Southwest Idaho highway construction report for May 6-13

BOISE - The following projects are part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

 

BOISE - Interstate 84, Cole Road to Broadway Avenue widening
ITD is rebuilding and widening east- and westbound I-84 between the Cole and Broadway interchanges in Boise. When complete, the interstate will have four lanes in each direction.

 

Two additional westbound lanes opened Thursday morning between the Broadway and Cole interchanges. Click here for a map of the new westbound lanes. The new eastbound lanes are expected to open this summer.

 

Motorists should expect ongoing, intermittent east- and westbound I-84 lane restrictions between Cole/Overland and Broadway interchanges during the month of May. Restrictions will occur from 10 p.m. to 5 a.m. 


Concrete Placing Co. Inc., of Boise, is the contractor. This $35.9 million project is expected to be complete in summer 2011.


MERIDIAN - Interstate 84, Ten Mile Interchange construction

Construction of the new I-84, Ten Mile Interchange will continue until early summer. The new interchange will include additional lanes on Ten Mile Road and on- and off-ramps to I-84.

 

East- and westbound I-84 will be restricted to two lanes in both directions near the interchange on Sunday and Monday nights (May 8 and 9). The restrictions will be rescheduled in the case of inclement weather.

 

One lane of Ten Mile Road is open in both directions between Franklin and Overland. The speed limit is 25 mph. Ramps and the connection to I-84 will remain closed until the interchange is completed in early summer. Crews are still working on ramps, turn lanes, landscaping, lighting and signage.

 

Idaho Sand & Gravel, of Nampa, is the contractor on this $33.8 million project, which is expected to be complete in summer 2011.

 

The landscaping, under a separate $580,000 contract to Franz Witte Landscape Contracting, is under way.

 

ITD is doing the initial Ten Mile landscaping. Once the landscaping project is finished in late July, the day-to-day maintenance of that landscaping system reverts to the city of Meridian.

 

The landscapers have finished most of the mainline and lateral piping on the interstate sides of the on- and off-ramps. Next week crews will focus their work on the SPUI ramp islands. Next weeks work will include the pouring of the concrete mowing strip, lateral irrigation lines, and placement of topsoil.

 

I-84 widening, Franklin to Garrity

On the project to widen Interstate 84 between the Franklin Boulevard and Garrity Boulevard interchanges in Nampa, traffic has shifted to the paved concrete median while crews construct the outside travel lanes.

 

Motorists can expect ongoing, intermittent nighttime lane closures for both east- and westbound traffic as crews work to complete the project by early summer 2012. All I-84 lanes remain open during the day.

 

The Garrity eastbound off-ramp is being paved now, and the Garrity westbound on-ramp will be paved later in May. On the Franklin eastbound on-ramp, concrete paving is anticipated next week. The Franklin westbound off-ramp will be done in two parts the first half at the end of this week or early next week, with the other half anticipated in mid-May.

 

Bridge girders will be set on the Union Pacific Railroad (UPRR) bridge eastbound overnight May 18-19, and crews will begin installing metal decking in late May or early June.

 

Construction of two new bridges over the UPRR and Phyllis Canal will accommodate the additional lanes on I-84.  

 

Concrete Placing Company, of Boise, is the contractor on this $22.2 million project. 

 

Once these interstate improvements are complete, I-84 between Franklin and Garrity will be widened to three lanes in each direction, with an additional auxiliary lane for eastbound traffic. The auxiliary lane will allow motorists to enter I-84 at Franklin, remain in the lane farthest right, and exit at Garrity - never having to merge with interstate traffic.

 

NAMPA - Interstate 84, Garrity Interchange Bridge reconstruction

Construction on the I-84 Garrity Interchange improvement project continues. The project replaces two bridges on I-84 at the Garrity Interchange with a single bridge to accommodate three lanes in each direction on the interstate.

 

Work also includes reconstructing the interstate about a mile east of the interchange to tie into the widening of I-84 between the Garrity and Meridian interchanges, and removing the bridge piers in the roadway at Garrity Boulevard.

 

Motorists can expect additional congestion around the westbound Garrity off-ramp for sidewalk construction. Sidewalks will be built on both sides of Garrity beneath I-84, but pedestrian crossings will only be installed on the east side of Garrity to match up with existing sidewalks and crossing signals. The sidewalk work should take a few weeks to complete, depending on weather conditions.

 

In the future, the city of Nampa may improve the sidewalk being built on the west side by installing pedestrian crossings and signals.

 

A ramp closure is upcoming in late May or early June.

 

Traffic on Garrity Boulevard will be shifted around into different configurations during daytime hours as crews work underneath the bridge. Two southbound and one northbound lane will remain open.

 

This project is part of ITD's plans to improve I-84 between the Franklin and Garrity interchanges in Nampa.

 

The completed improvements will include three lanes in each direction from the Franklin to Garrity interchanges, and eventually four lanes in each direction from the Garrity to Meridian interchanges.

 

The entire project is being constructed in three stages:

 

COMPLETED

Step 1 - Build the median section of the bridge between the existing bridges. Traffic will remain on existing bridges, with two lanes open in each direction.

Step 2 - Remove the existing westbound bridge and build a new westbound portion of bridge. Westbound traffic will be moved onto the new median section. Two lanes will remain open in each direction.

CURRENTLY UNDER WAY

Step 3 - Remove the existing eastbound bridge and build a new eastbound portion of bridge. Westbound traffic will be shifted onto the new westbound portion of the bridge, and eastbound traffic onto the median section.

Completion - By summer 2011, three lanes will be open in each direction over the bridge, eventually connecting with a fourth lane in each direction east of the interchange.

 

Concrete Placing Co. Inc., of Boise, is the contractor on the $15 million project.

 

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

 

BOISE COUNTY

Near Banks Road & Bridge project

Work began April 11 on a bridge project on Idaho 55 near Banks. The work should be completed on the South Fork Payette River Bridge just prior to Memorial Day, and paving from Banks south to occur after the holiday weekend.

 

At milepost 78.7, the deck of the bridge will receive a silica fume treatment to prevent further corrosion and penetration by water and salts. Bridge rail also will be repaired and repainted.

 

The northbound side of the bridge has been overlaid with a new deck surface. Traffic will be switched Sunday (May 1) onto the new surface and work will begin on the southbound side. 

A pavement preservation project involves approximately 14 miles of roadway from just north of Horseshoe Bend at the Payette River Bridge north to about two miles north of the Idaho 55 and Banks-to-Lowman road intersection. About 1.8 inches of new pavement will be applied in a thin-lift paving procedure.

Work is complete on the east side of the bridge, and the contractor is now working on the west side. Traffic has been reduced to one lane, with temporary signals controlling traffic.  Bridge work is scheduled to be completed by May 26, with paving from the bridge south to milepost 81 to begin after Memorial Day weekend.

 

Once paving operations begin, traffic will be reduced to one lane. Pilot cars and flaggers will direct traffic.

 

Knife River Corp., of Boise, is the contractor on this $2.6 million project.

 

East of Boise - Mores Creek Bridge upgrade

A project to update the Mores Creek Bridge (commonly known as the High Bridge) on Idaho 21 east of Boise is under way.

 

During this work, the bridge deck and joints will be rehabilitated and the bridge parapet and railing replaced. Work on the foundation during the low-water winter period will include a retaining wall, rock anchoring, slope armoring, and seismic retrofit.  Portions of the structural steel will be painted along with other repairs on the structure.  

 

Traffic across the bridge is controlled by signals at either end, with only one direction allowed to pass through at a time. Under normal conditions, the delays are expected to be 15 to 45 minutes in length. In addition, a nine-foot width restriction will be in effect.

 

Crews have finished stabilization at the bridge foundation for this year. The water level rose sooner than normal, so crews will have to complete the foundation work during the next water draw-down period this fall, sometime after Labor Day. In the meantime, work will continue above water level. 

 

Crew are working underneath the bridge on the piers for seismic reinforcement, and are moving and replacing the bridge railing on the east side. Traffic remains in a one-lane configuration. 

 

Although the number of boats and RVs is increasing, no problems have been reported.

 

RSCI, of Meridian, is the contractor on the $2.8 million project.

 

BOISE/VALLEY COUNTIES

A rockfall mitigation project from Banks north to Round Valley on Idaho 55 that was discontinued for the winter will be finished shortly.

 

Thursday (May 5) was the contractors last day of working on the highway with heavy equipment. Crews will be hydro-seeding (spreading seed with a water cannon) next week, which will involve minimal traffic control using flaggers. The resulting vegetation, when grown, will help reduce erosion and future slides.

 

The hours of operation are 7 a.m. to 6 p.m. Monday through Thursday, with some clean up occasionally on Fridays between 7 a.m. and noon.

 

They must be off the road by noon on Fridays and are prohibited from working on weekends to accommodate the tourism and recreational activities.

 

Western Construction, of Boise, is the contractor on this $1.6 million project.

 

CANYON COUNTY

NAMPA City traffic signal synchronization

A project has been under way since January to link traffic signals, creating a more efficient traffic flow in and around downtown Nampa.

 

The project will allow traffic signals to be synchronized through fiber optics and add pedestrian signals with countdown indicators at intersections. The signal improvements will mean people who drive the posted speed through the area should have fewer stops for red lights.

 

The contractor has completed work on eight of the 12 signal cabinets.  Next week, the contractor will begin work on replacing the signal at 12th Avenue and 2nd Street. They will also replace signal cabinets at 12th and 7th, and 16th and 3rd using flaggers at the intersections to direct traffic.

 

The work is expected to finish in July.

 

Construction crews will try to limit closures to sidewalks and parking stalls in the work areas. The contract does allow for lane closures if necessary, but only in work hours.

 

Quality Electric Inc., of Boise, is the construction contractor on this $1.01 million project. The city of Nampa paid for the design on this project and will pay a portion of the construction contract cost. No ITD funds are being expended on this off-system project. The funding breakdown is almost 93 percent Federal Aid and just over 7 percent Local funding. ITD is involved as a steward of the federal aid monies.

 

OWYHEE COUNTY

SW of MARSING U.S. 95 resurfacing

 

Approximately 17 miles of rural, two-lane U.S. 95, from the Idaho/Oregon border northeast into Owyhee County, will be repaved. The project is anticipated to extend into mid-July.
 
Drivers can expect intermittent lane closures and pilot cars will guide motorists during the work. The speed limit in the work zone will be reduced to 45 mph, and work hours are 7 a.m. to 5 p.m. Monday through Friday, with no work anticipated on the weekends unless necessary.

The first seven miles of the project will be done using the CRABS (Cement Recycled Asphalt Base Stabilization) process. The remainder of the project will require an overlay with a SALSA (Stress Absorbing Straight Layer of Asphalt).
 
CRABS involves grinding the existing roadway down to the gravel base, then adding cement to the old asphalt. This process extends the life of the roadway. SALSA is a process which involves shooting a layer of straight asphalt on the pavement and then applying a thin coat of chips. The SALSA process also includes an overlay of plant mix, which is a blend of asphalt and crushed rocks.
 
Idaho Sand & Gravel Co., of Nampa, is the contractor on this $4.9 million project.

 

PAYETTE COUNTY
PAYETTE U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is under way. It is expected to take about two years to complete, finishing in summer 2012.

Crews are replacing the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts as the current one does and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Traffic will utilize the southbound bridge while the new bridge is constructed. Traffic will then be switched to the new bridge while modifications to the southbound bridge are made and it is connected to the new bridge.

 

All piers are complete and bridge girders have been set. The cofferdams have been removed from the river. Diaphragms are being formed and placed between the girders.

 

Substructure work is complete. The cofferdams have been removed from the river. Diaphragms are complete on the south side and are being formed and poured on the north side of the new bridge. Deck formwork has been completed on the south side of the new bridge and has started on the north side. The rebar mat is being constructed. The first concrete deck pour on the south end of the new bridge is planned for the first week in May. Fill and roadwork activities are well under way north of the river.

 

Diaphragms (a structural system used to transfer lateral loads or resist lateral forces) are complete on the south side of the bridge and are being formed and poured on the north side. Deck formwork has been completed on the south side of the new bridge and has progressed to the fifth span. The first concrete deck pour on the south end of the new bridge is planned for the second week in May. Fill and roadwork activities are well under way, north of the river. The road has been brought up to subgrade. On the south side, obliteration of the old road has started.

 

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.

 