Repair of Zimmer Creek culvert for runoff control begins March 11

BOISE - The 2012 Springs Fire in southwest Idaho consumed more than 6,150 acres, and the negative affects are still being felt. The latest concession to the fire is the lack of runoff control now that all of the underbrush and vegetation has been burned off in the area.

With the ground thawing sufficiently to allow repairs, a pipe culvert at Zimmer Creek on Idaho 55 about two miles north of Banks will be cleaned out starting March 11 by the Idaho Transportation Department (ITD). The Forest Service and ITD predict significantly more runoff this spring due to loss of ground cover that would prevent erosion.

The work is expected to finish in three to four weeks.

Click here for picture of pipe.

The pipe has been in place for decades, and at some point a landslide clogged more than half of it, restricting the amount of flow it can handle. ITD’s maintenance forces attempted to clean it out last fall using equipment, but much of the debris in the 48-inch diameter pipe was too large and bulky to be moved. A professional contractor will clean out the pipe, likely by hand, with someone inside the pipe pulling out boulders, branches and other debris.

"ITD’s goal is to have the pipe cleaned out by spring runoff in hopes of preventing damage to the road due to floodwaters running over or undermining the highway," said Southwest Idaho Maintenance Manager Tom Points. 

Click here for Points' sound bite.

Pipeline Inspection Services, of Nampa, will complete the $29,000 work.

“The contractor is using innovative and outside-the-box thinking in approaching the work," said Project
Manager Amanda LaMott. "It looks like ITD could save significant money on this work, which should wrap up in about a month.”