $149,000 project. 

 

ELMORE COUNTY

MOUNTAIN HOME Canyon Creek Bridge replacement

Replacement of the old, narrow Canyon Creek Bridge is under way. The bridge is located near milepost 9 on Canyon Creek Road, north of Mountain Home.

 

The road, which sees a fair amount of hunting-related traffic each fall, will be completely closed through late January.   

 

The detour route will start at the intersection of Canyon Creek Road and Frontage Road, and continue west past the Sunset Highway on Old Oregon Trail Highway. The detour will cross I-84 to the north at Ditto Creek road and continue along Martha Avenue to the east, back to Canyon Creek.

The bridge replacement also involves minimal approach work to the connecting roads to ensure that the bridge and road fit together seamlessly. The bridge also will include guardrail (railing), which the old bridge lacks.

 

The contractor is still working on the formwork for the end diaphragms, after which the concrete will be poured.

 

The Mountain Home Highway District is the local sponsor of the project.

 

McAlvain Contractors, of Boise, is the contractor on this $493,000 project.

 

PAYETTE COUNTY
PAYETTE U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is now under way. It is expected to take about two years to complete, finishing in fall 2012.

Crews will replace the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Traffic will utilize the southbound bridge while the new bridge is constructed. Traffic will then be switched to the new bridge while modifications to the southbound bridge are made and it is connected to the new bridge.

 

The cofferdam has been removed from the south side and is being set up on north side to begin construction on piers 4 and 5. The traffic pattern will remain the same - one lane in each direction - but it will be on the new half of the bridge sometime this spring or summer.

 

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.


The Idaho Transportation Department is in charge of all roads within the State Highway System interstates, state highways and U.S. routes. All other roads are the responsibility of the local city or county entity.

 

ITD and the Idaho State Police caution motorists to slow down and pay attention when driving in work zones, where increased speeding fines and other penalties apply. Motorists are encouraged to plan ahead and dial 5-1-1 or visit 511.idaho.gov for information on the state highway or interstate system.

  

 
+