Owyhee County roadwork on Idaho 51 and Idaho 78 slated for this spring

BOISE - A thin overlay will be applied this spring to the existing roadway surface on two highways in rural Owyhee County - a 16-mile stretch of Idaho 51 from milepost 60 to the Snake River Bridge, and a matching 16-mile stretch of Idaho 78 from Grand View to the junction of Idaho 51.

 

The contractor can start work anytime between April 4 and June 20.

 

The Idaho Transportation Department advises that work is expected to last about two months, and during that time one lane will be closed with a pilot car moving traffic through the work area.

 

The work is necessary to correct cracking and roughness, and to preserve the existing highway system.

 

Idaho Sand & Gravel, of Nampa, is the contractor on this $3.4 million project.

 

 
+