Construction update for south-central Idaho Oct. 14-21
SHOSHONE - Here is the construction update for south central Idaho for Oct. 14-21:

U.S. 93, Twin Falls Alternate Route Stage 1: Utility trenching and reconstruction of the Perrine Coulee Bridge continue in the construction corridor from Fillmore Street to Grandview Drive. Motorists should anticipate 10-15 minute delays while flaggers direct one-way traffic through parts of the work zone. The use of alternate routes is encouraged.

Crews are paving the new eastbound lanes from west of Grandview Drive to just west of Washington Street Aside from increased truck traffic in the area, traffic impacts should be minimal.

Access to the south entrance of Grandview Drive from Pole Line Road in Twin Falls is closed. The closure will be in place through October during concrete paving work. Motorists can access Grandview Drive by using North College Road and Falls Avenue.

Idaho 77, Declo to Albion: This road reconstruction project begins five miles south of Declo and continues to Albion (mileposts 18-23). Vehicles exceeding 12 feet in width will be required to detour around the work areas using Idaho 81 from Declo to Malta, and then Idaho 77 from Malta to Albion. Delays of up to 10 minutes are possible. The speed limit is 35 mph and traffic is reduced to one lane. This project, expected to be complete by mid-November, will create a smoother and safer road surface.

U.S. 30, improvement project near Hagerman: U.S. 30 is being reconstructed from the Hagerman Rest Area to Banbury Hot Springs (mileposts 184-191). Traffic is reduced from two lanes to one during daylight hours with flaggers and pilot cars directing motorists. Delays of 10-15 minutes can be expected. The speed limit is reduced from 60-50 mph.

The highway is being rehabilitated using Cement Recycled Asphalt Base Stabilization (CRABS). In this procedure, crews grind the existing roadway surface down to the gravel base, add cement and compact it. The surface then is covered with a new layer of pavement. Guardrails along the seven-mile route will also be replaced.

The $2.3 million project, expected to be completed in October, will create a safer, smoother road surface. Western Construction, Inc. of Boise is the contractor.

U.S. 93, Salmon Falls Creek Canal bridge work: Crews are working on the U.S. 93 Salmon Falls Creek Canal Bridge near Hollister. This is the second phase of a project to replace the existing bridge as part of a future widening of U.S. 93 in the area.

Motorists can expect intermittent delays of up to 10 minutes. Flaggers are directing motorists through the work zone at milepost 25, about two miles south of Hollister. The speed limit is reduced to 50 mph. There is a 14-foot width restriction for vehicles through the construction zone.

This stage of the $1.6 million reconstruction project is expected to be completed by February. Idaho Construction Co. of Kimberly is the project contractor. Motorists are reminded to slow down in highway construction zones. Idaho State Police officers will be present at the construction site to monitor and enforce speed limits as part of Idaho's enhanced work zone safety program.

Idaho 81, bridge reconstruction: Repairs to the J&H Canal bridge on Idaho 81 (milepost 23-25) one mile east of Declo will begin Monday (Oct. 17), requiring vehicle width and length restrictions.

Vehicles traveling through the work zone will be limited to 12 feet wide and 45 feet long. Vehicles exceeding those restrictions will be required to detour around the work area using Idaho 77 from Declo to I-84 at exit 216, and I-84 to Idaho 81 at exit 228. Flaggers will be used periodically. Motorists should expect delays of up to 10 minutes.

The $1.4 million project to extend the life of the bridge is expected to complete in May 2006. Cannon Builders, Inc. of Blackfoot is the project contractor.


 
+