Southwest Idaho highway construction report for April 22-29

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

Shoulders will be closed between Vista and Broadway until sometime next week. ITD is paving two new eastbound lanes on I-84 between Cole and Broadway interchanges.  

 

Traffic will be shifted and lanes will be restricted on westbound I-84 early next week between the Broadway and Cole interchanges.

 

The Vista and Orchard westbound off-ramps will be adjusted slightly as crews re-stripe the roadway to accommodate two new lanes. The new lanes are expected to open later this month if weather permits.

 

Motorists should also expect intermittent east- and westbound I-84 lane restrictions between Cole/Overland and Broadway interchanges through the month of April. Restrictions will occur from 10 p.m. to 5 a.m. 


Concrete Placing Co. Inc., of Boise, is the contractor. This $35.9 million project is expected to be complete in summer 2011.


MERIDIAN - Interstate 84, Ten Mile Interchange construction

Construction of the new I-84, Ten Mile Interchange will continue until early summer. The new interchange will include additional lanes on Ten Mile Road and on- and off-ramps to I-84.

 

One lane of Ten Mile Road is open in both directions between Franklin and Overland. The speed limit is 25 mph. Ramps and the connection to I-84 will remain closed until the interchange is completed in early summer. Crews are still working on ramps, turn lanes, landscaping, lighting and signage.

 

Idaho Sand & Gravel, of Nampa, is the contractor on this $33.8 million project, which is expected to be complete in summer 2011.

The landscaping, under a separate $580,000 contract to Franz Witte Landscape Contracting, is set to begin this spring when the ground thaws.

ITD is doing the initial Ten Mile landscaping. Once the project is done the day-to-day maintenance of that landscaping system reverts to the city of Meridian.

 

Last week, power was established to the water pump location on Ten Mile Road. Mainline piping is complete and lateral pipes and sprinkler heads are about to be installed in the ground. The water pump should be arriving on-site to be installed. There will be no traffic impacts this week.

 

I-84 widening, Franklin to Garrity

On the project to widen Interstate 84 between the Franklin Boulevard and Garrity Boulevard interchanges in Nampa, traffic has shifted to the paved concrete median while crews construct the outside travel lanes.

 

Tonight (Friday, April 21), I-84 will be reduced to one lane in each direction through the project area while crews move equipment. This also happened Thursday night. Motorists can expect ongoing, intermittent nighttime lane closures for both east- and westbound traffic as crews work to complete the project by early summer 2012. All I-84 lanes remain open during the day.

 

Crews are constructing the off-ramps at eastbound Garrity and westbound Franklin. Paving of the ramps is scheduled for early May. Work is planned during daytime hours, and traffic will be shifted around the work zone. Similar work is planned for westbound Garrity and eastbound Franklin on-ramps beginning in late April through mid-May.

 

Other ongoing activity includes building abutments and retaining walls for the Pacific Railroad (UPRR) bridge. In late May, crews will remove the remaining sections of the bridge and prepare to set girders for the new structure. Construction of two new bridges over the UPRR and Phyllis Canal will accommodate the additional lanes on I-84.

 

Concrete Placing Company, of Boise, is the contractor on this $22.2 million project. 

 

Once these interstate improvements are complete, I-84 between Franklin and Garrity will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the lane farthest right, and exit at Garrity - never having to merge with interstate traffic.

 

NAMPA - Interstate 84, Garrity Interchange Bridge reconstruction

Construction on the I-84 Garrity Interchange improvement project continues. The project replaces two bridges on I-84 at the Garrity Interchange with a single bridge to accommodate three lanes in each direction on the interstate.

 

Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.

 

Motorists can expect additional congestion around the westbound Garrity off-ramp for sidewalk construction. Sidewalks will be built on both sides of Garrity beneath I-84, but at this time pedestrian crossings will only be installed on the east side of Garrity to match up with existing sidewalks and crossing signals. The sidewalk work should take a few weeks to complete, depending on weather conditions.

 

The work schedule is still highly dependent on weather conditions, with much concrete work and paving remaining. Also, there will be some restriping on I-84 that may cause intermittent interruptions.

 

In the future, the city of Nampa may improve the sidewalk being built on the west side by installing pedestrian crossings and signals.

 

An eastbound overnight right-lane restriction on I-84 is expected Thursday (April 28).

 

Traffic on Garrity Boulevard will be shifted around into different configurations during daytime hours as crews work underneath the bridge. Two southbound and one northbound lane will remain open.

 

This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa.

 

The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and eventually four lanes in each direction from the Garrity to Meridian interchanges.

 

The entire project is being constructed in three stages:

 

COMPLETED

Step 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Step 2 - Remove the existing westbound bridge and build a new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

CURRENTLY UNDER WAY

Step 3 - Remove the existing eastbound bridge and build a new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.

 

Concrete Placing Co. Inc., of Boise, is the contractor on the $15 million project.

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

 

BOISE COUNTY

Near Banks Road & Bridge project

Work began April 11 on a bridge project on Idaho 55 near Banks. The work should be completed on the South Fork Payette River Bridge just prior to Memorial Day, and paving from Banks south to occur after the holiday weekend.

 

At milepost 78.7, the deck of the bridge will receive a silica fume treatment to prevent further corrosion and penetration by water and salts. Bridge rail also will be repaired and repainted.

 

Crews are removing the surface level of the bridge deck on the northbound side and are hoping to place a silica fume overlay on that portion later this week or early next. 

A pavement preservation project involves approximately 14 miles of roadway from just north of Horseshoe Bend at the Payette River Bridge north to about two miles north of the Idaho 55 and Banks-to-Lowman road intersection. About 1.8 inches of new pavement will be applied in a thin-lift paving procedure.

 

Workers are hydro-blasting (using high-pressure water to remove) damaged sections of the old deck off the Idaho 55 Payette River Bridge in preparation for repaving. The roadway is reduced to one lane with temporary traffic signals controlling the intersection. 

 

Traffic will be reduced to one lane with temporary signals at the Idaho 55 and Banks-to-Lowman intersection for the bridge repair. Once paving operations begin, traffic will be reduced to one lane. Pilot cars and flaggers will direct traffic.

 

Knife River Corp., of Boise, is the contractor on this $2.6 million project.

 

East of Boise - Mores Creek Bridge upgrade

A project to update the Mores Creek Bridge (commonly known as the High Bridge) on Idaho 21 east of Boise is under way.

 

During this work, the bridge deck and joints will be rehabilitated and the bridge parapet and railing replaced. Work on the foundation during the low-water winter period will include a retaining wall, rock anchoring, slope armoring, and seismic retrofit.  Portions of the structural steel will be painted along with other repairs on the structure.  

 

Traffic across the bridge is controlled by signals at either end, with only one direction allowed to pass through at a time. Under normal conditions, the delays are expected to be 15 to 45 minutes in length. In addition, a nine-foot width restriction will be in effect.

 

Crews have finished stabilization at the bridge foundation for this year. The water level rose sooner than normal, so crews will have to complete the foundation work during the next water draw-down period this fall, sometime after Labor Day. In the meantime, work will continue above water level. 

 

Crews are working on replacing rail and bolstering reinforcement at the pier. Traffic is still restricted to one lane in each direction, with a temporary signal to guide movement across the bridge.

 

RSCI, of Meridian, is the contractor on the $2.8 million project.

 

BOISE/VALLEY COUNTIES

A rockfall mitigation project from Banks north to Round Valley on Idaho 55 that was discontinued for the winter has resumed.

 

Loose rock will be removed from the rockfall zone to prevent it from falling onto the roadway. Work must be completed by the Memorial Day holiday.

 

Any resulting traffic delays are for the safety of the driving public and construction workers.

 

Last winter crews left off at milepost 82.7, but over the winter several slides occurred next to that spot.

 

Currently, rock scaling is occurring from milepost 99.4 to 100. The scaling and guttering material is hauled to a state-owned site at milepost 102.

 

The hours of operation are 7 a.m. to 6 p.m. Monday through Thursday, with some clean up occasionally on Fridays between 7 a.m. and noon.

 

They must be off the road by noon on Fridays and are prohibited from working on weekends to accommodate the tourism and recreational activities.

 

During working hours, the southbound lane of Idaho 55 is closed. Flaggers are stationed at each end of the work zone, with a set of advanced warning flaggers on hand to slow traffic down through the canyon. Expect traffic delays from 45 minutes to one hour because of blasting, scaling and guttering within a very tight work zone that requires additional time for blasting and maneuvering equipment.

 

There are three slopes within the work zone that are being scaled simultaneously. This minimizes the delay to the traffic while utilizing the equipment and manpower as efficiently as possible. Crews expect to continue in that same area for the next two weeks.

  

Hydro-seeding will take place the week after May 4 and all work will be done by May 23.

 

Once crews have finished the scaling, cleaning the gutter, and hydro-seeding, they will be moving to the next area at milepost 99.9 (south end of the Rainbow Bridge). ITD maintenance crews will be responsible to clean up any additional slide material as the contractor will have moved his equipment to another location.

 

Western Construction, of Boise, is the contractor on this $1.6 million project.

 

CANYON COUNTY

NAMPA - City traffic signal synchronization

Weather permitting, the Idaho Transportation Department will have flaggers guide traffic overnight on Tuesday and Wednesday (April 26 and 27) as part of a project under way since January that will link traffic signals to create a more efficient traffic flow in and around downtown Nampa. The project is on pace to be completed in June.

 

Flagging will be necessary at the intersection of 11th Avenue and 1st Street in all directions from 6:30 p.m. to 6:30 a.m. so crews can open a trench across 11th Avenue to install conduit for the new signal cabinet.  

 

The project will allow traffic signals to be synchronized through fiber optics and add pedestrian signals with countdown indicators at intersections. The signal improvements will mean people who drive the posted speed through the area should have fewer stops for red lights.

 

Crews are continuing to modify the signals at 2nd and 13th and 2nd and 14th to operate with the new equipment. The power to the signals at these intersections is shut off so the contractor can rewire them. The intersections are operating with stop signs on 13th and 14th avenues. 

 

Second Street has the right of way through the intersections. 

 

There are intermittent lane closures in the downtown area from 8:30 a.m. to 4 p.m. for equipment storage.

 

Construction crews will try to limit closures to sidewalks and parking stalls in the work areas. The contract does allow for lane closures if necessary, but only in work hours.

 

Quality Electric Inc., of Boise, is the construction contractor on this $1.01 million project. The city of Nampa paid for the design on this project and will pay a portion of the construction contract cost. No ITD funds are being expended on this off-system project. The funding breakdown is almost 93 percent Federal Aid and just over 7 percent Local funding. ITD is involved as a steward of the federal aid monies.

 

PAYETTE COUNTY
PAYETTE - U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is under way. It is expected to take about two years to complete, finishing in fall 2012.

Crews are replacing the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.


The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Traffic will utilize the southbound bridge while the new bridge is constructed. Traffic will then be switched to the new bridge while modifications to the southbound bridge are made and it is connected to the new bridge.

 

All piers are complete and bridge girders have been set. The cofferdams have been removed from the river. Diaphragms are being formed and placed between the girders.

 

Substructure work is complete. The cofferdams have been removed from the river. Diaphragms are complete on the south side and are being formed and poured on the north side of the new bridge. Deck formwork has been completed on the south side of the new bridge and has started on the north side.  The rebar mat is being constructed.  The first concrete deck pour on the south end of the new bridge is planned for the first week in May. Fill and roadwork activities are well under way north of the river.

 

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.

 

Questions? Visit us online at itd.idaho.gov, follow ITD on Twitter (IdahoITD) or Facebook and check travel conditions at 511.idaho.gov or dial 5-1-1. Please slow down in highway construction zones and pay attention. Safety for drivers and workers is our highest priority.

 
+