UPDATE: Resurfacing of I-90, Idaho 41/54 junction to begin Aug. 5

COEUR d'ALENE - Idaho Transportation Department crews will pave a stretch of Interstate 90 near Coeur d’Alene and the junction of Idaho 41/54 starting Aug. 5.

ITD crews from the Coeur d’Alene maintenance sheds will work overnight from 7 p.m. to 5 a.m. to complete needed paving in those areas.

Drivers are asked to watch for flaggers and signs. ITD will use electronic signs on the freeway, portable signs on the roadside shoulders and truck-mounted signs to alert motorists to the work.

All ramp closures will start around 8 p.m.

Here is a schedule for the project:

August 5 and 6: Paving the Idaho 41/54 junction and the north and south through lanes to Rhode Island.
 
August 7: Crews will be paving Exit 11 on ramp Eastbound this ramp will be closed traffic will need to use Appleway or Ironwood to US 95 on ramp Eastbound.
 
August 8: Paving on the Exit 7 eastbound off-ramp will close half the ramp.
 
August 12: Work on the Exit 7 eastbound on-ramp will close the ramp. Traffic must use the Exit 6 eastbound on-ramp.
 
August 13: Work on the Northwest Boulevard overhead near the eastbound on-ramp, moving to milepost 12 on I-90 and to the Exit 13 off-ramp/4th Street. The ramp will be closed and traffic will need to use the Exit 12 off-ramp or Exit 15 off-ramp.
 
August 14: Working on I-90 from milepost 13 westbound near the 4th street off-ramp. The ramp will be closed at night traffic will need to use Exit 12.
 
August 15: Paving U.S. 95 from Ironwood to Northwest Boulevard southbound.

           
 
+