Southwest Idaho highway construction report for March 23-30

BOISE - The following project is part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.

ADA COUNTY
Idaho 16 Extension

Bids from potential contractors will be opened on April 3 for the first phase of the extension of Idaho 16. Crews will connect State Street to Chinden Boulevard, including a new bridge over the Boise River.

Following is an update on non-GARVEE state highway construction projects in southwest Idaho.

BOISE COUNTY
EAST OF BOISE - Mores Creek Bridge upgrade

The bridge has reopened to two lanes, with the width restriction removed, and the speed limit returned to 55 mph.

Crews will need to return to the bridge briefly in the spring to complete minor work, but this work will be performed under periodic lane closures. No signals will be necessary.

RSCI, of Meridian, is the contractor on the $2.8 million project.

BOISE COUNTY
NEAR LOWMAN – Fish-passage project

On the fish-passage project east of Lowman, the bridge has been reopened to traffic and the speed limit returned to 55 mph. The contractor will return in the spring to re-seed the work area and resume approach work.

This project is being funded through the U.S. Forest Service.

Cannon Builders Inc., of Blackfoot, is the contractor on this $1.2 million project.

PAYETTE COUNTY
FRUITLAND – U.S. 95/I-84 Exit 3 Overpass repair

Work began on Monday to resurface and repair the half-century-old U.S. 95 interchange overpass spanning I-84 at Exit 3 near Fruitland. Work is expected to finish in June.

The bridge deck and foundation for this bridge are considered to be in fair condition, with the superstructure in good condition.

The concrete deck will be overlayed and pier caps and columns patched in this project to extend the life of the bridge, built in 1960. The bridge railing will also be replaced.

Asphalt paving work will be performed to tie the bridge approaches into the road on each end of the bridge.

The normal lane, shoulders, and center lane are reduced slightly and allow passage of 14-foot vehicle and cargo widths.

Crews are performing a hydroblast deck removal in the center lane of the bridge.

Cannon Builders Inc., of Blackfoot, is the contractor for this $763,000 project.

PAYETTE COUNTY
PAYETTE – U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is under way. It is expected to finish in September 2012.

Crews are replacing the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts, as the current one does, and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

Crews continue removing concrete bridge deck, and on patching the leak in the concrete irrigation line that runs under U.S. 95.

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.

 
 
+