3/6/2020
Megan Jahns
ITD Communication
208-772-1295
megan.jahns@itd.idaho.gov
Rock removal to begin next week on US-95 at Winchester Hill
LEWISTON—The final season of work on a two-year project to
extend the southbound passing lane on US-95 near Winchester another 2.5 miles has begun. It is expected to finish in November.
The first road closure to accomodate blasting activities for rock removal is planned for March 12 from 6 p.m. to 7 p.m.
View a photo of pre-blasting work.
Blasting is scheduled to avoid peak commute times or weekends and is expected to last for an hour at a time. Drivers should heed digital signs in the area or visit 511.idaho.gov to avoid closures.
Other construction activities will require reduced speeds in the work zone, with crews expected on site during the day from around 6 a.m. to 6 p.m. and at nights when needed. No work is expected on weekends at this time.
Last year, blasting made room for 1.5 miles of passing lane to be added in the narrow canyon, and this year that surface will be paved. Of the nine aging culverts in this section, four still need to be upgraded to allow for fish passage.