Southwest Idaho highway construction report for March 30-April 6
BOISE - The following project is part of the GARVEE Transportation Program in southwest Idaho, which uses funds from Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite highway projects.
ADA COUNTY
BOISE – Idaho 16 extension, Boise River crossing
Bids from potential contractors will be opened in April for the first phase of the extension of Idaho 16. Crews will connect State Street to Chinden Boulevard, including a new bridge over the Boise River.
Following is an update on non-GARVEE state highway construction projects in southwest Idaho.
ADA COUNTY
MERIDIAN - Eagle Road resurfacing and medians
Bids from potential contractors will be opened in April for this project, which will resurface Idaho 55 from Fairview Avenue in Meridian to State Street in Eagle, and install raised medians from Franklin to Oakhampton Drive, one half-mile north of Chinden.
BOISE COUNTY
EAST OF BOISE - Mores Creek Bridge upgrade
The bridge has reopened to two lanes, with the width restriction removed, and the speed limit returned to 55 mph.
Crews will need to return to the bridge briefly in the spring to complete minor work, but this work will be performed under periodic lane closures. No signals will be necessary.
RSCI, of Meridian, is the contractor on the $2.8 million project.
BOISE COUNTY
NEAR LOWMAN – Fish-passage project
On the fish-passage project east of Lowman, the bridge has been reopened to traffic and the speed limit returned to 55 mph.
The contractor will return in the spring to re-seed the work area and resume approach work.
This project is being funded through the U.S. Forest Service.
Cannon Builders Inc., of Blackfoot, is the contractor on this $1.2 million project.
PAYETTE COUNTY
U.S. 95 Parma-Wilder resurfacing
Crews will repair a leaking pipe under a stretch of U.S. 95 today (Friday, March 30) in preparation for upcoming resurfacing.
The length of pipe to be replaced is approximately 60 feet long and buried eight feet under the highway, about four miles south of Exit 3 in Payette County.
During this one-day pipe repair, the two-lane road will be reduced to one lane, with flaggers controlling traffic. When the pipe work is completed that day, the road will be re-opened to unrestricted travel.
A stretch of U.S. 95 from the south city limits of Wilder to the south city limits of Parma, and from the north side of Parma to the junction with Interstate 84 will be resurfaced in a project starting in May.
In all, about 23 miles of the route will be resurfaced, repaired and widened in areas during the three-month project.
• 13.2 miles of U.S. 95, from Parma north city limits to Jct. I-84
• 1.6 miles of U.S. 20/26, from Snake River Bridge to Jct. U.S. 95
• 8.2 miles of U.S. 95, from Wilder south city limits to Parma south city limits
In two-lane sections, at least one lane will remain open at all times. In three- or four-lane segments, at least two lanes will remain open.??Work on nights or weekends is not expected, but is not prohibited if needed.
Idaho Sand & Gravel Co., of Nampa, is the contractor on this $5.7 million project.
PAYETTE COUNTY
FRUITLAND – U.S. 95/I-84 Exit 3 Overpass repair
Work is under way to resurface and repair the half-century-old U.S. 95 interchange overpass spanning I-84 at Exit 3 near Fruitland. The project is expected to finish in June.
The bridge deck and foundation for this bridge are considered to be in fair condition, with the superstructure in good condition.
The concrete deck will be overlayed and pier caps and columns patched in this project to extend the life of the bridge, built in 1960. The bridge railing will also be replaced.
Asphalt paving work will be performed to tie the bridge approaches into the road on each end of the bridge.
The normal lane, shoulders, and center lane are reduced slightly and allow passage of 14-foot vehicle and cargo widths.
A hydroblast (high-pressure water) deck removal in the center lane of the bridge is nearly finished. Work to repair cracked and spalled concrete on the piers columns and girders has begun.
Cannon Builders Inc., of Blackfoot, is the contractor for this $763,000 project.
PAYETTE COUNTY
PAYETTE – U.S. 95, Payette River Bridge replacement
The project to improve the U.S. 95 bridge over the Payette River south of Payette is under way. It is expected to finish in September 2012.
Crews are replacing the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette. The new bridge will be two feet higher off the water. It will have no overhead bracing or struts, as the current one does, and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.
The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.
U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.
Crews continue removing the concrete bridge deck, and have patched the leak in the concrete irrigation line under U.S. 95. Steel for the new deck has been delivered and crews will start tying rebar on the south side of the deck next week.
JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.