11/21/2014
Southwest Idaho highway construction report for Nov. 21-28
BOISE - Crews do not
anticipate working on Thursday, Nov. 27. Activities this week are weather
dependent.
I-84, Broadway Avenue Interchange
Crews continue to place soundwall panels along the
westbound on-ramp and continue to excavate the stormwater drainage area behind
the soundwall.
For more information on this project, please see the project website at:
http://apps.itd.idaho.gov/apps/broadwayinterchange/default.html
I-84, Gowen Road
Interchange
Lane restrictions on east- and westbound I-84 remain in place. When weather
allows, crews will restripe the roadway and ramps and open the interstate back up to two
lanes in each direction.
For more information on this project, please see the project website at: http://apps.itd.idaho.gov/apps/goweninterchange/default.html
I-84, Meridian Road Interchange
Crews are currently constructing bridge piers,
columns and walls on the east half of the bridge. Crews are beginning to install
new signal foundations at the northeast and northwest corners of the intersection of Meridian
and Overland roads. Ultimately the existing signal poles will be
replaced with new, relocated poles to accommodate the widening of Meridian
Road.
For more information on this project, please see the project website at: http://apps.itd.idaho.gov/apps/meridianinterchange/default.html
WASHINGTON COUNTY
PAYETTE - Idaho 52 railroad overpass replacement
Weather conditions have delayed striping pavement. The project is expected to wrap up later this month.
Braun-Jensen Inc., of Payette, is the contractor on this $1.3 million project.
VALLEY COUNTY
McCALL – Lardo Bridge Replacement
The bridge closed Oct. 15 and the new bridge was slid into place Oct. 27 using a unique lateral slide construction method. The new bridge is scheduled to open Nov. 26
The construction/design contract is for $3.64 million.
For more information on this project, please see the project website at:http://itd.idaho.gov/Projects/D3/ID55LardoBridge/default.html