10/31/2014






Southwest Idaho highway construction report for Oct. 31-Nov. 7

ADA COUNTY
Meridian, Broadway and Gowen interchange reconstructions (GARVEE)

I-84, Broadway Avenue Interchange

As of October 31, motorists will use the newly completed westbound on-ramp to enter I-84 from Broadway Avenue. In addition, traffic on Broadway Avenue will be shifted to the east.

With the new I-84 westbound on-ramp open, crews will begin removing the existing soundwall along the old ramp. Panels removed from this wall will be reused to build a new soundwall.

For more information on this project, please see the project website at: http://apps.itd.idaho.gov/apps/broadwayinterchange/default.html

I-84, Gowen Road Interchange
During the next week, I-84 traffic will be shifted into new configurations everyday as crews work to remove the crossover traffic pattern on eastbound I-84 between the Eisenman and Gowen interchanges. After this work is complete, I-84 near the Gowen Interchange will have one lane open on the eastbound side of the interstate and one lane open on the westbound side.

The crossover pattern was put in place several months ago so crews could construct improvements on the eastbound side of the Gowen Interchange. Work accomplished over the summer included tearing down and rebuilding the I-84 eastbound bridge over Gowen Road, widening the I-84 railroad bridge, and constructing the new eastbound on- and off-ramps.

Traffic will be shifted onto the new permanent eastbound off-ramp early next week.

For more information on this project, please see the project website at: http://apps.itd.idaho.gov/apps/goweninterchange/default.html

I-84, Meridian Road Interchange
Crews have removed the old Meridian Interchange bridge and will work over the next several months to build the east half of the new bridge. Crews will also begin rebuilding the east half of Meridian Road between Overland Road and the interstate ramps. Traffic on Meridian Road has been shifted to the west half of the new bridge.

Click here to see a video of the bridge demolition. 

For more information on this project, please see the project website at: http://apps.itd.idaho.gov/apps/meridianinterchange/default.html

VALLEY COUNTY

McCALL – Lardo Bridge Replacement

The bridge closed Oct. 15 and the new bridge was slid into place Monday (Oct. 27) using a unique lateral slide construction method. The method reduces a full closure of the bridge by months.

The construction/design contract is for $3.64 million.

For more information on this project, please see the project website at: http://itd.idaho.gov/Projects/D3/ID55LardoBridge/default.html

WASHINGTON COUNTY

PAYETTE - Idaho 52 railroad overpass replacement

Lead-based paint removal, rail-repair work and painting are now complete. Striping and water-proofing will begin next week. Work continues on deck rehab. Deck rehabilitation and superstructure crack repair is expected prior to the project finishing in mid-November.

Braun-Jensen Inc., of Payette, is the contractor on this $1.3 million project.

 
+