Southwest Idaho highway construction report for June 8-15

BOISE - The following projects in southwest Idaho are now under way or will begin soon.

ADA COUNTY

BOISE - Idaho 16 Extension

Work has started Tuesday for the first phase of the extension of Idaho 16. Initially, crews installed fence to keep domestic animals and wildlife out of the project area, and will work to build access roads – that work is constrained by migratory birds and raptors. They are also performing weed control. There will initially be no traffic interference.

Crews will connect State Street to Chinden Boulevard, including a new bridge over the Boise River. In the meantime, the contractor is working to install temporary fencing around the work site.

Concrete Placing Co. Inc., of Boise, is the contractor on this $19.4 million project.

ADA COUNTY

MERIDIAN - Eagle Road resurfacing and medians

Work will start Sunday night (June 10) on this project, which will resurface Idaho 55 from Fairview Avenue in Meridian to State Street in Eagle, and install raised medians from Franklin to Oakhampton Drive, one-half mile north of Chinden Boulevard.

Crews will initially be grinding off the pavement surface in a short segment between Fairview Avenue and River Valley Street (where the new traffic light was installed in late April). Crews will also begin preparing to install raised medians between Franklin Road and River Valley Street.

The work will take place overnight between 9 p.m. and 5 a.m. Access to businesses and residences will be kept open except for brief closures when crews are paving right at those approaches or driveways.

Idaho Sand & Gravel Co., of Nampa, is the contractor on this $4.7 million project.

ADA, ELMORE COUNTY

Repair of seven bridge decks in Ada and Elmore counties

The bridge decks on seven bridges from Boise through Mountain Home and to the east will be repaired and resurfaced in a six-month project that began in early May.

Lane restrictions of 12 feet over the 18th Street overpass will remain in effect until work is completed on the structure.

The 18th Street overpass should be done by June 20.

Currently all lane closures on I-84 for work activity will be during daylight hours only.

The bridges, their ages and the work is detailed below:

•  The east- and westbound U.S. 20 Interchange at Exit 95 (1971) – This work involves removing and replacing the deck concrete, replacing expansion joints, and injecting filler in cracks in the abutments and wing walls.

• The East Mountain Home/Oregon Trail Interchange at milepost 99 (1972) - This work involves removing and replacing concrete, replacing expansion joints, and injecting filler in cracks in the piers and wing walls.

• The Eisenman Interchange bridge at Exit 60 (1997) – The bridge deck will receive an epoxy overlay (deck seal).

• The Mayfield Interchange bridge east of Boise at Exit 71 (1960) – This work involves removing and replacing the deck concrete, replacing bearing pads on the piers and replacing the expansion joints.

• The Canyon Creek underpass in Mountain Home at milepost 92 (1971) – This work involves removing and replacing the deck concrete and replacing expansion joints.

•  The 18th Street underpass in Mountain Home at milepost 94 (1971) – This work involves removing and replacing the deck concrete, replacing expansion joints, and injecting filler in the cracks in pier walls.

•  The Hammett Interchange bridge at milepost 112 (1973) – This work involves removing and replacing concrete, replacing expansion joints, and injecting filler in cracks in the piers and wing walls.

Concrete Placing Co. Inc., of Boise, is the apparent low bidder on the $1.72 million repairs.

BOISE COUNTY

NEAR LOWMAN - Fish-passage project

On the fish-passage project east of Lowman, the bridge has been reopened to traffic and the speed limit returned to 55 mph. Crews have completed all work except returning in the fall to plant willows.

This project is being funded through the U.S. Forest Service.

Cannon Builders Inc., of Blackfoot, is the contractor on this $1.2 million project.

CANYON COUNTY

U.S. 95 Parma-Wilder resurfacing

A stretch of U.S. 95 from the south city limits of Wilder to the south city limits of Parma, and from the north side of Parma to the junction with Interstate 84 will be resurfaced in a project now under way.

In all, about 23 miles of the route will be resurfaced and repaired in areas during the three-month project. It will begin with the segment listed first, below:

• 8.2 miles of U.S. 95, from Wilder south city limits to Parma south city limits 
Paving within Wilder has been completed.

This will be followed by a section of work expected to be constructed starting in mid-July 2012, and finishing in mid-August.

• 13.2 miles of U.S. 95, from Parma north city limits to Jct. I-84
• 1.6 miles of U.S. 20/26, from Snake River Bridge to Jct. U.S. 95

In two-lane sections, at least one lane will remain open at all times. In three- or four-lane segments, at least two lanes will remain open.

Work on nights or weekends is not expected, but is not prohibited if needed.

Idaho Sand & Gravel Co., of Nampa, is the contractor on this $5.7 million project.

ELMORE COUNTY

I-84 repair Mountain Home to Hammett

A 25-mile pavement maintenance and repair project on Interstate 84 from Mountain Home east to Hammett is now under way. The project is expected to finish by the July Fourth holiday.

Crews are working a Monday-Friday schedule unless Saturday work is needed to stay on schedule.??The project, on both sides of the highway, involves the replacement of several joint seals, extensive crack sealing and the replacement of deteriorated concrete slabs. It also involves the application of sealant to highway shoulders to protect the surface against weather and water damage and prevent additional cracking.

Typically one lane will be closed in the immediate project area, which will be limited to about a half-mile at a time. In some areas of slab replacement, lanes will remain closed longer. The lane closures will vary in length based on the contractor’s progress.

A 14-foot width restriction will be in place when work is in the travel lanes. With advanced notice to the project inspector via ITD's Ports of Entry, wider loads of up to 16 feet may be able to pass through.

During daylight hours when workers are present and lane closures are in effect, the speed limit will be reduced to 45 mph. During other construction times, the speed limit will be 65 mph. The posted speed will return to 75 mph when work is not being conducted (nights and weekends).

A-Core of Idaho, of Boise, is the contractor on the $2.54 million project.

GEM COUNTY

EMMETT - Idaho 16, SH 44 to Substation Road

A road, bridge and guardrail-repair project for a 12.5–mile stretch of Idaho 16 from just north of its junction with Idaho 44 to Emmett’s Substation Road is under way. The project is expected to finish in late July.

Crews will work an overnight, 7:30 p.m. to 6 a.m. schedule, beginning in the northbound lane on the south end of the project. The contractor plans to work Monday through Thursday nights on paving, with some non-paving work occurring during the day (8:30 a.m. and 4 p.m.) as necessary.

Paving work was limited this week by inclement weather. Paving will continue, weather permitting, through Tuesday (June 12).

Traffic will follow pilot cars through the work zone with expected delays of up to 15 minutes. As work is completed, the contractor will reduce the overall length of the work zone behind them.

This pavement overlay will be divided into a trio of work-zone segments, each four miles long. Once work begins in the first segment, it must be completely finished and reopened to traffic before the contractor can move on to the next segment. Aside from morning and evening rush-hour commutes, traffic will be limited to one lane, with a speed-limit reduction. The speed limit will be reduced by 10 mph in the work-zone segment.

The section of road was built in 1959 and 1966. An overlay was performed in 1996 on the first nine miles, followed by a CRABS (Cement Recycled Asphalt Base Stabilization) resurfacing project in 1998 on the northern end.

When crews transition to repair work on the Black Canyon Irrigation Canal bridge, a lane closure will be required for 13 calendar days, with a temporary signal used to guide traffic.

Work on the bridge, located at approximately milepost 12, will include waterproofing, sealing and replacing joints, and removing and replacing portions of the concrete deck. Approaches to the bridge and transitions to surrounding roads will be adjusted to match the new grade of the road. Crews also are replacing 8,500 feet of substandard guardrail throughout the project.

Central Paving Co. Inc., of Boise, is the contractor on this $2.5 million project.

PAYETTE COUNTY

FRUITLAND – U.S. 95/I-84 Exit 3 Overpass repair

Work is under way to resurface and repair the half-century-old U.S. 95 interchange overpass spanning I-84 at Exit 3 near Fruitland. The project is expected to finish in June.

The bridge deck and foundation for this bridge are considered to be in fair condition, with the superstructure in good condition.

The concrete deck will be overlayed and pier caps and columns patched in this project to extend the life of the bridge, built in 1960. The bridge railing will also be replaced.

Asphalt paving work will be performed to tie the bridge approaches into the road on each end of the bridge.

Hydro-demolition work has been completed for the second lane of the structure. The lane is now being prepared for the new overlay by removing old expansion joints and concrete. Patching also continues on the piers and pier caps.

The normal lane, shoulders, and center lane are reduced slightly and allow passage of 14-foot vehicle and cargo widths.

Cannon Builders Inc., of Blackfoot, is the contractor for this $763,000 project.

PAYETTE COUNTY

PAYETTE – U.S. 95, Payette River Bridge replacement

The project to improve the U.S. 95 bridge over the Payette River south of Payette is under way. It is expected to finish in mid-September 2012.

Crews are replacing the existing northbound truss bridge (built in 1927) located on U.S. 95 between Fruitland and Payette.

The new bridge will be two feet higher off the water. It will have no overhead bracing or struts, as the current one does, and will be 84 feet in width, eliminating current safety concerns regarding both width and height restrictions.

The new bridge will be constructed next to, and will attach to, the existing southbound bridge. The project also includes minor roadway realignment to tie into the new bridge location.

U.S. 95 is the main route connecting northern and southern Idaho. About 18,000 vehicles use this portion of the highway daily. By 2026, the volume is expected to be more than 25,000.

The entire new bridge should be there by the end of this month, with a few months of work remaining before the bridge is set to reopen in early fall.

JC Constructors Inc., of Meridian, is the contractor for this $6.17 million project.

 
+